Deedo IDDL-RAI-DIKSAL9 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.
RERA projects7
Registrations7
Completion still due25 past their date
Median extension36 months71% of registrations extended
Regulatory cases0none on MahaRERA's lists
9 in 10 registrations run late here
7 MahaRERA registrations in Diksal
1 not yet due1 extended, not yet due5 past even the latest date
Extended registrations moved their completion date by a median of 36 months.
Projects in Diksal
7 projects registered with MahaRERA.
| Project | Delivery | Median ₹/sq ft | Booked |
|---|---|---|---|
| Nisarg ApartmentRaj Construction | 2 yrs 11 mo late | — | 40% |
| Shree Ganesh ResidencyArth Realtors | Due Jun 2027, extended 3 yrs | — | 10% |
| Tulsi LandmarkTulsi Buildcon | 2 yrs 11 mo late | — | 41% |
| Manas Shrushti ComplexPrakash Govind Gaikwad | 6 yrs 11 mo late | — | 57% |
| Florence TownBright Developers | Due Dec 2028 | — | — |
Nearby: other villages in Karjat
Most active promoters
- Arth Realtors1 project
- Bright Developers1 project
- Prakash Govind Gaikwad1 project
- Raj Construction1 project
- Santosh Ramesh Raut1 project
- Tulsi Buildcon1 project
- Tulsi Unison1 project
Diksal, in questions
How many projects in Diksal run late?
9 in 10 MahaRERA registrations (6 of 7): their completion date was extended or has passed, data through 7 Oct 2026.
Where does this data come from?
From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Diksal by Deedo. Medians on fewer than 3 deeds are not shown.
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology