Deedo IDDL-NSK-NASHIK7 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.
RERA projects4,204in 103 localities
Registrations4,255some projects hold several
Completion still due1,3062,580 past their date
Median extension4 months30% of registrations extended
Regulatory cases227on 198 projects
7 in 10 registrations run late here
4,255 MahaRERA registrations in Nashik and the places within it
376 completed410 not yet due887 extended, not yet due2,213 past even the latest date369 no date on record
Extended registrations moved their completion date by a median of 4 months.
Projects in Nashik
4,204 projects registered with MahaRERA in this district and the places within it.
| Project | Delivery | Median ₹/sq ft | Booked |
|---|---|---|---|
| C Square Complex | No date on record | — | — |
| Damayanti Heights | No date on record | — | — |
| Deacon Residency | No date on record | — | — |
| Deeplaxmi Plaza | No date on record | — | — |
| Devrenu Heights | No date on record | — | — |
| Devs Laxmi ApartmentLaxmi Buildcon | No date on record | — | — |
| Dhanashree Empire | No date on record | — | — |
| Dhruvatara A Wing | No date on record | — | — |
| Dhruvatara B Wing | No date on record | — | — |
| Diamond Residency | No date on record | — | — |
| Divya Row HousesRaju Manikrao Jagtap | No date on record | — | — |
| Divya Swapna Apartment | No date on record | — | — |
| Dnyaneshwari Apartment | No date on record | — | — |
| Dnyanyog Apartment | No date on record | — | — |
| Dream AuraAjaz Janamuddin Siddiqui | No date on record | — | — |
| Dream CentralAjaz Janamuddin Siddiqui | No date on record | — | — |
| Dream Heights | No date on record | — | — |
| Durvankur AnnexJay Amrutbhai Sanghani | No date on record | — | — |
| Durvankur EnclaveJay Amrutbhai Sanghani | No date on record | — | — |
| Durvankur GalaxyKanhaiya Infrastructure | No date on record | — | — |
| Durvankur HeightsJay Amrutbhai Sanghani | No date on record | — | — |
| Durvankur RegencyNarendra Asaram Jadhav | No date on record | — | — |
| Eandg Green Court | No date on record | — | — |
| F K PrideVishwas Infra | No date on record | — | — |
| F K Tower | No date on record | — | — |
Localities in Nashik
- Nashik1,372 projects
- Nashik (M Corp.)1,251 projects
- Nashik303 projects
- Aanandwali94 projects
- Deolaligaon67 projects
- Nashik Road67 projects
- Satpur56 projects
- Jail Road55 projects
- Deolali (Cb)50 projects
- Makhmalabad45 projects
- Pathardi37 projects
- Adgaon30 projects
All 103 localities
- Nashik Shiwar29
- Sinnar(M Cl)29
- Igatpuri (M Cl)28
- Vihitgaon28
- Kamatwade25
- Mhasrul25
- Bhagur Rural24
- Indiranagar24
- Sansari24
- Pimpalgaon Baswant23
- Chehedi Bk22
- Ozar (Ct)22
- Chandshi21
- Sinnar21
- Sinnar16
- Malegaon (M Corp.)15
- Wadala Shivar15
- Igatpuri14
- Gangapur13
- Chunchale10
- Dasak10
- Dindori10
- Jalalpur9
- Shinde9
- Belatgavhan8
- Palse8
- Ambad Khurd7
- Kasbe Vani7
- Lasalgaon7
- Panchak7
- Pimprisado7
- Bhagur (M Cl)6
- Gondedumala6
- Govardhan5
- Niphad5
- Satana4
- Malegaon3
- Niphad3
- Saikheda3
- Shramik Nagar3
- Trimbakeshwar3
- Yeola3
- Chandvad (Ct)2
- Dindori2
- Ghoti Bk. (Ct)2
- Girnare2
- Kawanai2
- Manmad (M Cl)2
- Naigaon2
- Nilgavhan2
- Ozar Gaon2
- Sangameshwar (Ct)2
- Saradwadi2
- Shivaji Nagar2
- Soyagaon (Ct)2
- Trimbakeshwar2
- Agartakli1
- Ashok Nagar1
- Behed1
- Beladgavhan1
- Borivali1
- Deola1
- Deshwandi1
- Gaulane1
- Gitakunj1
- Jaulke(Dindori)1
- Kasbe Sukene1
- Khambale1
- Madsangvi1
- Maparwadi1
- More Nagar1
- Mungsara1
- Naikwadi1
- Nandadgaon1
- Nandgaon1
- Pakhal Road1
- Pardevi1
- Pimpalgaon Bahula1
- Pimpalgaon Garudeshwar1
- Pimpalgaon Ketaki1
- Pimpalgaon Najik (Ct)1
- Satpur Colony1
- Surgana1
- Talegaon1
- Talegaon(Dindori)1
- Titoli1
- Trimbak (M Cl)1
- Umarane1
- Vilholi1
- Vinchur1
- Wasali1
Other districts
Most active promoters
- Roongta Homes Llp26 projects
- Jay Developers13 projects
- Kbc Global Limited12 projects
- Sanklecha Construction Private Limited11 projects
- Shah Builders And Developers11 projects
- Nashik Housing And Area Development Board10 projects
- Shreeji Life Space10 projects
- Deepak Kalyanji Chande9 projects
- Govinda Construction9 projects
- Sun Infrastructures Pvt. Ltd9 projects
Nashik, in questions
How many projects in Nashik run late?
7 in 10 MahaRERA registrations (3,100 of 4,255): their completion date was extended or has passed, data through 22 Nov 2026.
Where does this data come from?
From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Nashik by Deedo. Medians on fewer than 3 deeds are not shown.
Data through22 Nov 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology