Nashik
Deedo IDDL-NSK-NASHIK7 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.
RERA projects4,202in 103 localities
Registrations4,253some projects hold several
Completion still due1,3082,578 past their date
Median extension4 months30% of registrations extended
Regulatory cases227on 198 projects
7 in 10 registrations run late here
4,253 MahaRERA registrations in Nashik and the places within it
376 completed412 not yet due887 extended, not yet due2,211 past even the latest date367 no date on record
Extended registrations moved their completion date by a median of 4 months.
Projects in Nashik
4,202 projects registered with MahaRERA in this district and the places within it.
| Project | Delivery | Median ₹/sq ft | Booked |
|---|---|---|---|
| Sharda ResidencyMan Mandir Developers | Due Jan 2029, extended 4 mo | — | — |
| Ramas BellezzaChandrakant Ramdas Pingale | Due Apr 2031, extended 4 mo | — | — |
| Aaruth PrideBhoomi Infratech | Due Apr 2030, extended 4 mo | — | — |
| Gangotri HeightsGajvinayak Developers | Due Apr 2032, extended 4 mo | — | — |
| Krishna Kunj ApartmentAnup Buildcon | Due Oct 2030, extended 4 mo | — | — |
| Manohar SmrutiMonali Tushar Aher | Due Sep 2028 | — | — |
| Padma Vishwa IconSiddhi Developers | Due Apr 2030, extended 4 mo | — | — |
| Shraddha PrimusShraddha Land Developers & Builders | Due Apr 2028, extended 4 mo | — | — |
| The SolitaireShree Siddhi Vinayak Buildcon | Due Apr 2029, extended 4 mo | — | — |
| Dhaneshwari ApartmentShiv Vandana Realty | Due Apr 2028, extended 4 mo | — | — |
| Sai SaffronSwapnil Suryabhan Jadhav | Due Apr 2030, extended 4 mo | — | — |
| Shri Krushna WaterwaySarwdnya Buildtech | Due Sep 2029, extended 4 mo | — | — |
| Harmony HeavenNashik Housing & Area Development Board, Nashik | Due Mar 2031, extended 4 mo | — | — |
| Lakshmi Maya ApartmentTrinity Builders And Developers | Due Apr 2030, extended 4 mo | — | — |
| Ashiyana Luxuria IIBrijwasi Megaproperties LLP | Due Apr 2029 | — | — |
| Sinhgad co-operative Housing socity limitedKare Developers | Due Apr 2029, extended 4 mo | — | — |
| Acacia apartmentNashik Housing and Area Development Board | Due Mar 2031, extended 4 mo | — | — |
| Ashapuri SwastikVarad Developers | Due Apr 2030, extended 4 mo | — | — |
| Orchid OasisNashik Housing & Area Development Board, Nashik | Due Jan 2031, extended 4 mo | — | — |
| Primrose PlazaNashik Housing & Area Development Board, Nashik | Due Sep 2030, extended 4 mo | — | — |
| Shobha AishwaryaShobha Samanth Buildtech | Due Apr 2028, extended 4 mo | — | — |
| Shramvaibhav Co-Operative Housing Society LtdHiray & Jagtap Associates | Due Apr 2029, extended 4 mo | — | — |
| Starlight sanctuaryNashik Housing and Area Development Board | Due Mar 2031, extended 4 mo | — | — |
| Yunus ResidencyThe Graph Properties | Due Nov 2030, extended 4 mo | — | — |
| Avighna ParkP G A Enterprises | Due Jul 2029, extended 4 mo | — | — |
Localities in Nashik
- Nashik1,372 projects
- Nashik (M Corp.)1,251 projects
- Nashik301 projects
- Aanandwali94 projects
- Deolaligaon67 projects
- Nashik Road67 projects
- Satpur56 projects
- Jail Road55 projects
- Deolali (Cb)50 projects
- Makhmalabad45 projects
- Pathardi37 projects
- Adgaon30 projects
All 103 localities
- Nashik Shiwar29
- Sinnar(M Cl)29
- Igatpuri (M Cl)28
- Vihitgaon28
- Kamatwade25
- Mhasrul25
- Bhagur Rural24
- Indiranagar24
- Sansari24
- Pimpalgaon Baswant23
- Chehedi Bk22
- Ozar (Ct)22
- Chandshi21
- Sinnar21
- Sinnar16
- Malegaon (M Corp.)15
- Wadala Shivar15
- Igatpuri14
- Gangapur13
- Chunchale10
- Dasak10
- Dindori10
- Jalalpur9
- Shinde9
- Belatgavhan8
- Palse8
- Ambad Khurd7
- Kasbe Vani7
- Lasalgaon7
- Panchak7
- Pimprisado7
- Bhagur (M Cl)6
- Gondedumala6
- Govardhan5
- Niphad5
- Satana4
- Malegaon3
- Niphad3
- Saikheda3
- Shramik Nagar3
- Trimbakeshwar3
- Yeola3
- Chandvad (Ct)2
- Dindori2
- Ghoti Bk. (Ct)2
- Girnare2
- Kawanai2
- Manmad (M Cl)2
- Naigaon2
- Nilgavhan2
- Ozar Gaon2
- Sangameshwar (Ct)2
- Saradwadi2
- Shivaji Nagar2
- Soyagaon (Ct)2
- Trimbakeshwar2
- Agartakli1
- Ashok Nagar1
- Behed1
- Beladgavhan1
- Borivali1
- Deola1
- Deshwandi1
- Gaulane1
- Gitakunj1
- Jaulke(Dindori)1
- Kasbe Sukene1
- Khambale1
- Madsangvi1
- Maparwadi1
- More Nagar1
- Mungsara1
- Naikwadi1
- Nandadgaon1
- Nandgaon1
- Pakhal Road1
- Pardevi1
- Pimpalgaon Bahula1
- Pimpalgaon Garudeshwar1
- Pimpalgaon Ketaki1
- Pimpalgaon Najik (Ct)1
- Satpur Colony1
- Surgana1
- Talegaon1
- Talegaon(Dindori)1
- Titoli1
- Trimbak (M Cl)1
- Umarane1
- Vilholi1
- Vinchur1
- Wasali1
Other districts
Most active promoters
- Roongta Homes Llp26 projects
- Jay Developers13 projects
- Kbc Global Limited12 projects
- Sanklecha Construction Private Limited11 projects
- Shah Builders And Developers11 projects
- Nashik Housing And Area Development Board10 projects
- Shreeji Life Space10 projects
- Deepak Kalyanji Chande9 projects
- Govinda Construction9 projects
- Sun Infrastructures Pvt. Ltd9 projects
Nashik, in questions
How many projects in Nashik run late?
7 in 10 MahaRERA registrations (3,098 of 4,253): their completion date was extended or has passed, data through 15 Nov 2026.
Where does this data come from?
From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Nashik by Deedo. Medians on fewer than 3 deeds are not shown.
Data through15 Nov 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology