7 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.

RERA projects4,204in 103 localities
Registrations4,255some projects hold several
Completion still due1,3062,580 past their date
Median extension4 months30% of registrations extended
Regulatory cases227on 198 projects

7 in 10 registrations run late here

4,255 MahaRERA registrations in Nashik and the places within it

376 completed410 not yet due887 extended, not yet due2,213 past even the latest date369 no date on record

Extended registrations moved their completion date by a median of 4 months.

Projects in Nashik

4,204 projects registered with MahaRERA in this district and the places within it.

ProjectDeliveryMedian ₹/sq ftBooked
Aringle CircleNo date on record——
Aristol TownFareha Builders & Designers Private LimitedNo date on record——
Arkk Pushp NxNo date on record——
Ashirwad ResidencyNo date on record——
Ashok prideNo date on record——
Ashtavaibhav HeightsGm Builders & DevelopersNo date on record——
Ashwika ComplexSHREE SAI BUILDERS and DEVELOPERSNo date on record——
Atharva Galaxy ApartmentNo date on record——
Atharva Pooja ApartmentNo date on record——
Atharva SamruddhiSiddhivinayak BuildtechNo date on record——
Auto CenterPrakash Jyot Developers Proprietor Prakash Kanhaiyalal AdwaniNo date on record——
Avira VilleVijay Pandurang PingleNo date on record——
Bage TabassumNo date on record——
Baitul Akhtar ApartmentMufti-E-Azam-Hind BuildconNo date on record——
Baitul Ali ApartmentOnyx RealtyNo date on record——
Bhabad PlazaSharad Fakira BhabadNo date on record——
Bhagirathi TowerNo date on record——
Bhagwati Park Row HousesRakesh Bharat ShahNo date on record——
Capetown - Apartments Phase 1No date on record——
Capetown -Apartments Phase IINo date on record——
Chintamani EliteAnup Ramanlal PahadeNo date on record——
Construction Of 175 Ts EWS Under PMAY And 33 Shops On G No602/2 Adgaon NashikNashik Housing And Area Development BoardNo date on record——
Construction Of 42 Ts EWS Under PMAYNashik Housing And Area Devlopment BoardNo date on record——
Construction of 57LIG 17Shops 10 Offices at S No 517 520 521 523 Plot No P1 at Satpur NashikNashik Housing And Area Development BoardNo date on record——
Corporate TowersNo date on record——
Nashik market reportPDF: prices and rents, volumes, projects ranked by deals and the most delayed — with the latest exact salesSee what's inside · from ₹1,999

Most active promoters

  1. Roongta Homes Llp26 projects
  2. Jay Developers13 projects
  3. Kbc Global Limited12 projects
  4. Sanklecha Construction Private Limited11 projects
  5. Shah Builders And Developers11 projects
  6. Nashik Housing And Area Development Board10 projects
  7. Shreeji Life Space10 projects
  8. Deepak Kalyanji Chande9 projects
  9. Govinda Construction9 projects
  10. Sun Infrastructures Pvt. Ltd9 projects

Nashik, in questions

How many projects in Nashik run late?

7 in 10 MahaRERA registrations (3,100 of 4,255): their completion date was extended or has passed, data through 22 Nov 2026.

Where does this data come from?

From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Nashik by Deedo. Medians on fewer than 3 deeds are not shown.

Data through22 Nov 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology