8 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.

RERA projects6
Registrations6
Completion still due24 past their date
Median extension34 months83% of registrations extended
Regulatory cases0none on MahaRERA's lists

8 in 10 registrations run late here

6 MahaRERA registrations in Ukrul

1 not yet due1 extended, not yet due4 past even the latest date

Extended registrations moved their completion date by a median of 34 months.

Projects in Ukrul

6 projects registered with MahaRERA.

ProjectDeliveryMedian ₹/sq ftBooked
Saurabh Residency Wing DAshiana Builders and Developers3 yrs 2 mo late—35%
sai cityVenture HeightsDue Apr 2029, extended 4 mo—20%
Maple GreensThe SilwantCompleted, extended 2 yrs 7 mo—54%
Blossom Homes IFeroze Ahamed ShaikhDue Jun 2027—19%
Saurabh ResidencyAshiana Builders & Developers6 yrs 11 mo late—63%
All 6 projects →
Ukrul market reportPDF: prices and rents, volumes, projects ranked by deals and the most delayed — with the latest exact salesSee what's inside · from ₹1,999

Most active promoters

  1. Ashiana Builders & Developers3 projects
  2. Feroze Ahamed Shaikh1 project
  3. The Silwant1 project
  4. Venture Heights1 project

Ukrul, in questions

How many projects in Ukrul run late?

8 in 10 MahaRERA registrations (5 of 6): their completion date was extended or has passed, data through 7 Oct 2026.

Where does this data come from?

From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Ukrul by Deedo. Medians on fewer than 3 deeds are not shown.

Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology