Residential / Group Housing · 1 building · 16 unitsRERA P52000015494

Alpine Heritage

Deedo IDDP-RAI-RTKJ

Completion was pushed back 2 years and 3 months to Mar 2022, and that date has passed too; no MahaRERA orders on record; 63% of its units are booked.

Bopele, Raigarh 410101 · Promoter: Alpine Skyscrapers LLP

Delivery6 yrs 10 mo latePromised Dec 2019 · revised Mar 2022 · that date has passed tooRegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales63% booked10 of 16 units · as the promoter reported to MahaRERA
Alpine Heritage project report cardPDF: delivery, regulatory orders, people on record, every tower and the registered deals — for your bank or lawyerSee what's inside · from ₹1,499

Completion was pushed back 2 years and 3 months to Mar 2022, and that date has passed too

  • This projectRegistered 1 Mar 2018, completion promised 31 Dec 2019, revised to 31 Mar 2022, and still not shown completed today.

1 extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales, rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

The building

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP52000015494
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P520000154941 Mar 201831 Dec 201931 Mar 2022Alpine Skyscrapers LLPProject page
Documents61

2 documents held by Deedo, 59 filings listed on MahaRERA's project page

Registration certificate

Extension certificate

Finance

  • PAN CardALPINE PANCARD.pdf · uploaded 21 Jul 2021Source

Legal

  • Declaration Form BFORM B.pdf · uploaded 21 Feb 2018Source
  • Legal Title reporttitle.pdf · uploaded 21 Feb 2018Source

Migrated

  • 1 Certificates of CA (Form 3)CA.pdf · uploaded 20 Feb 2018Source
  • 1 Copy of the legal title reporttitle.pdf · uploaded 21 Feb 2018Source
  • 1 Details of encumbrancesFORM B.pdf · uploaded 21 Feb 2018Source
Show all 61 documentsShow fewer documents

Migrated

  • 1 Copy of Layout Approval (in case of layout)layout.pdf · uploaded 21 Feb 2018Source
  • 1 Building Plan Approval (IOD)CC.pdf · uploaded 21 Feb 2018Source
  • 1 Declaration in FORM BFORM B.pdf · uploaded 21 Feb 2018Source
  • 1 Proforma of Allotment letterDRAFT SALE AGREEMENT SAMPLE.pdf · uploaded 22 Feb 2018Source
  • 1 Commencement Certificates / NA Order for plotted developmentCC.pdf · uploaded 23 Mar 2018Source
  • 2 Certificates of CA (Form 3)FORM 3 30062019.pdf · uploaded 16 Jan 2020Source
  • 3 Certificates of CA (Form 3)FORM 3 30092019.pdf · uploaded 16 Jan 2020Source
  • 4 Certificates of CA (Form 3)FORM 3 30122019.pdf · uploaded 16 Jan 2020Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)FORM-5 FY17-18.pdf · uploaded 16 Jan 2020Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)FORM-5 FY18-19.pdf · uploaded 16 Jan 2020Source
  • 1 PAN CardALPINE PANCARD.pdf · uploaded 21 Jul 2021Source
  • 1 Declaration about Commencement CertificateCommence Certificate Plinth.pdf · uploaded 21 Jul 2021Source
  • 5 Certificates of CA (Form 3)31032021.pdf · uploaded 21 Jul 2021Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)ARCHITECT CERTIFICATE 10JULY21.pdf · uploaded 23 Jul 2021Source
  • 1 Disclosure of sold/ booked inventoryAnnexure A.pdf · uploaded 23 Jul 2021Source
  • 6 Certificates of CA (Form 3)march 2020.pdf · uploaded 23 Jul 2021Source
  • 7 Certificates of CA (Form 3)june 2020.pdf · uploaded 23 Jul 2021Source
  • 8 Certificates of CA (Form 3)sept 2020.pdf · uploaded 23 Jul 2021Source
  • 9 Certificates of CA (Form 3)dec 2020.pdf · uploaded 23 Jul 2021Source
  • 10 Certificates of CA (Form 3)march 2021.pdf · uploaded 23 Jul 2021Source
  • 11 Certificates of CA (Form 3)june 2021.pdf · uploaded 23 Jul 2021Source
  • 2 Commencement Certificates / NA Order for plotted developmentCC PLINTH.pdf · uploaded 12 Aug 2021Source
  • 2 Declaration about Commencement CertificateFORMAT-D DECLARATION ABOUT PROMOTER COMMENCEMENT CERTITIFICATE.pdf · uploaded 12 Aug 2021Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)JAN-FEB-MAR-2020-FORM-2.pdf · uploaded 12 Aug 2021Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)APR-MAY-JUN-2020-FORM-2.pdf · uploaded 12 Aug 2021Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)JUL-AUG-SEP-2020-FORM-2.pdf · uploaded 12 Aug 2021Source
  • 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)OCT-NOV-DEC-2020-FORM-2.pdf · uploaded 12 Aug 2021Source
  • 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)JAN-FEB-MAR-2021-FORM-2.pdf · uploaded 12 Aug 2021Source
  • 6 Engineer’s Certificate on Cost Incurred on Project (Form 2)APR-MAY-JUN-2021-FORM-2.pdf · uploaded 12 Aug 2021Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)FY-2019-2020-FORM-2A.pdf · uploaded 12 Aug 2021Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)FY-2020-2021-FORM-2A.pdf · uploaded 12 Aug 2021Source
  • 2 Disclosure of sold/ booked inventoryDisclosure of sold and Book Inventory.pdf · uploaded 12 Aug 2021Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)FORM-5 FY19-20.pdf · uploaded 12 Aug 2021Source
  • 3 Declaration about Commencement CertificateDeclaration Of Commencement Certificate.pdf · uploaded 24 Aug 2021Source
  • 1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentOC.pdf · uploaded 10 Aug 2022Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)CERTIFICATE OF ARCHITECT FORM 1.pdf · uploaded 4 May 2023Source
  • 7 Engineer’s Certificate on Cost Incurred on Project (Form 2)form 2 JUNE-JULY-AUG-2021.pdf · uploaded 8 May 2023Source
  • 8 Engineer’s Certificate on Cost Incurred on Project (Form 2)form 2 OCT -NOV -DEC -2021.pdf · uploaded 8 May 2023Source
  • 9 Engineer’s Certificate on Cost Incurred on Project (Form 2)form 2 JAN -FEB-MAR- 2022.pdf · uploaded 8 May 2023Source
  • 10 Engineer’s Certificate on Cost Incurred on Project (Form 2)form 2 APR -MAY-JUNE- 2022.pdf · uploaded 8 May 2023Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)form 2A 12-04-2022.pdf · uploaded 8 May 2023Source
  • 12 Certificates of CA (Form 3)FORM 3 30-6-21.pdf · uploaded 8 May 2023Source
  • 13 Certificates of CA (Form 3)FORM 3 31-12-21.pdf · uploaded 8 May 2023Source
  • 14 Certificates of CA (Form 3)form 3 30-09-21.pdf · uploaded 8 May 2023Source
  • 15 Certificates of CA (Form 3)FORM 3 31-12-21.pdf · uploaded 8 May 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)FORM 5 FY 20 -21_.pdf · uploaded 8 May 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)FORM 5 FY 21-22_.pdf · uploaded 8 May 2023Source
  • 3 Disclosure of sold/ booked inventoryAnnexure.pdf · uploaded 10 May 2023Source
  • 1 Architect’s Certificate on Completion of Project (Form 4)100 percent letter 1.pdf · uploaded 10 May 2023Source

Technical

  • DocumentCC.pdf · uploaded 21 Feb 2018Source
  • Documentlayout.pdf · uploaded 21 Feb 2018Source

Technical (Architect)

  • DocumentCERTIFICATE OF ARCHITECT FORM 1.pdf · uploaded 4 May 2023Source

Technical (Engineer)

  • Documentform 2 APR -MAY-JUNE- 2022.pdf · uploaded 8 May 2023Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsPlot No. 41, S.No.56

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Unit types
1BHK, 1RK16 units in all
Address
Plot No. 41, S.No.56PIN 410101
Village
Bopele, Karjat taluka
Designated bank account
159
Developed in phases
No

Survey, CTS, gat or plot numbers

Plot No. 41S.No.56

Boundaries

North
Plot No 42
South
6m Wide Internal Road
East
Plot No 3
West
9m Wide Internal Road

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking16 units

10 of 16 units booked (63%), as the promoter reported to MahaRERA

1BHK · 13 units1RK · 3 units
TypeCarpet areaUnitsBooked
1BHK20.7 sq m · 223 sq ft31
1BHK25.3 sq m · 272 sq ft33
1BHK26.5 sq m · 285 sq ft11
1BHK26.9 sq m · 290 sq ft62
1RK16.68 sq m · 180 sq ft33

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals5

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectChaitanya Kamalakar Shahasane—
Chartered accountantHr Khan—
Chartered accountantMaharajan Naidu—
EngineerAniruddha Consultant—
EngineerOptimum Consultants—

Source: MahaRERA project page. Contact details are not shown.

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Methodology