RERA projects in Dahiwali T. Waredi
16 projects under 22 MahaRERA registrations, registered 2017–2026. 14% have a completion date extended beyond the one promised.
Locality
16RERA projects
22Registrationssome projects hold several
10Completion still due12 past their completion date
29 monthsMedian extension beyond promised date14% of registrations extended
0Regulatory casesnone on MahaRERA's lists
1Buildings on recordfrom registration certificates
Registrations per year
New MahaRERA registrations by registration date.
| Year | Registrations |
|---|---|
| 2017 | 7 |
| 2018 | 3 |
| 2019 | 8 |
| 2020 | 0 |
| 2021 | 1 |
| 2022 | 1 |
| 2023 | 1 |
| 2024 | 0 |
| 2025 | 0 |
| 2026 | 1 |
Projects in Dahiwali T. Waredi
16 projects registered with MahaRERA.
| Project | RERA | Registered | Promised completion | Revised completion | Timing | Cases |
|---|---|---|---|---|---|---|
| Skyline riversideSkyline Millars Ltd | P52000053092, PR1270002502229 | 16 Oct 2023 | 31 Jul 2028 | — | Not yet due | 0 |
| Evergreen HeightsEvergreen Enterprises | P52000033141 | 9 Feb 2022 | 31 Dec 2024 | — | Promised date passed | 0 |
| Tarangan ResidencyBaliram Ganpat Deshmukh | P52000030063 | 29 Jul 2021 | 31 Dec 2022 | — | Promised date passed | 0 |
| Labdhi UmangLabdhi Homes LLP | P52000021819 | 29 Jul 2019 | 30 Dec 2027 | — | Not yet due | 0 |
| SAANJ CO OP HSG SOC PraposedShrikrishna Ramchandra Marathe | P52000019822 | 5 Mar 2019 | 30 Jun 2022 | 30 Jun 2024 | Extended 24 mo | 0 |
| Labdhi GardensLabdhi Lifestyle Limited | P52000019661, P52000019679, P52000019683 +3 | 20 Feb 2019 | 30 Dec 2027 | — | Not yet due | 0 |
| Gayatri KrupaGayatri Developers | P52000018789 | 5 Dec 2018 | 30 Apr 2023 | — | Promised date passed | 0 |
| Poojan Palacia A And B WingVed Developers | P52000018360 | 26 Oct 2018 | 30 May 2023 | — | Promised date passed | 0 |
| Vinayak Sankul Phase IM/S Vinayak Associates | P52000016291 | 2 May 2018 | 30 Oct 2022 | — | Promised date passed | 0 |
| Sunshine Phase IIMubin Mohammed Iqbal Jumani | P52000012800 | 7 Sep 2017 | 31 Mar 2019 | — | Promised date passed | 0 |
| Sunrise hillssamir manohar mantri | P52000012589 | 4 Sep 2017 | 25 May 2018 | 30 Oct 2020 | Extended 29 mo | 0 |
| Rosabella Building Number 2Svs Groups | P52000007466 | 17 Aug 2017 | 31 Jul 2018 | — | Promised date passed | 0 |
| The Mist -Phase IGeeCee Ventures Limited | P52000007101 | 17 Aug 2017 | 30 Sep 2020 | — | Promised date passed | 0 |
| Hillside SpaceSpace Housing | P52000006003 | 14 Aug 2017 | 30 Dec 2022 | — | Promised date passed | 0 |
| Blue BaySonde Builders & Developers Private Limited | P52000005297 | 11 Aug 2017 | 31 Dec 2026 | 31 Dec 2026 | Not yet due | 0 |
| Shreeji AuraShreeji Realtors | P52000005330 | 11 Aug 2017 | 30 Jun 2019 | 30 Jun 2023 | Extended 48 mo | 0 |
Other localities in Karjat
Most active promoters
By projects registered here, as named on MahaRERA.
- Baliram Ganpat Deshmukh1 project
- Evergreen Enterprises1 project
- Gayatri Developers1 project
- GeeCee Ventures Limited1 project
- Labdhi Homes LLP1 project
- Labdhi Lifestyle Limited1 project
- M/S Vinayak Associates1 project
- Mubin Mohammed Iqbal Jumani1 project
- samir manohar mantri1 project
- Shreeji Realtors1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology