Virat Greenwoods
Completion date passedPashane, Raigarh 410201 |Promoter: Vraj Realty
Project summary
As registered with MahaRERA
- RERA registrations
- 2
- Phases
- 2
Location
Coordinates as published by MahaRERA
Also registered as
Unit mix, parking, construction progress and the project's professionals come from that page. You can open it on MahaRERA (it asks for a CAPTCHA).
Latest registered deals
Completion timeline
Registration date, the completion date promised at registration, and any extension since
Completion promised for 30 Dec 2022
P52000017471The latest completion date on record passed 3 years and 10 months ago.
- Registered
- 13 Aug 2018
- Promised
- 30 Dec 2022
Completion promised for 30 Dec 2023
P52000022839The latest completion date on record passed 2 years and 10 months ago.
- Registered
- 30 Oct 2019
- Promised
- 30 Dec 2023
2 RERA registrations
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P52000017471 | 13 Aug 2018 | 30 Dec 2022 | — | Vraj Realty | Project page |
| P52000022839 | 30 Oct 2019 | 30 Dec 2023 | — | Vraj Realty | Project page |
Documents
2 documents held by Deedo
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Regulatory record
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
Land
In Pashane
Survey, CTS, gat or plot numbers
Source: registration certificates, as stated there.