7 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.

RERA projects4,202in 103 localities
Registrations4,253some projects hold several
Completion still due1,3082,578 past their date
Median extension4 months30% of registrations extended
Regulatory cases227on 198 projects

7 in 10 registrations run late here

4,253 MahaRERA registrations in Nashik and the places within it

376 completed412 not yet due887 extended, not yet due2,211 past even the latest date367 no date on record

Extended registrations moved their completion date by a median of 4 months.

Projects in Nashik

4,202 projects registered with MahaRERA in this district and the places within it.

ProjectDeliveryMedian ₹/sq ftBooked
Shree Gokul Coop Housing Society LtdFourth Dimension DevelopersCompleted—62%
Shri Eknath TowerSHREE BALAJI BUILDERS and DEVELOPERS1 yr 8 mo late—32%
Sukan SankulShaileshkumar Vithalbhai RakholiyaDue Jul 2027, extended 4 mo—35%
The EmeraldLuxshri Ventures LLPDue Apr 2027, extended 4 mo——
Tirupati HillsRahul Mandaleshwar Kale8 mo late—50%
Vastu AvenueApurva Builders & DevelopersCompleted—46%
Vedant III A WingNew Akshara ConstructionCompleted—100%
Sara HeightDiamond Arch Developers1 yr 11 mo late—30%
Shivtirth Co-op Hsg. SocietySunyard Developers11 mo late——
Shreeram ResidencyParmanand Shrikrishna Patil1 yr 6 mo late—90%
Shri Krushna Kunj TowerShankar Dilip SuryawanshiDue Apr 2027, extended 4 mo—22%
Anvita ParkAakaar Infra8 mo late——
Mansi ResidencyShraddha Developers1 yr 5 mo late——
Aashirvad Golden NestAashirvad Divyanirman Private LimitedCompleted——
Arjun ResidencyP Square Constructions And Developers7 mo late—54%
Ashtapad Phase VIArkk Builders And DevelopersDue Apr 2030, extended 4 mo—30%
Supremes Tejas ParadiseSupreme Constructions And CreationsDue Jul 2027, extended 4 mo——
Minakshi Viaan ApartmentShrihaan Builders Private LimitedCompleted—20%
Psd AvenueShivansh Infrastructure1 yr 11 mo late——
Ramkrishna Hari ApartmentVishant Vilas ChumbhaleDue Apr 2027, extended 4 mo——
Tulsi VasundharaTulsi DevelopersDue Aug 2028, extended 4 mo—8%
Vedant Prasad ApartmentGorakshanath Dashrath MhaskeCompleted—48%
Shiv ApartmentShree Laxmi BuildersCompleted——
Ashok Business CentreNagratan Ashok Kangokar & FamilyDue Apr 2029, extended 4 mo—9%
Capital DreamzR B & Co.Completed—9%
Nashik market reportPDF: prices and rents, volumes, projects ranked by deals and the most delayed — with the latest exact salesSee what's inside · from ₹1,999

Most active promoters

  1. Roongta Homes Llp26 projects
  2. Jay Developers13 projects
  3. Kbc Global Limited12 projects
  4. Sanklecha Construction Private Limited11 projects
  5. Shah Builders And Developers11 projects
  6. Nashik Housing And Area Development Board10 projects
  7. Shreeji Life Space10 projects
  8. Deepak Kalyanji Chande9 projects
  9. Govinda Construction9 projects
  10. Sun Infrastructures Pvt. Ltd9 projects

Nashik, in questions

How many projects in Nashik run late?

7 in 10 MahaRERA registrations (3,098 of 4,253): their completion date was extended or has passed, data through 15 Nov 2026.

Where does this data come from?

From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Nashik by Deedo. Medians on fewer than 3 deeds are not shown.

Data through15 Nov 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology