Pashane, Raigarh
6 in 10 MahaRERA registrations here have pushed their completion date back.
RERA projects33
Registrations38some projects hold several
Completion still due1226 past their date
Median extension12 months61% of registrations extended
Regulatory cases3on 3 projects
10 in 10 registrations run late here
38 MahaRERA registrations in Pashane
2 not yet due10 extended, not yet due26 past even the latest date
Extended registrations moved their completion date by a median of 12 months.
Projects in Pashane
33 projects registered with MahaRERA.
| Project | Delivery | Median ₹/sq ft | Booked |
|---|---|---|---|
| Gagangiri ParkGagangiri Group | Due Aug 2029, extended 4 mo | — | — |
| Virat Greenwoods Wing B & DVraj Realty | Due Apr 2030, extended 4 mo | — | — |
| Ashtavinayak ComplexAshtavinayak Enterprises | Due Apr 2030, extended 4 mo | — | — |
| Galaxy VrundavanShree Krishna Enterprises | Due Apr 2033, extended 4 mo | — | 0% |
| Tulsi VedantShubh Developers | Due Apr 2029, extended 4 mo | — | 0% |
| Dhruv Residency PlatinumKamlesh Devidas Dhruv | Due Apr 2027, extended 4 mo | — | 17% |
| Gagangiri ComplexGagangiri Developers | 1 yr 10 mo late | — | 77% |
| Virat Greenwoods Wing EVraj Realty | 2 yrs 10 mo late | — | 3% |
| Vaastu SankalpVaastu Enteprises | Due Dec 2026 | — | — |
| Sai Enrich HillsSai Infra Builders And Developers | 10 mo late | — | 0% |
| Vande Mataram DivineSadguru Shelter | 2 yrs 10 mo late | — | 66% |
| Wellwisher TulipAbhijeet Chandrakant Bhansali | Due Sep 2027, extended 3 yrs 1 mo | — | 11% |
| Wellwisher CosmosWellwisher Developer | 2 yrs 2 mo late | — | 0% |
| Wellwisher IrisHimgiri Dealcom LLP | Due Oct 2030, extended 4 mo | — | 0% |
| Wellwisher RoseHimgiri Dealcom LLP | 2 yrs 4 mo late | — | 0% |
| Wellwisher SunflowerAbhijeet Chandrakant Bhansali | 2 yrs 4 mo late | — | 0% |
| Galaxygarden Plot No 2 And Plot No 4S K Developers | 7 mo late | — | 83% |
| Virat GreenwoodsVraj Realty | 2 yrs 10 mo late | — | 32% |
| Tulsi V City - Tulsi VivaanRAJ REALTORS (A project by Raj Group) | 5 yrs 1 mo late | — | 72% |
| Shree Samarth ResidencyShree Samarth Infra Developers | 5 yrs 11 mo late | — | 15% |
| Dhruv Residency-NxKpz Enterprise | 4 yrs 7 mo late | — | 84% |
| Himalaya GardensHimalaya Builders And Developers LLP | Due Mar 2027 | — | 84% |
| Gurudev ParkGurudev Enterprises | 5 yrs 11 mo late | — | 0% |
| Vardhaman ResidencyGeetadevi Bimleshkumar Jain | 5 yrs 4 mo late | — | 99% |
| Sai ManasSai Smaran infra and Developers | 7 yrs 10 mo late | — | 100% |
Nearby: other localities in Karjat
Most active promoters
- Vraj Realty3 projects
- Abhijeet Chandrakant Bhansali2 projects
- Himalaya Builders And Developers LLP2 projects
- Himgiri Dealcom LLP2 projects
- S K Developers2 projects
- Ashtavinayak Enterprises1 project
- DeepJyoti Infra1 project
- Dhruv Associates1 project
- Gagangiri Developers1 project
- Gagangiri Group1 project
Data through21 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Methodology