Skip to content

RERA projects in Bopele

43 projects under 43 MahaRERA registrations, registered 2017–2026. 40% have a completion date extended beyond the one promised.

Locality
43RERA projects
43Registrations
9Completion still due34 past their completion date
12 monthsMedian extension beyond promised date40% of registrations extended
1Regulatory caseson 1 project
72Buildings on recordfrom registration certificates

Registrations per year

New MahaRERA registrations by registration date.

MahaRERA registrations per year
YearRegistrations
201719
20185
20194
20201
20215
20222
20231
20243
20251
20262

Projects in Bopele

43 projects registered with MahaRERA.

ProjectRERARegisteredPromised completionRevised completionTimingCases
Rajkumari ApartmentShiv Construction CompanyPM127000260129924 Jul 202631 Dec 202830 Apr 2029Extended 4 mo0
Vrushti PalacioVrushti EnterprisesPR12700026006838 Jun 202631 Dec 202830 Apr 2029Extended 4 mo0
Sonu Shree BalajiLaxmi BuildconP5200008049411 Jun 20258 Oct 20288 Feb 2029Extended 4 mo0
Balaji ResidencyBalaji Builders And DevelopersP5200006651411 Jun 202431 Dec 202531 Dec 2025Promised date passed0
Omega PlazaNoorul Azad Mohd Anwar KhanP5200006654011 Jun 202431 Dec 2027—Not yet due1
Vatsalya ApartmentM/S. Rehan DevelopersP520000546986 Feb 202431 Dec 202730 Apr 2028Extended 4 mo0
Pranill Shree GaneshaPranill Constrobuild LLPP5200005023727 Mar 202331 Mar 202631 Jul 2026Extended 4 mo0
Shiv PratimaFly DevelopersP520000479121 Dec 202230 Jun 202430 Jun 2024Promised date passed0
Anand VillaDarshana Shantaram MohiteP5200003346422 Feb 202231 Mar 202431 Dec 2027Extended 45 mo0
Sharda Sadan ApartmentVaastu Space AssociatesP520000305911 Sep 202131 Dec 202431 Dec 2024Promised date passed0
Meenarch ApartmentSteve Danny KinyP5200003015731 Jul 202131 Mar 202331 Mar 2023Promised date passed0
Laxmi Castello Phase-II, B1, A-Wing, B2, B-WingLaxmi GlobalP5200002899323 Apr 202131 Dec 202130 Jun 2022Extended 6 mo0
Shree Baa NiwasShree Baa BuildwellsP5200002868325 Mar 202130 Jun 202329 Jun 2024Extended 12 mo0
Shree Samarth ApartmentAbhishek Ravindra MogalP520000284142 Mar 202130 Mar 202430 Mar 2024Promised date passed0
Balaji KrupaBalaji DevelopersP5200002523723 Mar 202030 Jun 202630 Jun 2026Promised date passed0
Shree Hingad ChandraHingad DevelopersP520000225361 Oct 201921 May 202231 Dec 2024Extended 31 mo0
Shree Samarth AvenueShree Samarth RealtyP520000219188 Aug 201930 Dec 202230 Dec 2022Promised date passed0
Shree Samarth EnclaveShree Samarth RealtyP5200002139826 Jun 201930 Dec 202230 Dec 2022Promised date passed0
Skyland ResidencyGaurav KachharaP5200002081510 May 201930 May 202230 May 2022Promised date passed0
Anand ParkNarendra Sopan DahitankarP5200001693422 Jun 201831 Dec 202630 Apr 2027Extended 4 mo0
jewel heaven phase 1Jewel Builders and Infraprojects LtdP5200001597610 Apr 201830 Jun 202130 Dec 2022Extended 18 mo0
Alpine HeritageAlpine Skyscrapers LLPP520000154941 Mar 201831 Dec 201931 Mar 2022Extended 27 mo0
Piyush ApartmentPiyush EnterprisesP5200001543523 Feb 201830 Nov 201930 Nov 2019Promised date passed0
Sai ShraddhaBalaji EnterprisesP520000151967 Feb 201831 Dec 201930 Jun 2022Extended 30 mo0
Kajal PrideDeepak Bhaichand ShahP520000145358 Dec 201731 Dec 201931 Dec 2019Promised date passed0

Other localities in Karjat

Most active promoters

By projects registered here, as named on MahaRERA.

  1. Laxmi Global2 projects
  2. Shree Samarth Realty2 projects
  3. Abhishek Ravindra Mogal1 project
  4. Adesh Enterprises1 project
  5. Alpine Skyscrapers LLP1 project
  6. Balaji Builders And Developers1 project
  7. Balaji Developers1 project
  8. Balaji Enterprises1 project
  9. Darshana Shantaram Mohite1 project
  10. Deepak Bhaichand Shah1 project
Data through21 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology