7 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.

RERA projects4,202in 103 localities
Registrations4,253some projects hold several
Completion still due1,3082,578 past their date
Median extension4 months30% of registrations extended
Regulatory cases227on 198 projects

7 in 10 registrations run late here

4,253 MahaRERA registrations in Nashik and the places within it

376 completed412 not yet due887 extended, not yet due2,211 past even the latest date367 no date on record

Extended registrations moved their completion date by a median of 4 months.

Projects in Nashik

4,202 projects registered with MahaRERA in this district and the places within it.

ProjectDeliveryMedian ₹/sq ftBooked
River RidgeShashikant Narayan YeolaDue Dec 2026——
Rosewood G - A Wing & Rosewood H - B WingIshanya Buildcon11 mo late—61%
Antarang ApartmentShrinath RealtyDue Apr 2028, extended 4 mo—23%
Daksh SkywayR K ConstructionDue Mar 2029, extended 4 mo—5%
GovindanandAnagh InfraCompleted——
Joshi Baug Co-op Housing SocietyShubharambh BuildconDue Dec 2026——
Mahavir AvenueAbhaykumar Mukundchand LodhaCompleted——
Mona AvenueArunbhai Nanjibhai Mangroliya Prop Of Back Bone DevelopersCompleted——
Sakar PrimeMuktaben Purushottam NarodiaCompleted—27%
Samruddhi HaripathSamruddhi RealtyCompleted—6%
Shanti PrideMandabai Ramesh KothuleCompleted—53%
Shivshankar ApartmentDatta Nivrutti ShejvalCompleted—83%
Shreemalhar ApartmentShreeswami ConstructionsCompleted—25%
AavaasA L Realty Proprietor Akshay Sunil LolageDue Apr 2027, extended 4 mo—12%
Anand PalacePratik Sanjay JadhavCompleted—100%
Atreya HeightsAts Buildcon2 yrs 6 mo late—33%
Belle Vue RoyaleBelle Vue RealtyDue Apr 2027, extended 4 mo——
Chaitra AashaChaitra Builders Proprietor Chaitra Santosh HudlikarCompleted——
Gajanan HeightsAditya Vasudev Pund11 mo late—17%
Gajanan Row BunglowsGajanan DevelopersCompleted—88%
Govind AvenueManoj Prakash Pawar1 yr late——
Highness PlazaEkanta ConstructionCompleted, extended 1 yr—31%
Ishwar Pratishtha IVShankar Ghanshyamdas SamnaniCompleted—71%
Qadri PlazaHaidar Sadruddin KhotDue Dec 2030——
Sai Omkar Heights ApartmentNew Balaji Builder And DevelopersDue Apr 2028, extended 4 mo——
Nashik market reportPDF: prices and rents, volumes, projects ranked by deals and the most delayed — with the latest exact salesSee what's inside · from ₹1,999

Most active promoters

  1. Roongta Homes Llp26 projects
  2. Jay Developers13 projects
  3. Kbc Global Limited12 projects
  4. Sanklecha Construction Private Limited11 projects
  5. Shah Builders And Developers11 projects
  6. Nashik Housing And Area Development Board10 projects
  7. Shreeji Life Space10 projects
  8. Deepak Kalyanji Chande9 projects
  9. Govinda Construction9 projects
  10. Sun Infrastructures Pvt. Ltd9 projects

Nashik, in questions

How many projects in Nashik run late?

7 in 10 MahaRERA registrations (3,098 of 4,253): their completion date was extended or has passed, data through 15 Nov 2026.

Where does this data come from?

From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Nashik by Deedo. Medians on fewer than 3 deeds are not shown.

Data through15 Nov 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology