7 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.

RERA projects4,203in 103 localities
Registrations4,254some projects hold several
Completion still due1,3062,580 past their date
Median extension4 months30% of registrations extended
Regulatory cases227on 198 projects

7 in 10 registrations run late here

4,254 MahaRERA registrations in Nashik and the places within it

376 completed410 not yet due887 extended, not yet due2,213 past even the latest date368 no date on record

Extended registrations moved their completion date by a median of 4 months.

Projects in Nashik

4,203 projects registered with MahaRERA in this district and the places within it.

ProjectDeliveryMedian ₹/sq ftBooked
Laxmi Sky ParkLaxmi Builders And Developers1 yr 5 mo late——
Morya DarshanOmkar Builders And Developers1 yr 7 mo late——
M SquareSunanda Gangadhar ManeDue Mar 2027——
Omkar SankulOmkar Builders And Developers2 yrs 8 mo late——
Shilp KrishnaKaran Hemant GaikwadCompleted—36%
Shivsiddhi HeightsPankaj Sudhakar GavaliDue Apr 2027, extended 4 mo—36%
Shree Ganesh AvenueR P AssociatesCompleted—17%
Sky ParkviewSky DevelopersCompleted—4%
Snehabandh Co-Op Housing Society LtdJk BuildconCompleted—79%
Sugandha HeightsGaurav Chandrapal KajaleDue Apr 2028, extended 4 mo—28%
Swastik HeightEkta DevelopersCompleted—86%
Vinayak ApartmentGanesh Vasant YeoleCompleted—56%
Gangotri ParadiseAnil Kaluseth MataleDue Jun 2031, extended 4 mo——
Sai AshirwadTrishika Buildcon Private LimitedCompleted, extended 5 mo—80%
Pitruchaya ApartmentVedant Sachin Pawar2 yrs 8 mo late—40%
Sidhivinayak ApartmentAshwin Shamji MavaniCompleted——
Aadhya HeightsVedant ConstructionCompleted—79%
Aastha ResidencyManoj Madhukar ToshniwalCompleted—36%
Akshar ParkAshirwad ConstruwellCompleted——
Balaji HeightsAditya Dilip Bhandari3 yrs 8 mo late——
Chandra-TaraNirmaan Engineers And ContractorsCompleted—74%
Dwarika ApartmentMatoshri BuildconDue Dec 2026—27%
Fakhar Galaxy ApartmentBushra BuildersCompleted—98%
Garden VillaPawa Construction9 mo late——
Garib Nawaz ResidencyAsif Saqib BhureCompleted—100%
Nashik market reportPDF: prices and rents, volumes, projects ranked by deals and the most delayed — with the latest exact salesSee what's inside · from ₹1,999

Most active promoters

  1. Roongta Homes Llp26 projects
  2. Jay Developers13 projects
  3. Kbc Global Limited12 projects
  4. Sanklecha Construction Private Limited11 projects
  5. Shah Builders And Developers11 projects
  6. Nashik Housing And Area Development Board10 projects
  7. Shreeji Life Space10 projects
  8. Deepak Kalyanji Chande9 projects
  9. Govinda Construction9 projects
  10. Sun Infrastructures Pvt. Ltd9 projects

Nashik, in questions

How many projects in Nashik run late?

7 in 10 MahaRERA registrations (3,100 of 4,254): their completion date was extended or has passed, data through 20 Nov 2026.

Where does this data come from?

From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Nashik by Deedo. Medians on fewer than 3 deeds are not shown.

Data through20 Nov 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology