7 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.

RERA projects4,202in 103 localities
Registrations4,253some projects hold several
Completion still due1,3082,578 past their date
Median extension4 months30% of registrations extended
Regulatory cases227on 198 projects

7 in 10 registrations run late here

4,253 MahaRERA registrations in Nashik and the places within it

376 completed412 not yet due887 extended, not yet due2,211 past even the latest date367 no date on record

Extended registrations moved their completion date by a median of 4 months.

Projects in Nashik

4,202 projects registered with MahaRERA in this district and the places within it.

ProjectDeliveryMedian ₹/sq ftBooked
The Benchmark ApartmentSahyadri Builders & DevelopersDue Mar 2031, extended 4 mo——
Sri Kuberlaxmi ParkSri Kuberlaxmi GroupDue Mar 2031, extended 4 mo——
Prasad TowerSMR PropertiesDue Apr 2030, extended 4 mo——
Navniwant ApartmentVishwa ConstructionDue Apr 2032, extended 4 mo——
Trimurti AvenueTrimurti BuildconDue Apr 2028, extended 4 mo——
Grand VistaAnand Group Builders & DevelopersDue Apr 2029, extended 4 mo——
TGL CelestialThakkers Group LimitedDue Apr 2031, extended 4 mo——
Vedas Janardan HeightsSamruddhi BuildwellDue Apr 2029, extended 4 mo——
Bhagyalaxmi PlazaBharat PropertiesDue Nov 2027, extended 4 mo——
Omkar EnclaveOmkar RealtorsDue Jul 2029, extended 4 mo——
Pm1220002501775Para ConstructionDue Oct 2030——
Pm1221012501778Ashapuri DevelopersDue Mar 2032——
Sidhi Vinayak HeightSatyam Developers And Construction CompanyDue Feb 2029, extended 4 mo——
Tanishka CapitalTanishka Developers Proprietor Nandkumar Vasantrao JadhavDue Jan 2028, extended 4 mo——
Vastu AaradhyaVasturacheta BuildconDue Sep 2028, extended 4 mo——
W IslandShweta Infrastructure & Housing (I) Pvt. Ltd.Due Apr 2030, extended 4 mo——
Nisham InfiniaNisham DevelopersDue Jul 2028, extended 4 mo——
Om Shiv AnnexOm DevelopersDue Jul 2029, extended 4 mo——
Aashray HeightsVenkatesh Builders And DevelopersDue Feb 2027, extended 4 mo——
Sai Nisarg ApartmentBhadane BuildwellDue Nov 2028——
Samarth HeightsUttam BuildconDue Apr 2029, extended 4 mo——
Spm Square OneS M Buildcon And DevelopersDue Mar 2027——
AGK Ventures LotusAgk Ventures LotusDue Apr 2028, extended 4 mo——
Bhandari Greens Phase 2Ujjawala Sohanlal BhandariDue Jul 2027, extended 4 mo——
Shreeji IconicShreeji Landmarks LLPDue Oct 2031, extended 4 mo——
Nashik market reportPDF: prices and rents, volumes, projects ranked by deals and the most delayed — with the latest exact salesSee what's inside · from ₹1,999

Most active promoters

  1. Roongta Homes Llp26 projects
  2. Jay Developers13 projects
  3. Kbc Global Limited12 projects
  4. Sanklecha Construction Private Limited11 projects
  5. Shah Builders And Developers11 projects
  6. Nashik Housing And Area Development Board10 projects
  7. Shreeji Life Space10 projects
  8. Deepak Kalyanji Chande9 projects
  9. Govinda Construction9 projects
  10. Sun Infrastructures Pvt. Ltd9 projects

Nashik, in questions

How many projects in Nashik run late?

7 in 10 MahaRERA registrations (3,098 of 4,253): their completion date was extended or has passed, data through 14 Nov 2026.

Where does this data come from?

From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Nashik by Deedo. Medians on fewer than 3 deeds are not shown.

Data through14 Nov 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology