7 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.

RERA projects4,202in 103 localities
Registrations4,253some projects hold several
Completion still due1,3082,578 past their date
Median extension4 months30% of registrations extended
Regulatory cases227on 198 projects

7 in 10 registrations run late here

4,253 MahaRERA registrations in Nashik and the places within it

376 completed412 not yet due887 extended, not yet due2,211 past even the latest date367 no date on record

Extended registrations moved their completion date by a median of 4 months.

Projects in Nashik

4,202 projects registered with MahaRERA in this district and the places within it.

ProjectDeliveryMedian ₹/sq ftBooked
Siddhivinayak ApartmentSai Vaishnavi BuildconDue Jul 2028, extended 4 mo——
Bhavik MithilaBhavik Developers Private LimitedDue Apr 2033, extended 4 mo——
Goda MeadowsPatil and AssociatesDue Apr 2028, extended 4 mo——
Liberty OmkarDs VenturesDue Dec 2027, extended 4 mo——
Riddhi AnandvanDigvijay Builders And DevelopersDue Apr 2031, extended 4 mo——
Sarthi HomesShambhu RealtyDue Apr 2031, extended 4 mo——
Shree Harihar GalaxyShree Harihar InfraDue Mar 2029——
Keystone Saubhagya ApartmentKeystone BuildersDue Jul 2030, extended 4 mo——
Dev Darshan HeightsGoodwill PrideDue Jul 2029, extended 4 mo——
Imperial HeightsImperial RealtyDue Jul 2029, extended 4 mo——
Mahalaxmi PridePrasad InfraDue Jul 2028, extended 4 mo——
Mauli PrideDeepak Baban ChaudhariDue Jul 2028, extended 4 mo——
Sahydri HarmonyS K Builders And DevelopersDue Apr 2028, extended 4 mo——
Sai PrideJay InfrastructuresDue Nov 2029, extended 4 mo——
Sai Sulochana HeightsSai Kuber Builders And DevelopersDue Apr 2029, extended 4 mo——
The Skyline ApartmentAshokbhai Batukbhai AdrojaDue Jul 2029, extended 4 mo——
Bachhav EmpireAbhijit Ashok SoygaonkarDue Jul 2029, extended 4 mo——
HallmarkJSM EnterprisesDue Dec 2029——
Rosewood - I J and K WingIshanya BuildconDue Apr 2032, extended 4 mo——
Shantivinayak Co-operative Housing SocietyDhruved ConstructionDue Sep 2027, extended 4 mo——
Shiddh Sankul 2Raviraj BuildtechDue Apr 2027, extended 4 mo——
Varad HeightsVarad AssociatesDue Jul 2029, extended 4 mo——
Shree Platinum HeightsShree DevelopersDue Jul 2028, extended 4 mo——
Vijay SanskrutiVRV ConstructionDue Apr 2027, extended 4 mo——
D-Maps ShivtirthD Map EstatesDue Nov 2028, extended 4 mo——
Nashik market reportPDF: prices and rents, volumes, projects ranked by deals and the most delayed — with the latest exact salesSee what's inside · from ₹1,999

Most active promoters

  1. Roongta Homes Llp26 projects
  2. Jay Developers13 projects
  3. Kbc Global Limited12 projects
  4. Sanklecha Construction Private Limited11 projects
  5. Shah Builders And Developers11 projects
  6. Nashik Housing And Area Development Board10 projects
  7. Shreeji Life Space10 projects
  8. Deepak Kalyanji Chande9 projects
  9. Govinda Construction9 projects
  10. Sun Infrastructures Pvt. Ltd9 projects

Nashik, in questions

How many projects in Nashik run late?

7 in 10 MahaRERA registrations (3,098 of 4,253): their completion date was extended or has passed, data through 15 Nov 2026.

Where does this data come from?

From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Nashik by Deedo. Medians on fewer than 3 deeds are not shown.

Data through15 Nov 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology