7 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.

RERA projects4,203in 103 localities
Registrations4,254some projects hold several
Completion still due1,3062,580 past their date
Median extension4 months30% of registrations extended
Regulatory cases227on 198 projects

7 in 10 registrations run late here

4,254 MahaRERA registrations in Nashik and the places within it

376 completed410 not yet due887 extended, not yet due2,213 past even the latest date368 no date on record

Extended registrations moved their completion date by a median of 4 months.

Projects in Nashik

4,203 projects registered with MahaRERA in this district and the places within it.

ProjectDeliveryMedian ₹/sq ftBooked
Ganesh AtriaZenith DevelopersCompleted, extended 1 yr—33%
IchhamaniSanket BuildtechCompleted, extended 5 yrs 3 mo—50%
Laxmi Krupa ApartmentLakhamsi Raja PatelCompleted—50%
Pamko SmruteeSatish Balkrishna Paranjape4 yrs 7 mo late——
Sai Krupa ApartmentVijan Realty Private LimitedCompleted, extended 4 yrs 3 mo—75%
Krishna PrideShree Krishna ConstructionsCompleted—17%
Liberty NiwasShrishti BuildconCompleted—100%
Omkar ApartmentVimalbhai Parbatbhai TogadiyaCompleted—100%
Renuka DarshanRenuka DevelopersCompleted, extended 1 yr 6 mo—52%
Sno 250/2Nirman Estate Dev. Pvt. LtdCompleted——
Thakkers ParadiseMotel Kutir Nirman Pvt. Ltd.Completed—9%
AdiguruMahajan BuildconCompleted—56%
Anushree ApartmentRavi Mahajan ( HUF )Completed—100%
Archit NestSandeep Ramdas ShindeCompleted, extended 1 yr 6 mo—35%
Aurum estate phase 2 AURENEVIstacore VenturesCompleted——
Casablanca Road FrontArkk Builders And DevelopersCompleted—83%
Rajmudra EmpireUnity Associates NasikCompleted—95%
Saket Heights ApartmentGeeta Land DevelopersCompleted, extended 1 yr—80%
Suyojit Viridian Vallis-Phase 1-D1 Sector OtioSun Infrastructures Pvt LtdDue Dec 2026, extended 5 yrs 9 mo——
Aurum Estate Phase 3 AugustusVistacore VenturesCompleted——
Gurudev HeightsAmit Gangadhar JadhavCompleted—70%
Kunal ResidencyKunal Builders And DevelopersCompleted—69%
PADMAVATI NAGARI BLDG NO 1 A and B wingS D Bhalerao Constructions Pvt LtdCompleted, extended 1 yr 10 mo——
Parksyde Homes Phase 3Jaikumar Constructions LLPCompleted—99%
Shashi Anand EnclaveAnand Prem AssociatesCompleted—86%
Nashik market reportPDF: prices and rents, volumes, projects ranked by deals and the most delayed — with the latest exact salesSee what's inside · from ₹1,999

Most active promoters

  1. Roongta Homes Llp26 projects
  2. Jay Developers13 projects
  3. Kbc Global Limited12 projects
  4. Sanklecha Construction Private Limited11 projects
  5. Shah Builders And Developers11 projects
  6. Nashik Housing And Area Development Board10 projects
  7. Shreeji Life Space10 projects
  8. Deepak Kalyanji Chande9 projects
  9. Govinda Construction9 projects
  10. Sun Infrastructures Pvt. Ltd9 projects

Nashik, in questions

How many projects in Nashik run late?

7 in 10 MahaRERA registrations (3,100 of 4,254): their completion date was extended or has passed, data through 20 Nov 2026.

Where does this data come from?

From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Nashik by Deedo. Medians on fewer than 3 deeds are not shown.

Data through20 Nov 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology