Deedo IDDL-NSK-NASHIK7 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.
RERA projects4,203in 103 localities
Registrations4,254some projects hold several
Completion still due1,3062,580 past their date
Median extension4 months30% of registrations extended
Regulatory cases227on 198 projects
7 in 10 registrations run late here
4,254 MahaRERA registrations in Nashik and the places within it
376 completed410 not yet due887 extended, not yet due2,213 past even the latest date368 no date on record
Extended registrations moved their completion date by a median of 4 months.
Projects in Nashik
4,203 projects registered with MahaRERA in this district and the places within it.
| Project | Delivery | Median ₹/sq ft | Booked |
|---|---|---|---|
| Bhavya TowersNaresh Punjabhai Patel | Due Apr 2028, extended 4 mo | — | 2% |
| IshwarpushpKamani Buildcon | Due May 2027, extended 4 mo | — | — |
| Rajashree ManglamRajashree Properties | Completed | — | 36% |
| Sai Pushp ResidencyShree Sai Associates Proprietor Motilal Sai Umarwal | 1 yr 11 mo late | — | — |
| Samruddhi ApartmentVaishnavi Construction | Due Apr 2027, extended 4 mo | — | 35% |
| Shree Datt GloryVilas Dattatray Khairnar | Completed | — | 10% |
| Shreeji CelestiaShreeji Life Space | Due Oct 2028, extended 4 mo | — | 49% |
| The ChoupaalKalantri And Bang Properties | Due Jul 2027, extended 4 mo | — | — |
| Amrutdhara Housing Complex Phase - IRadheya Constructions & Developers Proprietor Ravi Raghunath Mahajan | Due Aug 2027, extended 4 mo | — | 26% |
| Brij Nikunj ApartmentSandeep Gulabchand Gupta | Completed | — | 60% |
| Daksh BlissH K Properties | Completed | — | 10% |
| Daksh OliveDaksh Construction | 11 mo late | — | 85% |
| Iris HeightsSamarth Infra | Due Apr 2027, extended 4 mo | — | 17% |
| Nimbus Business CentreS P M Developers | 1 yr 9 mo late | — | — |
| Olive GardenOlive Infrastructure | Due Jan 2027, extended 4 mo | — | 40% |
| Palm TownVakratunda Properties | Due Apr 2027, extended 4 mo | — | 21% |
| Prabhu SwarajPacific Builders | Completed | — | 63% |
| shivalayheightsShivalay Construction | Due Dec 2026 | — | 60% |
| Shree Ganadhish ParkC K Developers | Due Jan 2027, extended 4 mo | — | — |
| Shreeji The CrownShreeji Life Space | Due Oct 2028, extended 4 mo | — | 15% |
| Shree Krishna HeightsJk Buildcon | Due Jul 2027, extended 4 mo | — | — |
| Tulsi Nirvana ApartmentTulsi Construction | Completed | — | — |
| Chairman Hem Co-Op. Housing Society Ltd.Jk Infrastructures | Completed | — | — |
| Namo Narayan NagarA R Developers | Due Jul 2028, extended 4 mo | — | 31% |
| Neelkanth HeightsYatin Annasahib Wani | Completed | — | — |
Localities in Nashik
- Nashik1,372 projects
- Nashik (M Corp.)1,251 projects
- Nashik302 projects
- Aanandwali94 projects
- Deolaligaon67 projects
- Nashik Road67 projects
- Satpur56 projects
- Jail Road55 projects
- Deolali (Cb)50 projects
- Makhmalabad45 projects
- Pathardi37 projects
- Adgaon30 projects
All 103 localities
- Nashik Shiwar29
- Sinnar(M Cl)29
- Igatpuri (M Cl)28
- Vihitgaon28
- Kamatwade25
- Mhasrul25
- Bhagur Rural24
- Indiranagar24
- Sansari24
- Pimpalgaon Baswant23
- Chehedi Bk22
- Ozar (Ct)22
- Chandshi21
- Sinnar21
- Sinnar16
- Malegaon (M Corp.)15
- Wadala Shivar15
- Igatpuri14
- Gangapur13
- Chunchale10
- Dasak10
- Dindori10
- Jalalpur9
- Shinde9
- Belatgavhan8
- Palse8
- Ambad Khurd7
- Kasbe Vani7
- Lasalgaon7
- Panchak7
- Pimprisado7
- Bhagur (M Cl)6
- Gondedumala6
- Govardhan5
- Niphad5
- Satana4
- Malegaon3
- Niphad3
- Saikheda3
- Shramik Nagar3
- Trimbakeshwar3
- Yeola3
- Chandvad (Ct)2
- Dindori2
- Ghoti Bk. (Ct)2
- Girnare2
- Kawanai2
- Manmad (M Cl)2
- Naigaon2
- Nilgavhan2
- Ozar Gaon2
- Sangameshwar (Ct)2
- Saradwadi2
- Shivaji Nagar2
- Soyagaon (Ct)2
- Trimbakeshwar2
- Agartakli1
- Ashok Nagar1
- Behed1
- Beladgavhan1
- Borivali1
- Deola1
- Deshwandi1
- Gaulane1
- Gitakunj1
- Jaulke(Dindori)1
- Kasbe Sukene1
- Khambale1
- Madsangvi1
- Maparwadi1
- More Nagar1
- Mungsara1
- Naikwadi1
- Nandadgaon1
- Nandgaon1
- Pakhal Road1
- Pardevi1
- Pimpalgaon Bahula1
- Pimpalgaon Garudeshwar1
- Pimpalgaon Ketaki1
- Pimpalgaon Najik (Ct)1
- Satpur Colony1
- Surgana1
- Talegaon1
- Talegaon(Dindori)1
- Titoli1
- Trimbak (M Cl)1
- Umarane1
- Vilholi1
- Vinchur1
- Wasali1
Other districts
Most active promoters
- Roongta Homes Llp26 projects
- Jay Developers13 projects
- Kbc Global Limited12 projects
- Sanklecha Construction Private Limited11 projects
- Shah Builders And Developers11 projects
- Nashik Housing And Area Development Board10 projects
- Shreeji Life Space10 projects
- Deepak Kalyanji Chande9 projects
- Govinda Construction9 projects
- Sun Infrastructures Pvt. Ltd9 projects
Nashik, in questions
How many projects in Nashik run late?
7 in 10 MahaRERA registrations (3,100 of 4,254): their completion date was extended or has passed, data through 20 Nov 2026.
Where does this data come from?
From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Nashik by Deedo. Medians on fewer than 3 deeds are not shown.
Data through20 Nov 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology