Cluster A
Deedo IDDP-RAI-M6HACompletion was pushed back 4 months, to Apr 2027; no MahaRERA orders on record; 39% of its units are booked.
Neral, Raigarh 410101 · by Shibam Associates · 67% of its projects kept the RERA date
Buying a flat here?
See every deed registered on it.
Completion was pushed back 4 months, to Apr 2027
- This projectRegistered 26 Oct 2018, completion promised 31 Dec 2026, revised to 30 Apr 2027.
No extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales first, then rentals and mortgages matched to this project · the free view shows a price band
4 buildings
Open a building to see every flat, floor by floor.
- A1 and A24 floors · 38 units18% booked
- A3 and A44 floors · 38 units100% booked
- A5 and A64 floors · 38 units39% booked
- A7 and A8 - Proposed4 floors · 38 units0% booked
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP52000018378
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P52000018378 | 26 Oct 2018 | 31 Dec 2026 | 30 Apr 2027 | Shibam Associates | Project page |
Documents88
1 document held by Deedo, 87 filings listed on MahaRERA's project page
Legal
Migrated
- 1 Copy of the legal title reportTitle Certificate.pdf · uploaded 20 Oct 2018Source
- 1 Copy of Layout Approval (in case of layout)Cluster A Layout.pdf · uploaded 20 Oct 2018Source
- 1 Building Plan Approval (IOD)ZP cluster A.pdf · uploaded 20 Oct 2018Source
- 1 Commencement Certificates / NA Order for plotted developmentZP cluster A.pdf · uploaded 20 Oct 2018Source
Show all 88 documentsShow fewer documents
Migrated
- 1 Declaration in FORM BDeclaration.pdf · uploaded 20 Oct 2018Source
- 1 Certificates of CA (Form 3)CA Certificate.pdf · uploaded 20 Oct 2018Source
- 1 Proforma of Allotment letterReservation Letter (RERA Proforma).pdf · uploaded 20 Oct 2018Source
- 2 Proforma of Allotment lettermaster agreement cluster A.pdf · uploaded 20 Oct 2018Source
- 1 Details of encumbrancesENCUMBRANCE CERTIFICATE A.pdf · uploaded 23 Oct 2018Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)Cluster A Form 5 mar 2019.pdf · uploaded 5 Mar 2023Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)Cluster A Form 5 mar 2020.pdf · uploaded 5 Mar 2023Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)Cluster A Form 5 mar 2021.pdf · uploaded 5 Mar 2023Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)Cluster A Form 5 mar 2022.pdf · uploaded 5 Mar 2023Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Cluster A - Architects Certificate 31-03-20 Signed.pdf · uploaded 15 Mar 2023Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Cluster A - Architects Certificate 31-03-21 Signed.pdf · uploaded 15 Mar 2023Source
- 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)Cluster A - Architects Certificate 31-03-22 Signed.pdf · uploaded 15 Mar 2023Source
- 2 Certificates of CA (Form 3)Cluster A - Form 3 - CA Certificate 31032019_compressed.pdf · uploaded 15 Mar 2023Source
- 3 Certificates of CA (Form 3)Cluster A - Form 3 - CA Certificate 31032020_compressed.pdf · uploaded 15 Mar 2023Source
- 4 Certificates of CA (Form 3)Cluster A - Form 3 - CA Certificate 31032021_compressed.pdf · uploaded 15 Mar 2023Source
- 5 Certificates of CA (Form 3)Cluster A - Architects Certificate 31-03-22 Signed.pdf · uploaded 15 Mar 2023Source
- 6 Certificates of CA (Form 3)Cluster A - Form 3 - CA Certificate 31032022_compressed.pdf · uploaded 15 Mar 2023Source
- 1 Declaration about Commencement CertificateDeclaration about Commencement Certificate.pdf · uploaded 30 Jan 2024Source
- 2 Declaration in FORM BForm B.pdf · uploaded 30 Jan 2024Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)Form 2A - Sunil Prabhu.pdf · uploaded 30 Jan 2024Source
- 1 Disclosure of sold/ booked inventoryDiscolsure of Sold and Booked Inventory.pdf · uploaded 30 Jan 2024Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)Cluster A - Form 5 - CA Certificate 31032023 Signed.pdf · uploaded 30 Jan 2024Source
- Form 1Cluster A - Architects Certificate 30-06-2022.pdf · uploaded 2 Oct 2025Source
- Form 2Engineer Certificate Cluster A Jun 2022.pdf · uploaded 2 Oct 2025Source
- Form 3Shibham Cluster A_CA form 3 - Jun 2022.pdf · uploaded 2 Oct 2025Source
- Disclosure of Sold and Booked InventoryDisclosure of sold - booked inventory - RERA Jun 2022.pdf · uploaded 2 Oct 2025Source
- Form 1Cluster A - Architects Certificate 30-09-2022.pdf · uploaded 2 Oct 2025Source
- Form 2Engineer Certificate Cluster A Sep 2022.pdf · uploaded 2 Oct 2025Source
- Form 3Shibham Cluster A_CA form 3 - Sep 2022.pdf · uploaded 2 Oct 2025Source
- Disclosure of Sold and Booked InventoryDisclosure of sold - booked inventory - RERA Sept 2022.pdf · uploaded 2 Oct 2025Source
- Form 1Cluster A - Architects Certificate 31-12-2022.pdf · uploaded 2 Oct 2025Source
- Form 2Engineer Certificate Cluster A Dec 2022.pdf · uploaded 2 Oct 2025Source
- Form 3Shibham Cluster A_CA form 3 - Dec 2022.pdf · uploaded 2 Oct 2025Source
- Disclosure of Sold and Booked InventoryDisclosure of sold - booked inventory - RERA Dec 2022.pdf · uploaded 2 Oct 2025Source
- Form 1Cluster A - Architects Certificate 31-03-2023.pdf · uploaded 2 Oct 2025Source
- Form 2Engineer Certificate Cluster A Mar 2023.pdf · uploaded 2 Oct 2025Source
- Form 3Shibham Cluster A_CA form 3 - Mar 2023.pdf · uploaded 2 Oct 2025Source
- Disclosure of Sold and Booked InventoryDisclosure of sold - booked inventory - RERA Mar 2023.pdf · uploaded 2 Oct 2025Source
- Form 1Cluster A - Architects Certificate 30-06-2023.pdf · uploaded 2 Oct 2025Source
- Form 2Engineer Certificate Cluster A Jun 2023.pdf · uploaded 2 Oct 2025Source
- Form 3Shibham Cluster A_CA form 3 - Jun 2023.pdf · uploaded 2 Oct 2025Source
- Disclosure of Sold and Booked InventoryDisclosure of sold - booked inventory - RERA Jun 2023.pdf · uploaded 2 Oct 2025Source
- Form 1Cluster A - Architects Certificate 30-09-2023.pdf · uploaded 2 Oct 2025Source
- Form 2Engineer Certificate Cluster A Sep 2023.pdf · uploaded 2 Oct 2025Source
- Form 3Shibham Cluster A_CA form 3 - Sep 2023.pdf · uploaded 2 Oct 2025Source
- Disclosure of Sold and Booked InventoryDisclosure of sold - booked inventory - RERA Sept 2023.pdf · uploaded 2 Oct 2025Source
- Form 1Cluster A - Architects Certificate 31-12-2023.pdf · uploaded 2 Oct 2025Source
- Form 2Engineer Certificate Cluster A Dec 2023.pdf · uploaded 2 Oct 2025Source
- Form 3Shibham Cluster A_CA form 3 - Dec 2023.pdf · uploaded 2 Oct 2025Source
- Disclosure of Sold and Booked InventoryDisclosure of sold - booked inventory - RERA Dec 2023.pdf · uploaded 2 Oct 2025Source
- Form 1Cluster A - Architects Certificate 31-03-2024.pdf · uploaded 2 Oct 2025Source
- Form 2Engineer Certificate Cluster A Mar 2024.pdf · uploaded 2 Oct 2025Source
- Form 3Shibham Cluster A_CA form 3 - Mar 2024.pdf · uploaded 2 Oct 2025Source
- Disclosure of Sold and Booked InventoryDisclosure of sold - booked inventory - RERA Mar 2024.pdf · uploaded 2 Oct 2025Source
- Form 1Cluster A - Architects Certificate 30-06-2024.pdf · uploaded 2 Oct 2025Source
- Form 2Engineer Certificate Cluster A Jun 2024.pdf · uploaded 2 Oct 2025Source
- Form 3Shibham Cluster A_CA form 3 - Jun 2024.pdf · uploaded 2 Oct 2025Source
- Disclosure of Sold and Booked InventoryDisclosure of sold - booked inventory - RERA Jun 2024.pdf · uploaded 2 Oct 2025Source
- Form 1Cluster A - Architects Certificate 30-09-2024.pdf · uploaded 2 Oct 2025Source
- Form 2Engineer Certificate Cluster A Sep 2024.pdf · uploaded 2 Oct 2025Source
- Form 3Shibham Cluster A_CA form 3 - Sep 2024.pdf · uploaded 2 Oct 2025Source
