7 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.

RERA projects4,204in 103 localities
Registrations4,255some projects hold several
Completion still due1,3062,580 past their date
Median extension4 months30% of registrations extended
Regulatory cases227on 198 projects

7 in 10 registrations run late here

4,255 MahaRERA registrations in Nashik and the places within it

376 completed410 not yet due887 extended, not yet due2,213 past even the latest date369 no date on record

Extended registrations moved their completion date by a median of 4 months.

Projects in Nashik

4,204 projects registered with MahaRERA in this district and the places within it.

ProjectDeliveryMedian ₹/sq ftBooked
Vasturang Enclave C And D WingNo date on record——
Vastu Row HouseNo date on record——
Vasundhara Niketan Wing ANachiket Gopal PatilNo date on record——
Vasundhara Niketan Wing BNo date on record——
Vasundhara Niketan Wing CNo date on record——
Vedant Darshan ApartmentBalasaheb Kondaji KedarNo date on record——
Vedant HeightsNo date on record——
Vedant ParkNo date on record——
Ved Residency Co-Operative Housing Society LtdVed Residency Co-operative Housing Society LtdNo date on record——
Veds RajlaxmiNo date on record——
Venkatesh ParkAashray ConstructionNo date on record——
Vimal HeightsNo date on record——
Vimal Icon Phase 2Jayashree Vinod PatkarNo date on record——
Vimal PrideNo date on record——
Vinayak ApartmentSoumitra Ratnakar PawarNo date on record——
Viraj HeightsViraj Housing DevelopersNo date on record——
Vishwa HeightsNo date on record——
Vishwas ParkNo date on record——
Vithumauli ApartmentMauli Builders And DevlopersNo date on record——
Vitthal DarshanNiwas DevelopersNo date on record——
Vitthal PrideNo date on record——
Vrundavan AvadhootNo date on record——
Vrundavan ParkGhanshyambhai Gokalbhai ViramgamaNo date on record——
Vrundawan Apartment Wing BNo date on record——
Yashoda CrystalNo date on record——
Nashik market reportPDF: prices and rents, volumes, projects ranked by deals and the most delayed — with the latest exact salesSee what's inside · from ₹1,999

Most active promoters

  1. Roongta Homes Llp26 projects
  2. Jay Developers13 projects
  3. Kbc Global Limited12 projects
  4. Sanklecha Construction Private Limited11 projects
  5. Shah Builders And Developers11 projects
  6. Nashik Housing And Area Development Board10 projects
  7. Shreeji Life Space10 projects
  8. Deepak Kalyanji Chande9 projects
  9. Govinda Construction9 projects
  10. Sun Infrastructures Pvt. Ltd9 projects

Nashik, in questions

How many projects in Nashik run late?

7 in 10 MahaRERA registrations (3,100 of 4,255): their completion date was extended or has passed, data through 22 Nov 2026.

Where does this data come from?

From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Nashik by Deedo. Medians on fewer than 3 deeds are not shown.

Data through22 Nov 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology