Bopele, Raigarh
Deedo IDDL-RAI-BOPELE10 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.
RERA projects44
Registrations44
Completion still due935 past their date
Median extension12 months39% of registrations extended
Regulatory cases1on 1 project
10 in 10 registrations run late here
44 MahaRERA registrations in Bopele
2 not yet due7 extended, not yet due35 past even the latest date
Extended registrations moved their completion date by a median of 12 months.
Projects in Bopele
44 projects registered with MahaRERA.
| Project | Delivery | Median ₹/sq ft | Booked |
|---|---|---|---|
| Riddhi Sidhhi ApartmentsGoldee Infrastructure | Completed | — | — |
| Aarsh ResidencyShubham Enterprises | Due Dec 2026, extended 3 yrs | — | 62% |
| Vrindavan ArcadeShreeji Enterprises | Completed | — | 31% |
| Saurabh ApartmentTarachand Hastimal Chhajed | Completed | — | — |
| Drishti ArcadeKrishna Enterprises | 7 yrs 11 mo late | — | 54% |
| Kum Kum BhagyaKum Kum Enterprises | Completed, extended 1 yr 6 mo | — | 100% |
| Sunrise Parkville AnnexUnnati Enterprises | Completed | — | 54% |
| Shashwat SankulSai Smaran Construction | Completed | — | 77% |
| Nano CityNirman Realtors And Developers Ltd | Due Dec 2029 | — | 44% |
| Maruti SankulOm Sai Developers | Completed, extended 2 yrs 7 mo | — | 81% |
| Siddhi EnterprisesSiddhi Enterprises | Completed | — | 44% |
| Vastu PoojaAdesh Enterprises | 3 yrs 6 mo late | — | 38% |
| Sai Durga HillsSai Durga Developers | Completed | — | 36% |
| Anika ApartmentMidas Construction | Completed | — | — |
| Rachana One UpRachana Value Homes Pvt Ltd | Completed | — | 89% |
| Laxmi CastelloLaxmi Global | Completed | — | 67% |
| Shree PoojaMangalam Buildcon | Completed | — | 98% |
| MangalyaIntegrate Infraspaces | Completed | — | 25% |
| Shree Hari Nisarg ResidencyShree Hari Realtors | Completed | — | 74% |
Nearby: other villages in Karjat
Most active promoters
- Laxmi Global2 projects
- Shree Samarth Realty2 projects
- Abhishek Ravindra Mogal1 project
- Adesh Enterprises1 project
- Alpine Skyscrapers Llp1 project
- Balaji Builders And Developers1 project
- Balaji Developers1 project
- Balaji Enterprises1 project
- Darshana Shantaram Mohite1 project
- Deepak Bhaichand Shah1 project
Bopele, in questions
How many projects in Bopele run late?
10 in 10 MahaRERA registrations (42 of 44): their completion date was extended or has passed, data through 21 Oct 2026.
Where does this data come from?
From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Bopele by Deedo. Medians on fewer than 3 deeds are not shown.
Data through21 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology