7 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.

RERA projects4,202in 103 localities
Registrations4,253some projects hold several
Completion still due1,3082,578 past their date
Median extension4 months30% of registrations extended
Regulatory cases227on 198 projects

7 in 10 registrations run late here

4,253 MahaRERA registrations in Nashik and the places within it

376 completed412 not yet due887 extended, not yet due2,211 past even the latest date367 no date on record

Extended registrations moved their completion date by a median of 4 months.

Projects in Nashik

4,202 projects registered with MahaRERA in this district and the places within it.

ProjectDeliveryMedian ₹/sq ftBooked
Padma Vishwa LandmarkSiddhi ConstructionDue Apr 2027, extended 4 mo—50%
Swami Kuber ResidencySwami Kuber Construction1 yr 11 mo late—13%
Swaroop MajesticShivshankar Enterprises Proprietor Kiran Vishnu JanjaleCompleted—40%
Varad Vinayak ApartmentManoj Arun BagCompleted——
Vedas AvenueVedas SpacesCompleted—41%
Vedas Sonal ParkVedas SpacesCompleted——
Vihaan Glory ApartmentTirupati BuildconCompleted——
Avneshwari ApartmentIndrayani BuildconCompleted——
Devanshi HeightsDeepak Pramod DeshmukhCompleted——
Hariom Avenue ApartmentShiv DevelopersCompleted—36%
Jayshree BlissJayshree Infra ProjectsCompleted—67%
Keystone Sampanna ApartmentKeystone ConstructionCompleted—89%
Sai Rudra ResidencySun Developers Proprietor Mehul Parshottambhai KathiriyaCompleted—60%
Shree Ganesh CrescentPrakash Raman ChaudhariDue Apr 2028, extended 4 mo—56%
Shreeniwas ApartmentSunil Bhausing PawarCompleted——
Shree SocietyGanraj InfraDue Apr 2028, extended 4 mo——
Three Leaves Phase OneDeepak Infra And Homes Private LimitedDue Apr 2031, extended 4 mo—59%
Tulshibag PrideMusale Builders1 yr 11 mo late——
Vinayak HeightsNeha Bhavani DubeyCompleted—100%
Viraj Trade CenterViraj Estates Pvt. Ltd.Due Apr 2028, extended 4 mo—52%
DBS EmpyreanShree Dream BuildersCompleted——
Neel ResidencySandhya Vijay RasaneCompleted—17%
Vinayak ResidencyVinayak Premises Pvt. LtdCompleted—79%
Antariksha AvenueA K BuildwellDue Apr 2028, extended 4 mo——
Devdatta ApartmentAjay Madhavrao Mahajan And Makarand Sudhakar PuranikCompleted—30%
Nashik market reportPDF: prices and rents, volumes, projects ranked by deals and the most delayed — with the latest exact salesSee what's inside · from ₹1,999

Most active promoters

  1. Roongta Homes Llp26 projects
  2. Jay Developers13 projects
  3. Kbc Global Limited12 projects
  4. Sanklecha Construction Private Limited11 projects
  5. Shah Builders And Developers11 projects
  6. Nashik Housing And Area Development Board10 projects
  7. Shreeji Life Space10 projects
  8. Deepak Kalyanji Chande9 projects
  9. Govinda Construction9 projects
  10. Sun Infrastructures Pvt. Ltd9 projects

Nashik, in questions

How many projects in Nashik run late?

7 in 10 MahaRERA registrations (3,098 of 4,253): their completion date was extended or has passed, data through 15 Nov 2026.

Where does this data come from?

From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Nashik by Deedo. Medians on fewer than 3 deeds are not shown.

Data through15 Nov 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology