Vardhaman Residency
Completion date passedPashane, Raigarh 421503 |Promoter: Geetadevi Bimleshkumar Jain
Project summary
As registered with MahaRERA
- RERA registrations
- 2
- Phases
- 2
Location
Coordinates as published by MahaRERA
Also registered as
Unit mix, parking, construction progress and the project's professionals come from that page. You can open it on MahaRERA (it asks for a CAPTCHA).
Latest registered deals
Completion timeline
Registration date, the completion date promised at registration, and any extension since
Completion pushed back 4 years
P52000010494The latest completion date on record passed 2 years and 10 months ago.
- Registered
- 31 Aug 2017
- Promised
- 31 Dec 2019
- Revised
- 31 Dec 2023
Completion pushed back 3 years
P52000011680The latest completion date on record passed 2 years and 4 months ago.
- Registered
- 31 Aug 2017
- Promised
- 30 Jun 2021
- Revised
- 30 Jun 2024
2 RERA registrations
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P52000010494 | 31 Aug 2017 | 31 Dec 2019 | 31 Dec 2023 | Geetadevi Bimleshkumar Jain | Project page |
| P52000011680 | 31 Aug 2017 | 30 Jun 2021 | 30 Jun 2024 | Geetadevi Bimleshkumar Jain | Project page |
Documents
4 documents held by Deedo
Registration certificate (2)
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Regulatory record
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
Land
In Pashane
Survey, CTS, gat or plot numbers
Source: registration certificates, as stated there.
