7 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.

RERA projects4,202in 103 localities
Registrations4,253some projects hold several
Completion still due1,3082,578 past their date
Median extension4 months30% of registrations extended
Regulatory cases227on 198 projects

7 in 10 registrations run late here

4,253 MahaRERA registrations in Nashik and the places within it

376 completed412 not yet due887 extended, not yet due2,211 past even the latest date367 no date on record

Extended registrations moved their completion date by a median of 4 months.

Projects in Nashik

4,202 projects registered with MahaRERA in this district and the places within it.

ProjectDeliveryMedian ₹/sq ftBooked
Jyoti Prakash Co-operative Housing SocietyRevati EnterprisesDue Apr 2029, extended 4 mo——
Nilamay ApartmentVedant DevelopersDue Jul 2027, extended 4 mo——
Kamal ResidencyAnil Sharad KulkarniDue Feb 2028, extended 4 mo——
Narayani AvenueOjas Rajeev RasaneDue Nov 2028, extended 4 mo——
Sudha HeightsSudha BuildconDue Apr 2031, extended 4 mo——
Jeevan Darshan Co Op Housing Society LimitedJeevan Darshan Co Op Housing Society LimitedDue Jul 2029, extended 4 mo——
Kedarnath HeightsR K Builders & DevelopersDue Apr 2029, extended 4 mo——
Rajashree SiddhivinayakNandini Uday KothawadeDue Jul 2028, extended 4 mo——
Saptashrungi NandanSaptashrungi DevelopersDue Jul 2035, extended 4 mo——
Shreeji InsperiaShreeji Landmarks LLPDue Apr 2030, extended 4 mo——
Gangajal By ShreejiShreeji Landmarks LLPDue Apr 2030, extended 4 mo——
Sujan Co-operative Housing SocietyN S Builders and DevelopersDue Aug 2028, extended 4 mo——
Vraj ShrushtiKrrish DevelopersDue Apr 2031, extended 4 mo——
Shyam Amrut HeightsHeena Satishbhai ChavdaDue Jul 2028, extended 4 mo——
Ayodhya DhamTrimurti BuildconDue Apr 2027, extended 4 mo——
Madhurima Co Op Housing Society LtdK K ConstructionDue Jul 2027, extended 4 mo——
Nariman VanashreeNariman InfrastructureDue Apr 2031, extended 4 mo——
Shreeji Infinia PlusShreeji Landmarks LLPDue Jul 2030, extended 4 mo——
Sunrise SummitSawant Infra ProjectsDue Jul 2027, extended 4 mo——
Adarsh Gokul Co Op Housing SocietyFourth Dimension DevelopersDue Oct 2029, extended 4 mo——
Avdhoot ApartmentRAJENDRA BUILDERS and DEVELOPERS (PROP RAJENDRA PANDIT SONAJE)Due Jul 2029, extended 4 mo——
DSK GoldD S Kalantri Builders and DevelopersDue Mar 2027, extended 4 mo——
Kamdhenu HeightsKailash DevelopersDue Jul 2029, extended 4 mo——
Krishnai HillsBhaskar Baburao SonawaneDue Sep 2027, extended 4 mo——
Omkar ResidencyMetaliya DevelopersDue Apr 2031, extended 4 mo——
Nashik market reportPDF: prices and rents, volumes, projects ranked by deals and the most delayed — with the latest exact salesSee what's inside · from ₹1,999

Most active promoters

  1. Roongta Homes Llp26 projects
  2. Jay Developers13 projects
  3. Kbc Global Limited12 projects
  4. Sanklecha Construction Private Limited11 projects
  5. Shah Builders And Developers11 projects
  6. Nashik Housing And Area Development Board10 projects
  7. Shreeji Life Space10 projects
  8. Deepak Kalyanji Chande9 projects
  9. Govinda Construction9 projects
  10. Sun Infrastructures Pvt. Ltd9 projects

Nashik, in questions

How many projects in Nashik run late?

7 in 10 MahaRERA registrations (3,098 of 4,253): their completion date was extended or has passed, data through 15 Nov 2026.

Where does this data come from?

From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Nashik by Deedo. Medians on fewer than 3 deeds are not shown.

Data through15 Nov 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology