RERA projects in Kothimbe
7 projects under 7 MahaRERA registrations, registered 2017–2026. 57% have a completion date extended beyond the one promised.
Locality
7RERA projects
7Registrations
5Completion still due2 past their completion date
4 monthsMedian extension beyond promised date57% of registrations extended
1Regulatory caseson 1 project
151Buildings on recordfrom registration certificates
Registrations per year
New MahaRERA registrations by registration date.
| Year | Registrations |
|---|---|
| 2017 | 2 |
| 2018 | 0 |
| 2019 | 0 |
| 2020 | 0 |
| 2021 | 1 |
| 2022 | 0 |
| 2023 | 1 |
| 2024 | 0 |
| 2025 | 2 |
| 2026 | 1 |
Projects in Kothimbe
7 projects registered with MahaRERA.
| Project | RERA | Registered | Promised completion | Revised completion | Timing | Cases |
|---|---|---|---|---|---|---|
| Motiram PicassoPadmaja Infra Ventures | PR1270002502572 | 2 Mar 2026 | 31 Dec 2030 | 30 Apr 2031 | Extended 4 mo | 0 |
| The Morning StarM/S Mahadev Realty | PM1270002500244 | 10 Jul 2025 | 31 Dec 2030 | 30 Apr 2031 | Extended 4 mo | 0 |
| GoodlifeHbpl-Apapbn Jv | P52000079493 | 10 Mar 2025 | 30 Dec 2028 | 30 Apr 2029 | Extended 4 mo | 0 |
| Celeste VillasBuild Marque Realty LLP | P52000050001 | 6 Mar 2023 | 31 Dec 2027 | 31 Dec 2027 | Not yet due | 0 |
| My ElementSantosh Mayurendra Bhiwandkar | P52000028772 | 30 Mar 2021 | 30 Jun 2025 | 30 Jun 2025 | Promised date passed | 0 |
| Bella CasaVision Realty | P52000013404 | 4 Oct 2017 | 31 Dec 2018 | 31 Dec 2025 | Extended 84 mo | 0 |
| SukoonGreensspaces | P52000007698 | 17 Aug 2017 | 31 Dec 2028 | 31 Dec 2028 | Not yet due | 1 |
Other localities in Karjat
Most active promoters
By projects registered here, as named on MahaRERA.
- Build Marque Realty LLP1 project
- Greensspaces1 project
- Hbpl-Apapbn Jv1 project
- M/S Mahadev Realty1 project
- Padmaja Infra Ventures1 project
- Santosh Mayurendra Bhiwandkar1 project
- Vision Realty1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology