Skip to content

Tulsi Landmark

Certificate Signed

Diksal, Raigarh 410201 |Promoter: Tulsi Buildcon

30 Nov 2018Registered with MahaRERA
25 Dec 2023Promised completion
4Buildings
97Units registered40 booked (41%)
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA and published on its project page

Project type
Others
Status on MahaRERA
Certificate Signed
Buildings
4
Unit types
1BHK, 1RK, Shop, 1 BHK, 2BHK, 1 RK97 units in all
Address
19/12, At Diksal Village, Bhivpuri RoadPIN 410201
Designated bank account
212
Developed in phases
Yes

Location

Coordinates as published by MahaRERA

View on OpenStreetMap 18.96857, 73.33111
Tulsi Landmark is at latitude 18.96857, longitude 73.33111.

Registered transactions

No registered transactions matched to this project yetSales, resales, rentals and mortgages appear here once registered documents are matched to this project by evidence.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion promised for 25 Dec 2023

The latest completion date on record passed 2 years and 10 months ago.

Registered
30 Nov 2018
Promised
25 Dec 2023

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5200001875930 Nov 201825 Dec 202325 Dec 2023Tulsi BuildconProject page

4 buildings

Buildings and wings named in the registration

BuildingSanctioned floorsUnits
Wing A522
Wing B528
Wing C525
Wing D522

Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.

Units and parking

40 of 97 units booked (41%), as the promoter reported to MahaRERA

1BHK · 16 units1RK · 19 unitsShop · 33 units1 BHK · 17 units2BHK · 3 units1 RK · 9 units
BuildingTypeCarpet areaUnitsBooked
Wing A1BHK28.77 sq m · 310 sq ft32
Wing A1BHK31.06 sq m · 334 sq ft33
Wing A1BHK31.21 sq m · 336 sq ft33
Wing A1RK20.6 sq m · 222 sq ft44
Wing A1RK21.24 sq m · 229 sq ft11
Wing A1RK22.1 sq m · 238 sq ft11
Wing A1RK22.25 sq m · 239 sq ft11
Wing AShop10.92 sq m · 118 sq ft21
Show all 48 unit rowsShow fewer unit rows
BuildingTypeCarpet areaUnitsBooked
Wing AShop14.3 sq m · 154 sq ft20
Wing AShop15.34 sq m · 165 sq ft21
Wing B1 BHK31.06 sq m · 334 sq ft44
Wing B1 BHK38.8 sq m · 418 sq ft11
Wing B1BHK28.77 sq m · 310 sq ft33
Wing B1RK16.73 sq m · 180 sq ft30
Wing B1RK18.45 sq m · 199 sq ft20
Wing B1RK19.4 sq m · 209 sq ft33
Wing B2BHK49.07 sq m · 528 sq ft22
Wing BShop10.92 sq m · 118 sq ft20
Wing BShop11.07 sq m · 119 sq ft10
Wing BShop14.16 sq m · 152 sq ft10
Wing BShop14.3 sq m · 154 sq ft20
Wing BShop15.08 sq m · 162 sq ft20
Wing BShop17.76 sq m · 191 sq ft10
Wing BShop18.54 sq m · 200 sq ft10
Wing C1 BHK28.77 sq m · 310 sq ft30
Wing C1BHK31.06 sq m · 334 sq ft41
Wing C1 RK19.4 sq m · 209 sq ft22
Wing C1RK16.77 sq m · 181 sq ft30
Wing C1RK18.45 sq m · 199 sq ft10
Wing C2BHK49.07 sq m · 528 sq ft11
Wing CShop10.92 sq m · 118 sq ft21
Wing CShop14.3 sq m · 154 sq ft21
Wing CShop11.07 sq m · 119 sq ft10
Wing CShop14.16 sq m · 152 sq ft10
Wing CShop15.08 sq m · 162 sq ft20
Wing CShop15.34 sq m · 165 sq ft10
Wing CShop17.76 sq m · 191 sq ft10
Wing CShop18.54 sq m · 200 sq ft10
Wing D1 BHK28.77 sq m · 310 sq ft30
Wing D1 BHK31.06 sq m · 334 sq ft30
Wing D1 BHK31.21 sq m · 336 sq ft30
Wing D1 RK20.6 sq m · 222 sq ft40
Wing D1 RK21.24 sq m · 229 sq ft10
Wing D1 RK22.1 sq m · 238 sq ft10
Wing D1 RK22.25 sq m · 239 sq ft10
Wing DShop10.92 sq m · 118 sq ft21
Wing DShop14.3 sq m · 154 sq ft22
Wing DShop15.34 sq m · 165 sq ft21

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Documents

1 document held by Deedo, 36 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN CardPAN CARD.PDF · uploaded 7 Oct 2018Source

Legal

  • Legal Title reportLegal Title Certificate.PDF · uploaded 7 Oct 2018Source
  • Otherdevelopment agreement (2).pdf · uploaded 8 Oct 2018Source
  • Otherpower of attorney.pdf · uploaded 8 Oct 2018Source
  • Declaration Form Baffidavit form b1.pdf · uploaded 8 Oct 2018Source

Migrated

  • 1 PAN CardPAN CARD.PDF · uploaded 7 Oct 2018Source
  • 1 Copy of the legal title reportLegal Title Certificate.PDF · uploaded 7 Oct 2018Source
Show all 37 documentsShow fewer documents

Migrated

  • 1 Building Plan Approval (IOD)na order plan copy 1.pdf · uploaded 8 Oct 2018Source
  • 2 Building Plan Approval (IOD)na order plan copy 2.pdf · uploaded 8 Oct 2018Source
  • 3 Building Plan Approval (IOD)na order plan copy 3.pdf · uploaded 8 Oct 2018Source
  • 1 Commencement Certificates / NA Order for plotted developmentna order.pdf · uploaded 8 Oct 2018Source
  • 1 Declaration in FORM Baffidavit form b1.pdf · uploaded 8 Oct 2018Source
  • 1 Otherdevelopment agreement (2).pdf · uploaded 8 Oct 2018Source
  • 2 Otherpower of attorney.pdf · uploaded 8 Oct 2018Source
  • 1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Form 1.pdf · uploaded 29 Oct 2018Source
  • 1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)RCC CONSULTANT RERA LETTER.pdf · uploaded 21 Nov 2018Source
  • 1 Certificates of CA (Form 3)C A LETTER.pdf · uploaded 21 Nov 2018Source
  • 1 Details of encumbrancesNON ENCUMBRANCES CERTIFICATE.pdf · uploaded 22 Nov 2018Source
  • 1 Copy of Layout Approval (in case of layout)na order plan copy 1.pdf · uploaded 22 Nov 2018Source
  • 1 Proforma of Allotment letterAGREEMENT FOR SALE.pdf · uploaded 22 Nov 2018Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)Form 5.pdf · uploaded 18 Nov 2019Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)Sold Inventory Shop Tulsi Landmark.pdf · uploaded 11 Jul 2021Source
  • 1 Disclosure of sold/ booked inventorySold Inventory Flat Tulsi Landmark.pdf · uploaded 11 Jul 2021Source
  • 2 Disclosure of sold/ booked inventoryUnsold Inventory Flat Tulsi Landmark.pdf · uploaded 11 Jul 2021Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)RERA Form 5.pdf · uploaded 24 Aug 2021Source
  • 1 CERSAI detailsCERSAI_Search_Report_200231984399_For_Debtor_Based_Search_09_03_2022_15_43_21_131.pdf · uploaded 9 Mar 2022Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)RERA Form 5 (1).pdf · uploaded 9 Mar 2022Source
  • 2 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)FORM 5 01-04-2021 to 31-03-2022.pdf · uploaded 19 Apr 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)FORM 5 01-04-2021 to 31-03-2022.pdf · uploaded 19 Apr 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)FORM 5 STAMPED.pdf · uploaded 14 Oct 2023Source

Technical

  • Documentna order plan copy 1.pdf · uploaded 8 Oct 2018Source
  • Documentna order plan copy 2.pdf · uploaded 8 Oct 2018Source
  • Documentna order plan copy 3.pdf · uploaded 8 Oct 2018Source
  • Documentna order plan copy 1.pdf · uploaded 22 Nov 2018Source

Technical (Architect)

  • DocumentForm 1.pdf · uploaded 29 Oct 2018Source

Technical (Engineer)

  • DocumentRCC CONSULTANT RERA LETTER.pdf · uploaded 21 Nov 2018Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Diksal, Karjat taluka

Survey, CTS, gat or plot numbers

19/12

Boundaries

North
Commercial Shop
South
Village House
East
Opp Bhivpuri Railway Station
West
Village House

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectDestination Architecture Interior Designs—
EngineerK R Patel & Associate—

Source: MahaRERA project page. Contact details are not shown.

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Methodology