Neral, Raigarh
Deedo IDDL-RAI-NERAL5 in 10 MahaRERA registrations here have pushed their completion date back.
RERA projects87
Registrations89some projects hold several
Completion still due3158 past their date
Median extension12 months52% of registrations extended
Regulatory cases1on 1 project
9 in 10 registrations run late here
89 MahaRERA registrations in Neral
7 not yet due24 extended, not yet due58 past even the latest date
Extended registrations moved their completion date by a median of 12 months.
Projects in Neral
87 projects registered with MahaRERA.
| Project | Delivery | Median ₹/sq ft | Booked |
|---|---|---|---|
| Ira ApartmentPrashant Prakash Sawant | Due Dec 2026 | — | — |
| Amber HeritageV N Developers | 1 yr 9 mo late | — | 87% |
| Pardeshi PlazaRajesh Shankar Pardeshi | 4 yrs 1 mo late | — | 54% |
| Mahalaxmi DarshanBharat Vishanji Patel | 2 yrs 4 mo late | — | 0% |
| Malhar HeightsMalhar Enterprises | Due Mar 2027, extended 4 yrs | — | 71% |
| Royal ParadiseZishan Builders And Developers | 3 yrs 11 mo late | — | 0% |
| Laxmi KiranKiran Enterprises | 2 yrs 4 mo late | — | 48% |
| Green FieldStonehard Builders And Developers LLP | 3 yrs 4 mo late | — | 47% |
| Buniyad ResidencyNasir Ibrahim Diwan | 3 yrs 4 mo late | — | 14% |
| Pushkar ApartmentPankaj Prakash Sawant | 3 yrs 8 mo late | — | 100% |
| Sai SagarSanjay Mahendra Singh | 5 yrs 11 mo late | — | 50% |
| Durgeshwari ApartmentDurga Developers | 3 yrs 4 mo late | — | 0% |
| S V BuildersSameerali Safarali Virani | 3 yrs 10 mo late | — | 0% |
| Friends ArcadeFriends Developers | Due Dec 2026, extended 3 yrs | — | 0% |
| AaradhyaAaradhya Enterprises | 3 yrs 10 mo late | — | 0% |
| Shiv Jeevan ApartmentRahul Mahadev Atpadkar | 5 yrs 1 mo late | — | 17% |
| Renaissance Royal Phase 1Shree Sharada Infrastructures | Due Dec 2026 | — | 20% |
| Trishul ApartmentMahakali Developers | 3 yrs 10 mo late | — | 0% |
| Shri Varadvinayak ApartmentM/S Brs Builders & Developers | 5 yrs 8 mo late | — | 0% |
| Cluster AShibam Associates | Due Apr 2027, extended 4 mo | — | 39% |
| Planet HighlandsHabib Umar Khan | 3 yrs 9 mo late | — | — |
| Shree Sai Srushti ParadiseArun Ramesh Tamboli | 3 yrs 4 mo late | — | 0% |
| Sai DishaSairath Develoeprs | 3 yrs 11 mo late | — | 50% |
| Shagun PrestigeShagun Reals | 4 yrs 7 mo late | — | 43% |
| Shree Sai Mangal ApartmentShri Sai Chintan Enterprises | 4 yrs 5 mo late | — | 31% |
Nearby: other localities in Karjat
Most active promoters
- M/s. Seema Promoters And Builders Private Limited6 projects
- Shibam Associates4 projects
- Dreamz Realty3 projects
- M/S Brs Builders & Developers2 projects
- Navkar developers2 projects
- Nehaldhara Realtors2 projects
- Pankaj Prakash Sawant2 projects
- Prashant Prakash Sawant2 projects
- Shree Sharada Infrastructures2 projects
- 5P Developers1 project
Data through22 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Methodology