7 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.

RERA projects4,203in 103 localities
Registrations4,254some projects hold several
Completion still due1,3062,580 past their date
Median extension4 months30% of registrations extended
Regulatory cases227on 198 projects

7 in 10 registrations run late here

4,254 MahaRERA registrations in Nashik and the places within it

376 completed410 not yet due887 extended, not yet due2,213 past even the latest date368 no date on record

Extended registrations moved their completion date by a median of 4 months.

Projects in Nashik

4,203 projects registered with MahaRERA in this district and the places within it.

ProjectDeliveryMedian ₹/sq ftBooked
Vnp VrindavanSahyadri AssociatesCompleted—56%
Ayodhya Co Op Hsg Society LtdHiray And Jagtap AssociatesCompleted—10%
Bella CasaManomay BuildtechDue Mar 2027, extended 2 yrs——
Dream Avenue ApartmentHardik DevelopersCompleted——
Golden HeightsBalkrushna Keshraj Mehekarkar2 yrs 3 mo late——
Junnare HeightsSaumya BuildconCompleted, extended 8 mo—78%
Laxmi HeightsPramod Dudhnath Gupta2 yrs 11 mo late——
Mahalaxmi GardenMahalaxmi ConstructionsCompleted——
Sakar Vatika ApartmentManish Purshottam NarodiaCompleted—93%
Shree Atharvapark 2 Phase 2Atharvashree Buildmat Pvt LtdCompleted, extended 6 mo—26%
Shree Krishnavihar ApartmentMadhuri Prakash MaliCompleted—83%
Shri Sharan- NestSandip Surecsh ThakreCompleted——
Shrutika HeightsBharti Anil PawarCompleted—60%
Siddhesh ApartmentSiddhesh DevelopersCompleted—100%
Ashok Elite ApartmentSagar Bhagwat PawarCompleted—93%
Ashtapad HeightsArkk Builders And DevelopersDue Apr 2027, extended 4 mo——
Balaji ParadiseVipul Ashok KhairnarCompleted——
Galaxy ApartmentVihaan Realtors3 yrs 11 mo late——
Natures NestRoyal DevelopersDue Nov 2026, extended 4 mo—20%
Nirmal VishwaNirmal Construction3 yrs late——
Samruddhi ParkDg InfraCompleted——
Samruddhi VishwaSunita Laxman GomaseCompleted—100%
Shree Chintamani AneexS.m.developers11 mo late—24%
Shubharambh ResidencyLaxmi Buildcon2 yrs 3 mo late—100%
Varni TownShree Hari Builders And DevelopersCompleted——
Nashik market reportPDF: prices and rents, volumes, projects ranked by deals and the most delayed — with the latest exact salesSee what's inside · from ₹1,999

Most active promoters

  1. Roongta Homes Llp26 projects
  2. Jay Developers13 projects
  3. Kbc Global Limited12 projects
  4. Sanklecha Construction Private Limited11 projects
  5. Shah Builders And Developers11 projects
  6. Nashik Housing And Area Development Board10 projects
  7. Shreeji Life Space10 projects
  8. Deepak Kalyanji Chande9 projects
  9. Govinda Construction9 projects
  10. Sun Infrastructures Pvt. Ltd9 projects

Nashik, in questions

How many projects in Nashik run late?

7 in 10 MahaRERA registrations (3,100 of 4,254): their completion date was extended or has passed, data through 20 Nov 2026.

Where does this data come from?

From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Nashik by Deedo. Medians on fewer than 3 deeds are not shown.

Data through20 Nov 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology