8,415 MahaRERA projects in 36 districts are past their promised completion date, and MahaRERA shows no completion for them.

Most overdue first

Late: the latest completion date MahaRERA records (promised, or revised by an extension) has passed. Months late count from the first promised date. Page 70 of 169.

ProjectLocalityPromisedRevisedDelivery
Swami DarshanGeetai FoundationKhuntavaliThaneAug 2023Aug 20243 yrs 3 mo late
Tower A to E on CTS 4853, 4853 9 to 85 and 88 of village kole kalyan taluka andheriA A Estates Pvt LtdAndheriMumbai SuburbanAug 2023Aug 20233 yrs 3 mo late
Tower F and G on CTS 4853, 4853 9 to 85 and 88 of village kole kalyan taluka andheriA A Estates Pvt LtdAndheriMumbai SuburbanAug 2023Aug 20233 yrs 3 mo late
Vedant Pooja ApartmentPravin Balasaheb KedarSinnar(M Cl)NashikAug 2023Aug 20233 yrs 3 mo late
Shree ApartmentVaibhavi Builders And DevelopersLatur (M Cl)LaturAug 2023Aug 20233 yrs 3 mo late
Bhakti ResidencyYash AssociatesBaramati (M Cl)PuneAug 2023Aug 20233 yrs 3 mo late
Kamal HiraFourways InfrastructureAndheriMumbai SuburbanAug 2023Dec 20253 yrs 3 mo late
Matoshri TowerShri Builders And DevelopersIndiranagarNashikAug 2023Aug 20233 yrs 3 mo late
New Laxmi Bhavan Wing ASantacruz Laxminarayan TempleAndheriMumbai SuburbanAug 2023Aug 20233 yrs 3 mo late
Sushma ParkReena Roshan ShethWahalRaigarhAug 2023Aug 20233 yrs 3 mo late
Tulsai ApartmentOmprakash Vijaykumar RathiKhamgaon (M Cl)BuldanaAug 2023Aug 20233 yrs 3 mo late
Amrutshilp ApartmentBalaji Controctor And DevelopersLatur (Rural)LaturSep 2023Sep 20233 yrs 2 mo late
Dharti apartmentPrithviraj Kakade Constructions PVT LTDUjalaiwadi (Ct)KolhapurSep 2023Sep 20233 yrs 2 mo late
Saurabh Residency Wing DAshiana Builders and DevelopersUkrulRaigarhSep 2023Jun 20263 yrs 2 mo late
Shyam VrindavanSatnam Sakhi const LLPUlhasnagarThaneSep 2023Sep 20233 yrs 2 mo late
Saroj Vihar ApartmentRajashree DevelopersNashikSep 2023Sep 20233 yrs 2 mo late
Shivshakti Apartment 2Sanjay PatilVasaivirar City (M Corp)PalgharSep 2023Sep 20233 yrs 2 mo late
Shree Krushnai-IShree Siddhivinayak EnterprisesAjivaliRaigarhSep 2023Sep 20243 yrs 2 mo late
Shreepad Nakhate TowersRamesh Haribhau LabadeRahataniPuneSep 2023Sep 20233 yrs 2 mo late
Vedant Bhakti ApartmentVaijayanta V Nagare and Kamal E Shelke partner of BHAKTI CONSTRUCTIONSinnar(M Cl)NashikSep 2023Sep 20233 yrs 2 mo late
Kadam ResidencySwakarma Builders & DevelopersRatnagiriSep 2023Sep 20233 yrs 2 mo late
Riddhi Siddhi ApartmentDinesh Ramrao DolareAmravati (M Corp.)AmravatiSep 2023—3 yrs 2 mo late
Om Sahil SolitaireOm Sahil SolitaireWard FsouthMumbai CitySep 2023Sep 20233 yrs 2 mo late
Durga HeightsD S AssociatesHaveliPuneSep 2023Sep 20233 yrs 2 mo late
230/1 Shukrwar PethLiyakat Usman ShaikhShukrawar PethPuneSep 2023Sep 20233 yrs 2 mo late
Shivansh ResidencySankalp DeveloperKivalePuneSep 2023Sep 20233 yrs 2 mo late
24 RatnamAum DevelopersPune (M Corp.)PuneSep 2023Sep 20233 yrs 2 mo late
Aastha ResidencyAastha DevelopersLahagaonPuneSep 2023Sep 20233 yrs 2 mo late
Abc PalladiumKrish Realtors Private LimitedMahalungePuneSep 2023Sep 20233 yrs 2 mo late
Anand DhamVHS DevelopersDombivliThaneSep 2023Sep 20233 yrs 2 mo late
AnutamTruly Highdreams Realtors LLPAndheriMumbai SuburbanSep 2023Sep 20263 yrs 2 mo late
Audumber ChayaLaxmi DevelopersLanja (Ct)RatnagiriSep 2023Sep 20253 yrs 2 mo late
Balaji SaiPrakash Shankar KoliUlaweRaigarhSep 2023Sep 20233 yrs 2 mo late
Blue Fortuna Phase IIAtul Projects India Private LimitedAndheriMumbai SuburbanSep 2023Nov 20253 yrs 2 mo late
Chandan NagarNarendra Sonule & 3 Others Ramesh SonuleWardhaSep 2023Dec 20253 yrs 2 mo late
Chitra C.h.s LtdChitra Chs LtdMumbaiMumbai SuburbanSep 2023Sep 20243 yrs 2 mo late
Elite ResidencyBuildcity DevelopersUlaweRaigarhSep 2023Sep 20243 yrs 2 mo late
Falak CityFalak ConstructionGoregaonRaigarhSep 2023Mar 20263 yrs 2 mo late
Ganga Shankar HeightsVikrant Anil TurekarVadghar (Ct)RaigarhSep 2023Sep 20263 yrs 2 mo late
Gaurav Nagari 3PMG AssociatesRajoliChandrapurSep 2023Sep 20233 yrs 2 mo late
Geetaban Residency Phase-2Bhaishree Ventures LLPSawangiAurangabadSep 2023Mar 20243 yrs 2 mo late
Golden Palms- Phase 2 A WingGeeta Vidhyai ConstructionsBhukumPuneSep 2023Sep 20243 yrs 2 mo late
High Rise PearlNew High Rise ConstructionsNagpur (M Corp.)NagpurSep 2023Sep 20233 yrs 2 mo late
Hari Nakshatra Phase IIShree Sainath Land & Development (India) Private LimitedDeolaligaonNashikSep 2023Sep 20233 yrs 2 mo late
Icon GalaxyIcon EnterprisesVadghar (Ct)RaigarhSep 2023Sep 20233 yrs 2 mo late
Integrated ArcadeSadgurukrupa DevelopersKurlaMumbai SuburbanSep 2023Mar 20263 yrs 2 mo late
Ishwar NagarMahesh Keshardasji Batra And Firoz Faruk HusainYavatmalSep 2023Sep 20233 yrs 2 mo late
James Cottage Co-Operative Housing Society LtdShrusti RealtorsNaupadaThaneSep 2023Sep 20233 yrs 2 mo late
Jashraj ClassicShripatii Realtors Pvt LtdNavi Mumbai (M Corp.)ThaneSep 2023Dec 20243 yrs 2 mo late
Kalantri PlazaShree DevelopersBhiwandi (M Corp.)ThaneSep 2023Dec 20253 yrs 2 mo late

Delayed projects by district

SourcesMahaRERA registrations, extension certificates, project pages and document listsA project counts as completed when MahaRERA shows it so: its status, or a completion or occupancy certificate in its documents. Dates are MahaRERA's; Deedo does not know the day a project was handed over.Report a problemMethodology