Deedo IDDP-RAI-ZZKGCompletion was pushed back 4 months, to Apr 2027; no MahaRERA orders on record; 37% of its units are booked.
Pashane, Raigarh 410101 · by Gurudev Developers
Buying a flat here?
See every deed registered on it.
Completion was pushed back 4 months, to Apr 2027
- This projectRegistered 8 Dec 2023, completion promised 31 Dec 2026, revised to 30 Apr 2027.
No extension certificate on record.
1 registration · Source: MahaRERA registration and extension certificates
Latest registered deeds
Sales first, then rentals and mortgages matched to this project · the free view shows a price band
2 buildings
Open a building to see every flat, floor by floor.
Floors and units from the registration certificate annexures and MahaRERA's project page.
Regulatory recordNone found
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
RERA registrationP52000053866
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P52000053866 | 8 Dec 2023 | 31 Dec 2026 | 30 Apr 2027 | Gurudev Developers | Project page |
Documents119
1 document held by Deedo, 118 filings listed on MahaRERA's project page
Finance
- PAN CardPAN Card.pdf · uploaded 14 Sep 2023Source
Legal
- Declaration Form BForm B - Promoter.pdf · uploaded 15 Sep 2023Source
- Declaration Form BForm B - Landowner.pdf · uploaded 15 Sep 2023Source
- Other – LegalApproved Layout_cropped.pdf · uploaded 21 Sep 2023Source
- Legal Title reportTitle report uploaded in rera.pdf · uploaded 6 Oct 2023Source
- Other – Legal7 12 Extract.pdf · uploaded 3 May 2025Source
- Legal Title reportTitle Search report.pdf · uploaded 3 May 2025Source
Show all 119 documentsShow fewer documents
Migrated
- 1 PAN CardPAN Card.pdf · uploaded 14 Sep 2023Source
- 1 Copy of Layout Approval (in case of layout)Approved Layout.pdf · uploaded 15 Sep 2023Source
- 1 Building Plan Approval / NA Order for plotted developmentApproved Building Plan.pdf · uploaded 15 Sep 2023Source
- 1 Commencement Certificates / NA Order for plotted developmentCommencement Certificate.pdf · uploaded 15 Sep 2023Source
- 1 Declaration in FORM BForm B - Promoter.pdf · uploaded 15 Sep 2023Source
- 2 Declaration in FORM BForm B - Landowner.pdf · uploaded 15 Sep 2023Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Engineers Certificate.pdf · uploaded 15 Sep 2023Source
- 1 CERSAI detailsCERSAI Search Report Gurudev Developers.pdf · uploaded 15 Sep 2023Source
- 1 Disclosure of Interest in Other Real Estate OrganizationsDeclaration in other organisations AALAP R PATEL.pdf · uploaded 15 Sep 2023Source
- 2 Disclosure of Interest in Other Real Estate OrganizationsDeclaration in other organisations VINODKUMAR M PATEL.pdf · uploaded 15 Sep 2023Source
- 3 Disclosure of Interest in Other Real Estate OrganizationsDeclaration in other organisations RAMESH K PATEL.pdf · uploaded 15 Sep 2023Source
- 4 Disclosure of Interest in Other Real Estate OrganizationsDeclaration in other organisations SUNILKUMAR H PATEL.pdf · uploaded 15 Sep 2023Source
- 1 Proforma of Allotment letterModel copy of Allotment letter Gurudev Developers.pdf · uploaded 15 Sep 2023Source
- 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameDeclaration about separate bank account.pdf · uploaded 15 Sep 2023Source
- 1 Deviation Report with respect to Allotment letterDeviation report with respect to model copy of Allotment letter.pdf · uploaded 15 Sep 2023Source
- 1 Deviation Report with respect to model copy of AgreementDeviation report with respect to model copy of Agreement to sale.pdf · uploaded 15 Sep 2023Source
- 1 a Details of encumbrances concerned to FinanceDetails of encumbrances concerned to Finance.pdf · uploaded 21 Sep 2023Source
- 2 a Details of encumbrances concerned to FinanceDetails of encumbrances concerned to Legal GD.pdf · uploaded 21 Sep 2023Source
- 1 b Details of encumbrances concerned to LegalDetails of encumbrances concerned to Finance.pdf · uploaded 21 Sep 2023Source
- 2 b Details of encumbrances concerned to LegalDetails of encumbrances concerned to Legal GD.pdf · uploaded 21 Sep 2023Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 - Architect certificate_organized.pdf · uploaded 21 Sep 2023Source
- 5 Disclosure of Interest in Other Real Estate OrganizationsDeclaration in other organisations -MANILAL D POKAR.pdf · uploaded 21 Sep 2023Source
- 6 Disclosure of Interest in Other Real Estate OrganizationsDeclaration in other organisations - PRIYANK D BHIMANI.pdf · uploaded 21 Sep 2023Source
- 7 Disclosure of Interest in Other Real Estate OrganizationsDeclaration in other organisations - JAYRAM DHULE.pdf · uploaded 21 Sep 2023Source
- 1 Other – LegalApproved Layout_cropped.pdf · uploaded 21 Sep 2023Source
- 2 Commencement Certificates / NA Order for plotted developmentCommencement Certificate 2022.pdf · uploaded 22 Sep 2023Source
- 1 Declaration about Commencement CertificateDeclaration of commencement certificate.pdf · uploaded 22 Sep 2023Source
- 1 Copy of the legal title reportTitle report uploaded in rera.pdf · uploaded 6 Oct 2023Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 - Adarsh A Patel NEW.pdf · uploaded 6 Oct 2023Source
- 1 Other – TechnicalOCCC MAIL.pdf · uploaded 16 Nov 2023Source
- 1 Proforma of Agreement for sale1 Proforma of Agreement for sale.pdf · uploaded 17 Nov 2023Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect certificate Signed Copy 31122023.pdf · uploaded 16 Jan 2024Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineers Certiifcate Signed Copy .pdf · uploaded 16 Jan 2024Source
- 1 Disclosure of sold/ booked inventorySold unsold Inventory 31122023 .pdf · uploaded 16 Jan 2024Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA certificate Signed copy 31122023.pdf · uploaded 16 Jan 2024Source
- 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 Gurudev Developer 31032024.pdf · uploaded 17 Apr 2024Source
- 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Engineer certificate 31032024.pdf · uploaded 17 Apr 2024Source
- 2 Disclosure of sold/ booked inventorySold Unsold Declaration 31032024.pdf · uploaded 17 Apr 2024Source
- 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 - Adarsh A Patel as on 31032024.pdf · uploaded 17 Apr 2024Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)Gurudev Developers Form 5 FY2324 scanned.pdf · uploaded 27 Jun 2024Source
- 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 Architect Certificate 30062024.pdf · uploaded 19 Aug 2024Source
- 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Engineer Certificate.pdf · uploaded 19 Aug 2024Source
- 3 Disclosure of sold/ booked inventorySold Unsold Inventory 30062024.pdf · uploaded 19 Aug 2024Source
- 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 - Adarsh A Patel as on 30062024.pdf · uploaded 19 Aug 2024Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 Nikhil Park.pdf · uploaded 16 Oct 2024Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 Nikhil Park 30092024.pdf · uploaded 16 Oct 2024Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Nikhil Park 30092024.pdf · uploaded 16 Oct 2024Source
- 2 Disclosure of sold/ booked inventorySold Unsold Declaration Nikhil Park 30092024.pdf · uploaded 16 Oct 2024Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)31122024 Form 1 Architect Certificate Nikhil Park.pdf · uploaded 5 Feb 2025Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)31122024 Form 3 CA Certificate Nikhil Park.pdf · uploaded 5 Feb 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)31122024 Form 2 Engineer Certificate Nikhil Park.pdf · uploaded 5 Feb 2025Source
- 1 Disclosure of sold/ booked inventory31122024 Sold Unsold Declaration Nikhil Park.pdf · uploaded 5 Feb 2025Source
- 1 Copy of the legal title reportTitle Search report.pdf · uploaded 3 May 2025Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 Nikhil Park 31032025.pdf · uploaded 3 May 2025Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 Nikhil Park 31032025.pdf · uploaded 3 May 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Nikhil Park 31032025.pdf · uploaded 3 May 2025Source
- 1 Other – Legal7 12 Extract.pdf · uploaded 3 May 2025Source
- 1 Disclosure of sold/ booked inventorySold Unsold Declaration.pdf · uploaded 3 May 2025Source
- Form 1Form 1 Arc Nikhil Park 31122023.pdf · uploaded 26 Aug 2025Source
- Form 2Form 2 Eng Nikhil Park 31122023.pdf · uploaded 26 Aug 2025Source
- Form 3Form 3 CA Cert Nikhil Park 31122023.pdf · uploaded 26 Aug 2025Source
- Disclosure of Sold and Booked InventorySold unsold Inventory 31122023 .pdf · uploaded 26 Aug 2025Source
- Form 1Form 1 Gurudev Developer 31032024.pdf · uploaded 26 Aug 2025Source
- Form 2Form 2 Gurudev Developer 31032024.pdf · uploaded 26 Aug 2025Source
- Form 3Form 3 Gurudev Developer 31032024.pdf · uploaded 26 Aug 2025Source
- Disclosure of Sold and Booked InventorySold Unsold Declaration 31032024.pdf · uploaded 26 Aug 2025Source
- Form 1Form 1 Gurudev Developers 30062024.pdf · uploaded 26 Aug 2025Source
- Form 2Form 2 Gurudev developers 30062024.pdf · uploaded 26 Aug 2025Source
- Form 3Form 3 Gurudev developers 30062024.pdf · uploaded 26 Aug 2025Source
- Disclosure of Sold and Booked InventorySold Unsold Inventory 30062024.pdf · uploaded 26 Aug 2025Source
- Form 1Form 1 Nikhil Park 30092024.pdf · uploaded 26 Aug 2025Source
- Form 2Form 2 Nikhil Park 30092024.pdf · uploaded 26 Aug 2025Source
- Form 3Form 3 Nikhil Park 30092024.pdf · uploaded 26 Aug 2025Source
- Disclosure of Sold and Booked InventorySold Unsold Declaration Nikhil Park 30092024.pdf · uploaded 26 Aug 2025Source
- Form 131122024 Form 1 Architect Certificate Nikhil Park.pdf · uploaded 26 Aug 2025Source
- Form 231122024 Form 2 Engineer Certificate Nikhil Park.pdf · uploaded 26 Aug 2025Source
- Form 331122024 Form 3 CA Certificate Nikhil Park.pdf · uploaded 26 Aug 2025Source
- Disclosure of Sold and Booked Inventory31122024 Sold Unsold Declaration Nikhil Park.pdf · uploaded 26 Aug 2025Source
- Form 1Form 1 Nikhil Park 31032025.pdf · uploaded 26 Aug 2025Source
- Form 2Form 2 Nikhil Park 31032025.pdf · uploaded 26 Aug 2025Source
- Form 3Form 3 Nikhil Park 31032025.pdf · uploaded 26 Aug 2025Source
- Disclosure of Sold and Booked InventorySold Unsold Declaration.pdf · uploaded 26 Aug 2025Source
- Withdrawal Update Form 1Form 1 Gurudev developers 30062025.pdf · uploaded 28 Aug 2025Source
- Withdrawal Update Form 2Form 2 Gurudev developers 30062025.pdf · uploaded 28 Aug 2025Source
- Withdrawal Update Form 3Form 3 - Nikhil Park 30062025.pdf · uploaded 28 Aug 2025Source
- Form 5 (FY 2023-2024)Gurudev Developers Form 5 FY2324 scanned.pdf · uploaded 26 Sep 2025Source
- Form 5 (FY 2024-2025)Form 5 - Gurudev Developers FY24-25 for Upload.pdf · uploaded 26 Sep 2025Source
- Withdrawal Update Form 1Form 1 Architect Certificate 30092025.pdf · uploaded 8 Nov 2025Source
- Withdrawal Update Form 2Form 2 Engineer Certificate 30092025.pdf · uploaded 8 Nov 2025Source
- Withdrawal Update Form 3Form 3 CA Certificate 30092025.pdf · uploaded 8 Nov 2025Source
- Withdrawal Update Form 1Gurudev developers Form 1 31122025.pdf · uploaded 12 Feb 2026Source
- Withdrawal Update Form 2Gurudev developers Form 2 31122025.pdf · uploaded 12 Feb 2026Source
- Withdrawal Update Form 3Gurudev developers Form 3 31122025.pdf · uploaded 12 Feb 2026Source
- Withdrawal Update Form 1Form 1 Architect Certificate 31032026.pdf · uploaded 28 Apr 2026Source
- Withdrawal Update Form 2Form 2 Engineer certificate 31032026.pdf · uploaded 28 Apr 2026Source
- Withdrawal Update Form 3Form 3 CA Certificate 31032026.pdf · uploaded 28 Apr 2026Source
- Withdrawal Update Form 1FORM 1 30062026 - Architect.pdf · uploaded 30 Jul 2026Source
- Withdrawal Update Form 2FORM 2 30062026 - Engineer.PDF · uploaded 30 Jul 2026Source
- Withdrawal Update Form 3Form 3 30062026.pdf · uploaded 30 Jul 2026Source
- Form 5 (FY 2025-2026)Form 5 signed copy.pdf · uploaded 29 Sep 2026Source
Technical
Technical (Architect)
Technical (Engineer)
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Land & approvalsLand parcel 151/2 at Karjat
As registered with MahaRERA and published on its project page
- Project type
- Others
- Status on MahaRERA
- Certificate Signed
- Unit types
- —70 units in all
- Address
- 151/2, Pashane, PashanePIN 410101
- Village
- Pashane, Karjat taluka
- Location
- 19.10197, 73.31346
- Land area for this project
- 1,800 sq m (19,375 sq ft)
- Permissible built-up area
- 1,992 sq m (21,446 sq ft)
- Sanctioned built-up area
- 1,992 sq m (21,446 sq ft)
- Designated bank account
- 21
- Developed in phases
- Yes
Survey, CTS, gat or plot numbers
Land as published on MahaRERA's project page
151/2
Boundaries
- North
- Existing Road
- South
- Survey No 151-6
- East
- Survey No 151
- West
- Survey No 144
Source: registration certificates and MahaRERA's project page, as stated there.
Units & parking70 units
70 units registered
| Building | Type | Carpet area | Units |
|---|---|---|---|
| Wing A | — | — | 32 |
| Wing B | — | — | 38 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Professionals3
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Dipali B Meher | — |
| Chartered accountant | Adarsh A Patel & Co | — |
| Engineer | Aadhar Engineers | — |
Source: MahaRERA project page. Contact details are not shown.
Other projects in Pashane
- Gagangiri ParkRERA PM1270002600623
- Virat Greenwoods Wing B & DRERA PM1270002501372
- Ashtavinayak ComplexRERA PM1270002501104
- Galaxy VrundavanRERA P52000080710
- Tulsi VedantRERA P52000080255
- Dhruv Residency PlatinumRERA P52000047179
- Gagangiri ComplexRERA P52000030075
- Virat Greenwoods Wing ERERA P52000029781
All 34 projects in Pashane · Compare Nikhil Park with another project