Shibam Associates
Deedo IDDD-BK74Of 3 registrations whose promised date has arrived, 2 kept it (67%). The rest ran a median 8 mo late — longer than Maharashtra's 4 mo.
Delivery record
2 of 4 registrations with dates moved or missed their RERA date · months late against the original promise
4 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Cluster CP52000006617 | Neral | Certificate Signed | 22 Nov 2019 | 21 Nov 2020 | +12 mo |
| Cluster FP52000008779 | Neral | Certificate Signed | 15 Mar 2019 | 15 Mar 2019 | On date |
| Cluster GP52000009953 | Neral | Certificate Signed | 14 May 2022 | 14 May 2022 | On date |
| Cluster AP52000018378 | Neral | Certificate Signed | 31 Dec 2026 | 30 Apr 2027 | +4 mo |
Shibam Associates, in questions
Does Shibam Associates finish projects on time?
Of 3 MahaRERA registrations whose promised completion date has arrived, 2 kept it (67%). The rest ran a median 8 mo late. Across Maharashtra, 73% kept their date.
How many projects has Shibam Associates registered with MahaRERA?
4 projects under 4 MahaRERA registrations; 3 completed on MahaRERA.
Does Shibam Associates have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.