Completion was pushed back 5 months to May 2025, and that date has passed too; no MahaRERA orders on record; 77% of its units are booked.

Pashane, Raigarh 410101 · by Gagangiri Developers

Delivery1 yr 11 mo latePromised Dec 2024 · revised May 2025 · that date has passed tooRegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales77% booked54 of 70 units · as the promoter reported to MahaRERA

Buying a flat here?

See every deed registered on it.

Completion was pushed back 5 months to May 2025, and that date has passed too

  • This projectRegistered 29 Jul 2021, completion promised 31 Dec 2024, revised to 31 May 2025, and still not shown completed today.

1 extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales, rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

5 buildings

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP52000030075
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5200003007529 Jul 202131 Dec 202431 May 2025Gagangiri DevelopersProject page
Documents103

3 documents held by Deedo, 100 filings listed on MahaRERA's project page

Registration certificate

Extension certificate

Other

  • OtherDate not statedView

Finance

  • PAN CardFIRM PAN CARD.pdf · uploaded 13 Jul 2021Source

Legal

  • OtherCREDAI CERTIFICATE.pdf · uploaded 13 Jul 2021Source
  • OtherDEVELOPMENT AGREEMENT PART 1.pdf · uploaded 13 Jul 2021Source
  • OtherDEVELOPMENT AGREEMENT PART 2.pdf · uploaded 13 Jul 2021Source
  • OtherDEVELOPMENT AGREEMENT PART 3.pdf · uploaded 13 Jul 2021Source
Show all 103 documentsShow fewer documents

Legal

  • OtherDEVELOPMENT AGREEMENT PART 4.pdf · uploaded 13 Jul 2021Source
  • OtherDEATH CERTIFICATE.pdf · uploaded 13 Jul 2021Source
  • OtherAFFIDAVIT.pdf · uploaded 13 Jul 2021Source
  • Legal Title reportLEGAL TITLE REPORT.pdf · uploaded 13 Jul 2021Source
  • Declaration Form BFORM B.pdf · uploaded 13 Jul 2021Source
  • Declaration Form BFORM B REVISED FINAL.pdf · uploaded 26 Dec 2024Source
  • Declaration Form BFORM B REVISED GAGANGIRI.pdf · uploaded 17 Mar 2025Source

Migrated

  • 1 PAN CardFIRM PAN CARD.pdf · uploaded 13 Jul 2021Source
  • 1 Copy of the legal title reportLEGAL TITLE REPORT.pdf · uploaded 13 Jul 2021Source
  • 1 Details of encumbrancesENCUMBRANCE LETTER.pdf · uploaded 13 Jul 2021Source
  • 1 Commencement Certificates / NA Order for plotted developmentC C PART 1.pdf · uploaded 13 Jul 2021Source
  • 2 Commencement Certificates / NA Order for plotted developmentC C PART 2.pdf · uploaded 13 Jul 2021Source
  • 3 Commencement Certificates / NA Order for plotted developmentC C PART 3.pdf · uploaded 13 Jul 2021Source
  • 1 Declaration in FORM BFORM B.pdf · uploaded 13 Jul 2021Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)ARCHITECT CERTIFICATE.pdf · uploaded 13 Jul 2021Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)ENGINEER CERTIFICATE.pdf · uploaded 13 Jul 2021Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA CERTIFICATE.pdf · uploaded 13 Jul 2021Source
  • 1 Proforma of Allotment letterDRAFT ALLOTMENT LETTER.pdf · uploaded 13 Jul 2021Source
  • 2 Proforma of Allotment letterDRAFT AGREEMENT.pdf · uploaded 13 Jul 2021Source
  • 1 OtherCREDAI CERTIFICATE.pdf · uploaded 13 Jul 2021Source
  • 2 OtherDEVELOPMENT AGREEMENT PART 1.pdf · uploaded 13 Jul 2021Source
  • 3 OtherDEVELOPMENT AGREEMENT PART 2.pdf · uploaded 13 Jul 2021Source
  • 4 OtherDEVELOPMENT AGREEMENT PART 3.pdf · uploaded 13 Jul 2021Source
  • 5 OtherDEVELOPMENT AGREEMENT PART 4.pdf · uploaded 13 Jul 2021Source
  • 6 OtherDEATH CERTIFICATE.pdf · uploaded 13 Jul 2021Source
  • 7 OtherAFFIDAVIT.pdf · uploaded 13 Jul 2021Source
  • 1 Copy of Layout Approval (in case of layout)BUILDING LAYOUT PLAN.pdf · uploaded 14 Jul 2021Source
  • 1 Building Plan Approval / NA Order for plotted developmentBUILDING LAYOUT PLAN.pdf · uploaded 14 Jul 2021Source
  • 1 Declaration about Commencement CertificateC C DECLARATION.pdf · uploaded 14 Jul 2021Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)FORM 5 FY 2021-22 GAGANGIRI COMPLEX.pdf · uploaded 5 Apr 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)FORM 5 GAGANGIRI COMPLEX.pdf · uploaded 2 Mar 2024Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)FROM 5 GAGANGIRI COMPLEX.pdf · uploaded 6 Dec 2024Source
  • 1 Declaration in FORM BFORM B REVISED FINAL.pdf · uploaded 26 Dec 2024Source
  • 9 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 ARCHITECH CERTIFICATE.pdf · uploaded 26 Dec 2024Source
  • 9 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3 CA CERTIFICATE FINAL.pdf · uploaded 26 Dec 2024Source
  • 9 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 ENGINEER CERTIFICATE.pdf · uploaded 26 Dec 2024Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)FORM 2A ENGINEER CERTIFICATE.pdf · uploaded 26 Dec 2024Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)5 FORM 1 ARCHITECT 31 3 2023.pdf · uploaded 18 Feb 2025Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)6 FORM 1 ARCHITECT 30 6 2023.pdf · uploaded 18 Feb 2025Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)7 FORM 1 ARCHITECT 30 9 2023.pdf · uploaded 18 Feb 2025Source
  • 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)8 FORM 1 ARCHITECT 31 12 2023.pdf · uploaded 18 Feb 2025Source
  • 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)1 FORM 1 ARCHITECT 31 3 2024.pdf · uploaded 18 Feb 2025Source
  • 6 Architect’s Certificate of Percentage of Completion of Work (Form 1)2 FORM 1 ARCHITECT 30 6 2024.pdf · uploaded 18 Feb 2025Source
  • 7 Architect’s Certificate of Percentage of Completion of Work (Form 1)3 FORM 1 ARCHITECT 30 9 2024.pdf · uploaded 18 Feb 2025Source
  • 8 Architect’s Certificate of Percentage of Completion of Work (Form 1)4 FORM 1 ARCHITECT 31 12 2024.pdf · uploaded 18 Feb 2025Source
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)3 FORM 3 CA CERT 30 9 2023.pdf · uploaded 18 Feb 2025Source
  • 8 CA Certificate on Project Cost & Fund withdrawal (Form 3)12 FORM 3 CA CERT 31 12 2024.pdf · uploaded 18 Feb 2025Source
  • 7 CA Certificate on Project Cost & Fund withdrawal (Form 3)11 FORM 3 CA CERT 30 9 2024.pdf · uploaded 18 Feb 2025Source
  • 6 CA Certificate on Project Cost & Fund withdrawal (Form 3)10 FORM 3 CA CERT 30 6 2024.pdf · uploaded 18 Feb 2025Source
  • 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)9 FORM 3 CA CERT 31 3 2024.pdf · uploaded 18 Feb 2025Source
  • 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)4 FORM 3 CA CERT 31 12 2023.pdf · uploaded 18 Feb 2025Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)2 FORM 3 CA CERT 30 6 2023.pdf · uploaded 18 Feb 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)1 FORM 3 CA CERT 31 3 2023.pdf · uploaded 18 Feb 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)9 FORM 2 ENGINEER 31 3 2023.pdf · uploaded 18 Feb 2025Source
  • 8 Engineer’s Certificate on Cost Incurred on Project (Form 2)8 FORM 2 ENGINEER 31 12 2024.pdf · uploaded 18 Feb 2025Source
  • 7 Engineer’s Certificate on Cost Incurred on Project (Form 2)7 FORM 2 ENGINEER 30 9 2024.pdf · uploaded 18 Feb 2025Source
  • 6 Engineer’s Certificate on Cost Incurred on Project (Form 2)6 FORM 2 ENGINEER 30 6 2024.pdf · uploaded 18 Feb 2025Source
  • 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)5 FORM 2 ENGINEER 31 3 2024.pdf · uploaded 18 Feb 2025Source
  • 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)12 FORM 2 ENGINEER 31 12 2023.pdf · uploaded 18 Feb 2025Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)11 FORM 2 ENGINEER 30 9 2023.pdf · uploaded 18 Feb 2025Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)10 FORM 2 ENGINEER 30 6 2023.pdf · uploaded 18 Feb 2025Source
  • 1 Disclosure of sold/ booked inventory14 SOLD UNSOLD UPDATE 31 3 2023.pdf · uploaded 18 Feb 2025Source
  • 2 Disclosure of sold/ booked inventory15 SOLD UNSOLD UPDATE 30 6 2023.pdf · uploaded 18 Feb 2025Source
  • 3 Disclosure of sold/ booked inventory16 SOLD UNSOLD UPDATE 30 9 2023.pdf · uploaded 18 Feb 2025Source
  • 4 Disclosure of sold/ booked inventory17 SOLD UNSOLD UPDATE 31 12 2023.pdf · uploaded 18 Feb 2025Source
  • 5 Disclosure of sold/ booked inventory14 SOLD UNSOLD UPDATE 31 3 2024.pdf · uploaded 18 Feb 2025Source
  • 6 Disclosure of sold/ booked inventory15 SOLD UNSOLD UPDATE 30 6 2024.pdf · uploaded 18 Feb 2025Source
  • 7 Disclosure of sold/ booked inventory16 SOLD UNSOLD UPDATE 30 9 2024.pdf · uploaded 18 Feb 2025Source
  • 8 Disclosure of sold/ booked inventory17 SOLD UNSOLD UPDATE 31 12 2024.pdf · uploaded 18 Feb 2025View
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)13 FORM 2A ENGINEER 31 3 2023.pdf · uploaded 18 Feb 2025Source
  • 1 Declaration in FORM BFORM B REVISED GAGANGIRI.pdf · uploaded 17 Mar 2025Source
  • 1 Other – TechnicalENGINEER LETTER FOR CPM PERT.pdf · uploaded 17 Mar 2025Source

Technical

  • DocumentBUILDING LAYOUT PLAN.pdf · uploaded 14 Jul 2021Source
  • DocumentBUILDING LAYOUT PLAN.pdf · uploaded 14 Jul 2021Source
  • Other – TechnicalENGINEER LETTER FOR CPM PERT.pdf · uploaded 17 Mar 2025Source

Technical (Architect)

  • DocumentARCHITECT CERTIFICATE.pdf · uploaded 13 Jul 2021Source
  • DocumentFORM 1 ARCHITECH CERTIFICATE.pdf · uploaded 26 Dec 2024Source
  • Document5 FORM 1 ARCHITECT 31 3 2023.pdf · uploaded 18 Feb 2025Source
  • Document6 FORM 1 ARCHITECT 30 6 2023.pdf · uploaded 18 Feb 2025Source
  • Document7 FORM 1 ARCHITECT 30 9 2023.pdf · uploaded 18 Feb 2025Source
  • Document8 FORM 1 ARCHITECT 31 12 2023.pdf · uploaded 18 Feb 2025Source
  • Document1 FORM 1 ARCHITECT 31 3 2024.pdf · uploaded 18 Feb 2025Source
  • Document2 FORM 1 ARCHITECT 30 6 2024.pdf · uploaded 18 Feb 2025Source
  • Document3 FORM 1 ARCHITECT 30 9 2024.pdf · uploaded 18 Feb 2025Source
  • Document4 FORM 1 ARCHITECT 31 12 2024.pdf · uploaded 18 Feb 2025Source

Technical (Engineer)

  • DocumentENGINEER CERTIFICATE.pdf · uploaded 13 Jul 2021Source
  • DocumentFORM 2 ENGINEER CERTIFICATE.pdf · uploaded 26 Dec 2024Source
  • Document9 FORM 2 ENGINEER 31 3 2023.pdf · uploaded 18 Feb 2025Source
  • Document10 FORM 2 ENGINEER 30 6 2023.pdf · uploaded 18 Feb 2025Source
  • Document11 FORM 2 ENGINEER 30 9 2023.pdf · uploaded 18 Feb 2025Source
  • Document12 FORM 2 ENGINEER 31 12 2023.pdf · uploaded 18 Feb 2025Source
  • Document5 FORM 2 ENGINEER 31 3 2024.pdf · uploaded 18 Feb 2025Source
  • Document6 FORM 2 ENGINEER 30 6 2024.pdf · uploaded 18 Feb 2025Source
  • Document7 FORM 2 ENGINEER 30 9 2024.pdf · uploaded 18 Feb 2025Source
  • Document8 FORM 2 ENGINEER 31 12 2024.pdf · uploaded 18 Feb 2025Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel 175/1C, SURVEY NO. 175/1B

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Unit types
1BHK, 1RK, Shop70 units in all
Address
SURVEY NO. 175/1B AND 175/1C, Survey No.175/1B and 175/1C, Village - Pashane, Vangani (w)PIN 410101
Village
Pashane, Karjat taluka
Land area for this project
1,700 sq m (18,299 sq ft)
Permissible built-up area
1,955 sq m (21,043 sq ft)
Sanctioned built-up area
1,955 sq m (21,043 sq ft)
Designated bank account
85
Developed in phases
Yes

Survey, CTS, gat or plot numbers

175/1CSURVEY NO. 175/1B

Land as published on MahaRERA's project page

SURVEY NO. 175/1B AND 175/1C

Boundaries

North
Survey No 232
South
Survey No 234 - 1a
East
Survey No 233
West
Survey No 234 - 1k

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking70 units

54 of 70 units booked (77%), as the promoter reported to MahaRERA

1BHK · 20 units1RK · 36 unitsShop · 14 units
BuildingTypeCarpet areaUnitsBooked
A-Wing1BHK35 sq m · 377 sq ft44
A-Wing1BHK36.56 sq m · 394 sq ft44
A-Wing1RK23.8 sq m · 256 sq ft86
A-Wing1RK23.82 sq m · 256 sq ft43
A-Wing1RK24.45 sq m · 263 sq ft44
A-Wing1RK24.8 sq m · 267 sq ft44
A-WingShop5.83 sq m · 63 sq ft22
A-WingShop8.45 sq m · 91 sq ft11
Show all 20 unit rowsShow fewer unit rows
BuildingTypeCarpet areaUnitsBooked
A-WingShop11.21 sq m · 121 sq ft33
A-WingShop12.42 sq m · 134 sq ft11
B-Wing1BHK35 sq m · 377 sq ft42
B-Wing1BHK36.56 sq m · 394 sq ft43
B-Wing1BHK37.11 sq m · 399 sq ft42
B-Wing1RK23.8 sq m · 256 sq ft87
B-Wing1RK23.82 sq m · 256 sq ft43
B-Wing1RK24.8 sq m · 267 sq ft43
B-WingShop5.83 sq m · 63 sq ft20
B-WingShop8.45 sq m · 91 sq ft10
B-WingShop11.21 sq m · 121 sq ft32
B-WingShop12.42 sq m · 134 sq ft10

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals3

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectNeeta Associates—
Chartered accountantYogesh Nanda And Associates—
EngineerShree Samarth Krupa Associates—

Source: MahaRERA project page. Contact details are not shown.

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Report a problemMethodology