- Disclosure of Sold and Booked InventoryDisclosure of sold - booked inventory - RERA Sept 2024.pdf · uploaded 2 Oct 2025Source
- Form 1Cluster A - Architects Certificate 31-12-2024.pdf · uploaded 2 Oct 2025Source
- Form 2Engineer Certificate Cluster A Dec 2024.pdf · uploaded 2 Oct 2025Source
- Form 3Shibham Cluster A_CA form 3 - Dec 2024.pdf · uploaded 2 Oct 2025Source
- Disclosure of Sold and Booked InventoryDisclosure of sold - booked inventory - RERA Dec 2024.pdf · uploaded 2 Oct 2025Source
- Form 2A (FY 2018-2019)Form 2A - March 19.pdf · uploaded 22 Dec 2025Source
- Form 2A (FY 2019-2020)Form 2A - March 20.pdf · uploaded 22 Dec 2025Source
- Form 2A (FY 2022-2023)Form 2A - March 23.pdf · uploaded 22 Dec 2025Source
- Form 2A (FY 2023-2024)Form 2A - March 24.pdf · uploaded 22 Dec 2025Source
- Form 2A (FY 2024-2025)Form 2A - March 25.pdf · uploaded 22 Dec 2025Source
- Form 5 (FY 2023-2024)4 Form 5 - 23-24.pdf · uploaded 3 Jan 2026Source
- Form 5 (FY 2024-2025)5 Form 5 24-25.pdf · uploaded 3 Jan 2026Source
- Form 1Cluster A - Architects Certificate 31-03-2025.pdf · uploaded 29 Sep 2026Source
- Form 2Engineer Certificate Cluster A 31-03-2025.pdf · uploaded 29 Sep 2026Source
- Form 3Shibham Cluster A_CA form 3 - Mar 2025.pdf · uploaded 29 Sep 2026Source
- Disclosure of Sold and Booked InventoryDisclosure of sold - booked inventory - RERA Mar 2025.pdf · uploaded 29 Sep 2026Source
Technical
Technical (Architect)
- DocumentCluster A - Architects Certificate 31-03-2026.pdf · uploaded 29 Sep 2026Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsLand parcel S.No 404 Plot No. 49 to 56, S.No 407 Plot No. 2 to 8
As registered with MahaRERA and published on its project page
- Project type
- Residential / Group Housing
- Status on MahaRERA
- Certificate Signed
- Unit types
- 1BHK, 1 RK152 units in all
- Address
- S.No 407 Plot No. 2 to 8 and S.No 404 Plot No. 49 to 56, SH 79, NeralPIN 410101
- Village
- Neral, Karjat taluka
- Location
- 19.01646, 73.31583
- Land area for this project
- 5,051 sq m (54,368 sq ft)
- Permissible built-up area
- 5,943 sq m (63,965 sq ft)
- Sanctioned built-up area
- 4,862 sq m (52,331 sq ft)
- Designated bank account
- 76
- Developed in phases
- Yes
Survey, CTS, gat or plot numbers
Land as published on MahaRERA's project page
S.No 407 Plot No. 2 to 8 and S.No 404 Plot No. 49 to 56
Boundaries
- North
- S No 90
- South
- Internal Road
- East
- Internal Road
- West
- H No 7
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking152 units
60 of 152 units booked (39%), as the promoter reported to MahaRERA
| Building | Type | Carpet area | Units | Booked |
|---|---|---|---|---|
| A1 and A2 | 1BHK | 36.14 sq m · 389 sq ft | 24 | 4 |
| A1 and A2 | 1BHK | 37.12 sq m · 400 sq ft | 14 | 3 |
| A3 and A4 | 1BHK | 36.14 sq m · 389 sq ft | 24 | 24 |
| A3 and A4 | 1BHK | 37.12 sq m · 400 sq ft | 14 | 14 |
| A5 and A6 | 1BHK | 36.14 sq m · 389 sq ft | 24 | 10 |
| A5 and A6 | 1BHK | 37.12 sq m · 400 sq ft | 14 | 5 |
| A7 and A8 - Proposed | 1 RK | 22.16 sq m · 239 sq ft | 38 | 0 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals4
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Chalisa and Chalisa | — |
| Chartered accountant | Nooruddin F Mandsaurwala | — |
| Chartered accountant | Zujar Ismail Latifjiwala | — |
| Engineer | Juzer N Merchant | — |
Source: MahaRERA project page. Contact details are not shown.
Other projects in Neral
- Sushrut AvenueRERA PR1270002602351
- Renaissance Royal Phase IIRERA PR1271012600760
- Shree Balaji TowerRERA PM1270002600237
- Asma TowerRERA PM1270002501288
- Saroj SerenityRERA PM1271012500916
- Shivamrut PlazaRERA PM1270002500518
- Shree Parshwanath ResidencyRERA PR1270002500113
- Shanti Lake ViewRERA P52000079251
All 88 projects in Neral · Compare Cluster A with another project