7 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.

RERA projects4,203in 103 localities
Registrations4,254some projects hold several
Completion still due1,3062,580 past their date
Median extension4 months30% of registrations extended
Regulatory cases227on 198 projects

7 in 10 registrations run late here

4,254 MahaRERA registrations in Nashik and the places within it

376 completed410 not yet due887 extended, not yet due2,213 past even the latest date368 no date on record

Extended registrations moved their completion date by a median of 4 months.

Projects in Nashik

4,203 projects registered with MahaRERA in this district and the places within it.

ProjectDeliveryMedian ₹/sq ftBooked
Elite RiaanRiaan Ankit RealtechCompleted——
Gangasagar Residency ApartmentPramod Pralhad Kakad10 mo late—58%
Renuka AnnexRenuka Builders And DevelopersDue Mar 2027—48%
Rushiraj Serenity ApartmentJhala InfratechCompleted—67%
Samarth Vijay GalaxyAtul Tukaram Wagh2 yrs 9 mo late——
Shivrudra HeightsShruti Enterprises1 yr 9 mo late——
Shivsrushti AnnexVishal Laxman GadekarCompleted——
Shreeja HeightsPalde Construction2 yrs 11 mo late——
Aakar PrimeAakar BuildconCompleted——
AnantaShiv Agro Farms1 yr 5 mo late——
Ayodhya PalaceShubh Sankalp Builders & DevelopersCompleted—100%
Ganesh EssencePebble Infracon LLPDue Jul 2027, extended 4 mo—51%
Ganesh ExcellaPebble Infracon LLPDue Jul 2027, extended 4 mo——
Kamdhenu SkyBhagwati DevelopersCompleted—36%
Mahaveer HeightsMahaveer Builders and DevelopersCompleted——
Morya ParkKiran Nivrutti Kate2 yrs 3 mo late——
NakshatraStandard Realtors Private Limited1 yr 5 mo late——
Nirmay HeightsNirmay InfraDue Apr 2027, extended 4 mo——
Nooren HeritageEjaz Abdul Majid ShaikhDue Apr 2027, extended 4 mo——
PADMASHREE ApartmentPadma BuildconCompleted——
Siddhivinayak HeightsSiddhivinayak BuildtechCompleted——
The Grand By Parksyde Phase - 1Jaikumar Constructions LtdDue Aug 2027, extended 4 mo——
The Grand By Parksyde Phase - 2Jaikumar Constructions LtdCompleted——
Aditi ApartmentMinaxi Chaitanya Sompura2 yrs 4 mo late——
Ariba ApartmentMohammad Anjar Inamullah Khan3 yrs 1 mo late——
Nashik market reportPDF: prices and rents, volumes, projects ranked by deals and the most delayed — with the latest exact salesSee what's inside · from ₹1,999

Most active promoters

  1. Roongta Homes Llp26 projects
  2. Jay Developers13 projects
  3. Kbc Global Limited12 projects
  4. Sanklecha Construction Private Limited11 projects
  5. Shah Builders And Developers11 projects
  6. Nashik Housing And Area Development Board10 projects
  7. Shreeji Life Space10 projects
  8. Deepak Kalyanji Chande9 projects
  9. Govinda Construction9 projects
  10. Sun Infrastructures Pvt. Ltd9 projects

Nashik, in questions

How many projects in Nashik run late?

7 in 10 MahaRERA registrations (3,100 of 4,254): their completion date was extended or has passed, data through 20 Nov 2026.

Where does this data come from?

From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Nashik by Deedo. Medians on fewer than 3 deeds are not shown.

Data through20 Nov 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology