87 projects under 89 MahaRERA registrations, registered 2017–2026. 52% have a completion date extended beyond the one promised.
Locality
87RERA projects
89Registrationssome projects hold several
31Completion still due58 past their completion date
12 monthsMedian extension beyond promised date52% of registrations extended
1Regulatory caseson 1 project
185Buildings on recordfrom registration certificates
Registrations per year
New MahaRERA registrations by registration date.
| Year | Registrations |
|---|---|
| 2017 | 32 |
| 2018 | 13 |
| 2019 | 6 |
| 2020 | 5 |
| 2021 | 5 |
| 2022 | 3 |
| 2023 | 10 |
| 2024 | 7 |
| 2025 | 5 |
| 2026 | 3 |
Projects in Neral
87 projects registered with MahaRERA.
| Project | RERA | Registered | Promised completion | Revised completion | Timing | Cases |
|---|---|---|---|---|---|---|
| Sushrut AvenueBalaji Buildcon | PR1270002602351 | 16 Oct 2026 | 31 Dec 2031 | — | Not yet due | 0 |
| Renaissance Royal Phase IIShree Sharada Infrastructures | PR1271012600760 | 12 Jun 2026 | 31 Dec 2028 | 30 Apr 2029 | Extended 4 mo | 0 |
| Shree Balaji TowerBainsla Buildcon | PM1270002600237 | 21 Apr 2026 | 31 Dec 2030 | 30 Apr 2031 | Extended 4 mo | 0 |
| Asma TowerMujeeb Badruddin Ansari | PM1270002501288 | 20 Oct 2025 | 31 Dec 2029 | 30 Apr 2030 | Extended 4 mo | 0 |
| Saroj SerenityOlympeo Constructions Private Limited | PM1271012500916 | 23 Sep 2025 | 30 Jun 2030 | 30 Oct 2030 | Extended 4 mo | 0 |
| Shivamrut PlazaShivamrut Builder And Developer | PM1270002500518 | 7 Aug 2025 | 31 Dec 2027 | 30 Apr 2028 | Extended 4 mo | 0 |
| Shree Parshwanath ResidencyOm Sai Construction | PR1270002500113 | 23 Jun 2025 | 9 Feb 2027 | 9 Jun 2027 | Extended 4 mo | 0 |
| Shanti Lake ViewPadmavati Developers | P52000079251 | 18 Feb 2025 | 31 Mar 2027 | 31 Jul 2027 | Extended 4 mo | 0 |
| Amber NirvanaVn Buildtech | P52000078152 | 25 Nov 2024 | 31 Dec 2027 | 30 Apr 2028 | Extended 4 mo | 0 |
| Anand AaradhyaAaradhya Developers | P52000077187 | 29 Jul 2024 | 31 Mar 2027 | 31 Jul 2027 | Extended 4 mo | 0 |
| Swami SadanAnil Baburao Achrekar | P52000077172 | 29 Jul 2024 | 31 Dec 2026 | 30 Apr 2027 | Extended 4 mo | 0 |
| Shree Swami MountviewDhruvatan Realtors | P52000077039 | 16 Jul 2024 | 23 Jun 2028 | 23 Oct 2028 | Extended 4 mo | 0 |
| Green City Phase 1Sarah Builder & Developers Private Limited | P52000055706 | 15 Apr 2024 | 30 Jun 2028 | 30 Oct 2028 | Extended 4 mo | 0 |
| Mulla ResidencyZafar Mohd Rashid Mulla | P52000055346 | 18 Mar 2024 | 31 Dec 2026 | 30 Apr 2027 | Extended 4 mo | 0 |
| Prakash ComplexPankaj Prakash Sawant | P52000055204 | 11 Mar 2024 | 31 Mar 2029 | 31 Jul 2029 | Extended 4 mo | 0 |
| Avnit PlazaAvnit Enterprise | P52000051924 | 13 Jul 2023 | 31 Oct 2024 | 31 Oct 2025 | Extended 12 mo | 0 |
| Tower C-Mars,plutoDreamz Realty | P52000051852 | 7 Jul 2023 | 31 Dec 2030 | 30 Apr 2031 | Extended 4 mo | 0 |
| Harshita ApartmentPrashant Prakash Sawant | P52000051450 | 23 Jun 2023 | 28 Feb 2027 | 28 Jun 2027 | Extended 4 mo | 0 |
| Tower B-Jupiter, NeptuneDreamz Realty | P52000051000 | 19 May 2023 | 31 Dec 2030 | 30 Apr 2031 | Extended 4 mo | 0 |
| Raj HeightRajhas Enterprise | P52000050249 | 27 Mar 2023 | 30 Jun 2024 | 30 Jun 2024 | Promised date passed | 0 |
| Vansh HeightsNavkar Developers | P52000049810 | 24 Feb 2023 | 31 Mar 2028 | 31 Jul 2028 | Extended 4 mo | 0 |
| Shree Sai TowersM/S Brs Builders & Developers | P52000049335 | 7 Feb 2023 | 31 Dec 2024 | 31 Dec 2024 | Promised date passed | 0 |
| Shree Samarth ParadiseShree Samarth Residency | P52000049281 | 7 Feb 2023 | 31 Dec 2027 | 31 Dec 2027 | Not yet due | 0 |
| Tower A Mercury, VenusDreamz Realty | P52000049371 | 7 Feb 2023 | 31 Dec 2030 | 30 Apr 2031 | Extended 4 mo | 0 |
| Shree Sai ShambuSameer Lalchand Mhatre | P52000034675 | 20 Apr 2022 | 31 May 2027 | 31 May 2027 | Not yet due | 0 |
Other localities in Karjat
Most active promoters
By projects registered here, as named on MahaRERA.
- M/s. Seema Promoters And Builders Private Limited6 projects
- Shibam Associates4 projects
- Dreamz Realty3 projects
- M/S Brs Builders & Developers2 projects
- Navkar developers2 projects
- Nehaldhara Realtors2 projects
- Pankaj Prakash Sawant2 projects
- Prashant Prakash Sawant2 projects
- Shree Sharada Infrastructures2 projects
- 5P Developers1 project
Data through17 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology