Deedo IDDP-RAI-DACZIt is due for completion in Dec 2027, with no extension on record; no MahaRERA orders on record; 25% of its units are booked.
Kothimbe, Raigarh 410201 · by Build Marque Realty LLP
Buying a flat here?
See every deed registered on it.
It is due for completion in Dec 2027, with no extension on record
- This projectRegistered 6 Mar 2023, completion promised 31 Dec 2027.
No extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales, rentals and mortgages matched to this project · the free view shows a price band
16 buildings
Open a building to see every flat, floor by floor.
- Type A-11 floor · 1 unit100% booked
- Type A-21 floor · 1 unit100% booked
- Type B-11 floor · 1 unit100% booked
- Type B-101 floor · 1 unit100% booked
- Type B-111 floor · 1 unit0% booked
- Type B-21 floor · 1 unit0% booked
- Type B-31 floor · 1 unit0% booked
- Type B-41 floor · 1 unit0% booked
- Type B-51 floor · 1 unit0% booked
- Type B-61 floor · 1 unit0% booked
- Type B-71 floor · 1 unit0% booked
- Type B-81 floor · 1 unit0% booked
Show all 16 buildingsShow fewer buildings
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP52000050001
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P52000050001 | 6 Mar 2023 | 31 Dec 2027 | 31 Dec 2027 | Build Marque Realty LLP | Project page |
Documents96
1 document held by Deedo, 95 filings listed on MahaRERA's project page
Finance
- PAN Card01 Pan Card Build Marque Reality.pdf · uploaded 17 Nov 2022Source
Legal
- Declaration Form BFORM B FAZAL AHMED SHAIKH.pdf · uploaded 17 Nov 2022Source
- Declaration Form BFORM B ISTYAK AHMED NABI SHAH.pdf · uploaded 17 Nov 2022Source
- Declaration Form BFORM B SHAHAB SAAQIB ALTAF ANDRABI SYED.pdf · uploaded 17 Nov 2022Source
- Declaration Form BFORM B SIDDIQUI WASIM AHMED.pdf · uploaded 17 Nov 2022Source
- Declaration Form BFORM B ZAHEER ABBAS.pdf · uploaded 17 Nov 2022Source
- Declaration Form BFORM B ZAIN ALTAF SYED.pdf · uploaded 17 Nov 2022Source
Show all 96 documentsShow fewer documents
Legal
Migrated
- 1 PAN Card01 Pan Card Build Marque Reality.pdf · uploaded 17 Nov 2022Source
- 1 Copy of Layout Approval (in case of layout)05 Layout Approval.pdf · uploaded 17 Nov 2022Source
- 1 Building Plan Approval / NA Order for plotted development06 NA ORDER.pdf · uploaded 17 Nov 2022Source
- 1 Commencement Certificates / NA Order for plotted development06 NA ORDER.pdf · uploaded 17 Nov 2022Source
- 1 Declaration in FORM BFORM B FAZAL AHMED SHAIKH.pdf · uploaded 17 Nov 2022Source
- 2 Declaration in FORM BFORM B ISTYAK AHMED NABI SHAH.pdf · uploaded 17 Nov 2022Source
- 3 Declaration in FORM BFORM B SHAHAB SAAQIB ALTAF ANDRABI SYED.pdf · uploaded 17 Nov 2022Source
- 4 Declaration in FORM BFORM B SIDDIQUI WASIM AHMED.pdf · uploaded 17 Nov 2022Source
- 5 Declaration in FORM BFORM B ZAHEER ABBAS.pdf · uploaded 17 Nov 2022Source
- 6 Declaration in FORM BFORM B ZAIN ALTAF SYED.pdf · uploaded 17 Nov 2022Source
- 7 Declaration in FORM BFORM B ZEESHAN MANZOOR KHAN.pdf · uploaded 17 Nov 2022Source
- 1 Declaration about Commencement CertificateDeclaration about Commencement Certificate.pdf · uploaded 21 Nov 2022Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 - Architect Certificate Kothimbe.pdf · uploaded 21 Nov 2022Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 RERA Engineer Certificate.pdf · uploaded 21 Nov 2022Source
- 1 Proforma of Allotment letterBMR Allotment Letter Form.pdf · uploaded 21 Nov 2022Source
- 1 Deviation Report with respect to Allotment letterDeviation report with respect to allotment letter.pdf · uploaded 21 Nov 2022Source
- 1 CERSAI detailsUndertaking regarding no security interest.pdf · uploaded 29 Nov 2022Source
- 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameDeclaration about Separate Bank Account.pdf · uploaded 29 Nov 2022Source
- 1 a Details of encumbrances concerned to FinanceNo encumbrance certificate.pdf · uploaded 5 Dec 2022Source
- 2 a Details of encumbrances concerned to FinanceNo encumbrance certificate.pdf · uploaded 5 Dec 2022Source
- 1 b Details of encumbrances concerned to LegalNo encumbrance certificate.pdf · uploaded 5 Dec 2022Source
- 2 b Details of encumbrances concerned to LegalNo encumbrance certificate.pdf · uploaded 5 Dec 2022Source
- 1 Disclosure of Interest in Other Real Estate OrganizationsFAZAL AHMED SHAIKH-1.pdf · uploaded 20 Jan 2023Source
- 2 Disclosure of Interest in Other Real Estate OrganizationsISTYAK AHMED NABI SHAH-1.pdf · uploaded 20 Jan 2023Source
- 3 Disclosure of Interest in Other Real Estate OrganizationsSHAHAB SAAQIB ALTAF ANDRABI SYED.pdf · uploaded 20 Jan 2023Source
- 4 Disclosure of Interest in Other Real Estate OrganizationsSIDDIQUI WASIM AHMED-1.pdf · uploaded 20 Jan 2023Source
- 5 Disclosure of Interest in Other Real Estate OrganizationsZAHEER ABBAS-1.pdf · uploaded 20 Jan 2023Source
- 6 Disclosure of Interest in Other Real Estate OrganizationsZAIN ALTAF SYED-1.pdf · uploaded 20 Jan 2023Source
- 7 Disclosure of Interest in Other Real Estate OrganizationsZEESHAN MANZOOR KHAN-1.pdf · uploaded 20 Jan 2023Source
- 1 Deviation Report with respect to model copy of AgreementDeviation Report in Agreement for sale.pdf · uploaded 16 Feb 2023Source
- 1 Copy of the legal title reportLegal Title Report.pdf · uploaded 23 Feb 2023Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3 NEW COMPRESS.pdf · uploaded 23 Feb 2023Source
- 1 Proforma of Agreement for saleNew Draft Agreement For Sale.pdf · uploaded 23 Feb 2023Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form - 1 Architect Certificate.pdf · uploaded 26 Jan 2024Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form - 2 - Build Marque Reality.pdf · uploaded 26 Jan 2024Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM3.pdf · uploaded 26 Jan 2024Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)FORM 5.pdf · uploaded 26 Jan 2024Source
- 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 (ARTITECT'S CERTIFICATE Q2).pdf · uploaded 14 Mar 2024Source
- 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 (ARTITECT'S CERTIFICATE Q3).pdf · uploaded 14 Mar 2024Source
- 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 (ARTITECT'S CERTIFICATE Q4).pdf · uploaded 14 Mar 2024Source
- 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 (ENGINEER CERTIFICATE Q2).pdf · uploaded 14 Mar 2024Source
- 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 (ENGINEER CERTIFICATE Q3).pdf · uploaded 14 Mar 2024Source
- 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 (ENGINEER CERTIFICATE Q4).pdf · uploaded 14 Mar 2024Source
- 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 Q2.pdf · uploaded 14 Mar 2024Source
- 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 Q3_11zon.pdf · uploaded 14 Mar 2024Source
- 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 Q4.pdf · uploaded 14 Mar 2024Source
- 2 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)Form 5 2022-23.pdf · uploaded 14 Mar 2024Source
- 6 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 Architect Certificate Q1.pdf · uploaded 23 Apr 2024Source
- 6 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Engineer Certificate Q1.pdf · uploaded 23 Apr 2024Source
- 6 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 Chartered Accountants Q1_11zon.pdf · uploaded 23 Apr 2024Source
- 1 Disclosure of sold/ booked inventorybmr.pdf · uploaded 25 Apr 2024Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)FORM 2A (Engineer's Certificate on Quality Assurance Submitted Annually).pdf · uploaded 2 May 2024Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)form 5.pdf · uploaded 2 May 2024Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 Build Marque 3 Quarter 2024.pdf · uploaded 18 Oct 2024Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM-2 QPR3 Sep24_compressed.pdf · uploaded 18 Oct 2024Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 BUILD MARQUE 4 QUARTER-compressed.pdf · uploaded 9 Apr 2025Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)July To Sept 2024.pdf · uploaded 9 Apr 2025Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Oct To Dec 2024.pdf · uploaded 9 Apr 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)NEW DOC 02-14-2025.pdf · uploaded 9 Apr 2025Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Build Marque form 1 Quarter 1 2025.pdf · uploaded 22 Apr 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer certificate.pdf · uploaded 22 Apr 2025Source
- Withdrawal Update Form 1Withdrawal Application Form1.pdf · uploaded 8 Oct 2025Source
- Withdrawal Update Form 1Withdrawal Application Form1.pdf · uploaded 8 Oct 2025Source
- Withdrawal Update Form 2Annexure B Form 2.pdf · uploaded 8 Oct 2025Source
- Withdrawal Update Form 2Annexure B Form 2.pdf · uploaded 8 Oct 2025Source
- Withdrawal Update Form 3BMR CA Certificate form 3 q3.pdf · uploaded 8 Oct 2025Source
- Withdrawal Update Form 3BMR CA Certificate form 3 q3.pdf · uploaded 8 Oct 2025Source
- Withdrawal Update Form 1Form 1 Jan 26 signed (1).pdf · uploaded 20 Feb 2026Source
- Withdrawal Update Form 2Form 2 Jan 26 (1).pdf · uploaded 20 Feb 2026Source
- Withdrawal Update Form 3Form 3 Jan 26 (1).pdf · uploaded 20 Feb 2026Source
- Withdrawal Update Form 1Form 1 March 2026.pdf · uploaded 29 May 2026Source
- Withdrawal Update Form 2Form 2 March 2026.pdf · uploaded 29 May 2026Source
- Withdrawal Update Form 3Form 3 March 2026.pdf · uploaded 29 May 2026Source
- Withdrawal Update Form 1Architect withdrawal Form 1 Q126_compressed.pdf · uploaded 17 Aug 2026Source
- Withdrawal Update Form 2Form 2 March 2026.pdf · uploaded 17 Aug 2026Source
- Withdrawal Update Form 3Withdrawal Application Form 3 q126_compressed.pdf · uploaded 17 Aug 2026Source
Technical
Technical (Architect)
- DocumentForm 1 Build Marque 3 Quarter 2024.pdf · uploaded 18 Oct 2024Source
- DocumentFORM 1 BUILD MARQUE 4 QUARTER-compressed.pdf · uploaded 9 Apr 2025Source
- DocumentBuild Marque form 1 Quarter 1 2025.pdf · uploaded 22 Apr 2025Source
- DocumentArchitect withdrawal Form 1 Q126_compressed.pdf · uploaded 17 Aug 2026Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsLand parcel SURVEY NO 80 H NO 3 PLOT NO 1 TO 16
As registered with MahaRERA and published on its project page
- Project type
- Residential / Group Housing
- Status on MahaRERA
- Certificate Signed
- Unit types
- —16 units in all
- Address
- Survey No 80 H No 3 Plot No 1 To 16, Survey No 80, H No 3PIN 410201
- Village
- Kothimbe, Karjat taluka
- Location
- 18.99839, 73.43562
- Land area for this project
- 5,400 sq m (58,125 sq ft)
- Permissible built-up area
- 1,960 sq m (21,094 sq ft)
- Sanctioned built-up area
- 1,960 sq m (21,094 sq ft)
- Recreational open space
- 540 sq m (5,813 sq ft)
- Designated bank account
- 76
- Developed in phases
- Yes
Survey, CTS, gat or plot numbers
Land as published on MahaRERA's project page
SURVEY NO 80 H NO 3 PLOT NO 1 TO 16
Boundaries
- North
- 18 Mtrs Odr Road
- South
- S No 80 H No 5
- East
- S No 80 H No 4
- West
- S No 79
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking16 units
16 units registered
| Building | Type | Carpet area | Units |
|---|---|---|---|
| Type A-1 | — | — | 1 |
| Type A-2 | — | — | 1 |
| Type B-1 | — | — | 1 |
| Type B-10 | — | — | 1 |
| Type B-11 | — | — | 1 |
| Type B-2 | — | — | 1 |
| Type B-3 | — | — | 1 |
| Type B-4 | — | — | 1 |
Show all 16 unit rowsShow fewer unit rows
| Building | Type | Carpet area | Units |
|---|---|---|---|
| Type B-5 | — | — | 1 |
| Type B-6 | — | — | 1 |
| Type B-7 | — | — | 1 |
| Type B-8 | — | — | 1 |
| Type B-9 | — | — | 1 |
| Type C-1 | — | — | 1 |
| Type D-1 | — | — | 1 |
| Type E-1 | — | — | 1 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals4
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Anup Suresh Salvi | — |
| Chartered accountant | Arsalaan Shaikh | — |
| Chartered accountant | Ganesh Krishna Bhoir | — |
| Engineer | Shreeshail Gaikwad | — |
Source: MahaRERA project page. Contact details are not shown.