Skip to content
Residential / Group Housing · 2 buildings · 114 unitsRERA P52000021291

Wellwisher Iris

Deedo IDDP-RAI-MGN7

Completion was pushed back 4 months, to Oct 2030; no MahaRERA orders on record; 0% of its units are booked.

Pashane, Raigarh 410201 · by Himgiri Dealcom LLP

DeliveryExtended 4 moPromised Jun 2030 · now due Oct 2030RegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales0% booked0 of 114 units · as the promoter reported to MahaRERA

Buying a flat here?

See every deed registered on it.

Completion was pushed back 4 months, to Oct 2030

  • This projectRegistered 21 Jun 2019, completion promised 30 Jun 2030, revised to 30 Oct 2030.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales first, then rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

2 buildings

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP52000021291
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5200002129121 Jun 201930 Jun 203030 Oct 2030Himgiri Dealcom LLPProject page
Documents84

1 document held by Deedo, 83 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN Cardpan card -himgiri dealcom llp.pdf · uploaded 14 Jun 2019Source

Legal

  • OtherPlot No 13-712.pdf · uploaded 14 Jun 2019Source
  • Legal Title reportTile Search Report Plot No 13 -resize.pdf · uploaded 14 Jun 2019Source
  • Declaration Form BForm B_compressed.pdf · uploaded 14 Jun 2019Source

Migrated

  • 1 PAN Cardpan card -himgiri dealcom llp.pdf · uploaded 14 Jun 2019Source
  • 1 Copy of the legal title reportTile Search Report Plot No 13 -resize.pdf · uploaded 14 Jun 2019Source
  • 1 Details of encumbrancesencumbrance letter.pdf · uploaded 14 Jun 2019Source
Show all 84 documentsShow fewer documents

Migrated

  • 1 Copy of Layout Approval (in case of layout)Layout Plan Plot No 13.PDF · uploaded 14 Jun 2019Source
  • 1 Building Plan Approval (IOD)Building Plan Plot no 13-1.PDF · uploaded 14 Jun 2019Source
  • 2 Building Plan Approval (IOD)Building Plan Plot no 13-2.PDF · uploaded 14 Jun 2019Source
  • 3 Building Plan Approval (IOD)Building Plan Plot no 13-3.PDF · uploaded 14 Jun 2019Source
  • 1 Commencement Certificates / NA Order for plotted developmentCC.pdf · uploaded 14 Jun 2019Source
  • 1 Declaration in FORM BForm B_compressed.pdf · uploaded 14 Jun 2019Source
  • 1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Architects Certificate.pdf · uploaded 14 Jun 2019Source
  • 1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Engineer Certificate.pdf · uploaded 14 Jun 2019Source
  • 1 Certificates of CA (Form 3)CA Certificate final.pdf · uploaded 14 Jun 2019Source
  • 1 Proforma of Allotment letterAgreement for sale--.pdf · uploaded 14 Jun 2019Source
  • 1 OtherPlot No 13-712.pdf · uploaded 14 Jun 2019Source
  • 2 Certificates of Architect (Form 1)(Mandatory for only ongoing project)architect certificate_compressed (10).pdf · uploaded 9 Nov 2019Source
  • 2 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)engineer certificate_compressed (6).pdf · uploaded 9 Nov 2019Source
  • 2 Certificates of CA (Form 3)CA Certificate.pdf · uploaded 9 Nov 2019Source
  • 3 Certificates of CA (Form 3)Form-3-Iris-March 2021.pdf · uploaded 19 Jul 2021Source
  • 4 Certificates of CA (Form 3)Form-3-Iris-Dec 2021.pdf · uploaded 4 Mar 2022Source
  • 5 Certificates of CA (Form 3)Form-3-Iris-March 2022.pdf · uploaded 26 May 2022Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)RERA Annual-WI-F Y 2018-19-sign.pdf · uploaded 22 Dec 2022Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)RERA Annual-WI-F Y 2019-20-Sign.pdf · uploaded 22 Dec 2022Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)RERA Annual-WI-F Y 2020-21-Sign.pdf · uploaded 22 Dec 2022Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)RERA Annual-WI-F Y 2021-22-Sign.pdf · uploaded 22 Dec 2022Source
  • 3 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Plot no 13, Vangani Rera Certificate_compressed.pdf · uploaded 20 Feb 2023Source
  • 3 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)FORM 2-PLOT 13 EC 30-12-22.pdf · uploaded 3 Mar 2023Source
  • Form 130062025 ( form 1_compressed.pdf · uploaded 11 Aug 2025Source
  • Form 230062025 (form 2.pdf · uploaded 11 Aug 2025Source
  • Form 3Form 3 - Jun 25_compressed.pdf · uploaded 11 Aug 2025Source
  • Disclosure of Sold and Booked Inventorysold unsold.pdf · uploaded 11 Aug 2025Source
  • Form 131-03-2025.pdf · uploaded 11 Aug 2025Source
  • Form 230062025 (form 2.pdf · uploaded 11 Aug 2025Source
  • Disclosure of Sold and Booked Inventorysold unsold.pdf · uploaded 11 Aug 2025Source
  • Form 3Form 3 - Mar 25_compressed.pdf · uploaded 11 Aug 2025Source
  • Form 3Form 3 - Mar 25_compressed.pdf · uploaded 11 Aug 2025Source
  • Form 230062025 (form 2.pdf · uploaded 11 Aug 2025Source
  • Disclosure of Sold and Booked Inventorysold unsold.pdf · uploaded 11 Aug 2025Source
  • Form 131-03-2024.pdf · uploaded 11 Aug 2025Source
  • Form 2A (FY 2023-2024)form 2a (2).pdf · uploaded 12 Aug 2025Source
  • Form 2A (FY 2024-2025)form 2a (2).pdf · uploaded 12 Aug 2025Source
  • Form 5 (FY 2024-2025)FORM 56.pdf · uploaded 12 Aug 2025Source
  • Form 130062025 ( form 1_compressed.pdf · uploaded 13 Aug 2025Source
  • Form 230062025 (form 2.pdf · uploaded 13 Aug 2025Source
  • Disclosure of Sold and Booked Inventorysold unsold.pdf · uploaded 13 Aug 2025Source
  • Form 3Iris - Jun 2025.pdf · uploaded 13 Aug 2025Source
  • Form 3Form 3 - Iris - 30-03-25.pdf · uploaded 17 Oct 2025Source
  • Form 1WELLWISHER IRIS FORM 1_compressed.pdf · uploaded 17 Oct 2025Source
  • Disclosure of Sold and Booked Inventoryiris -SOLD UNSOLD.pdf · uploaded 17 Oct 2025Source
  • Form 2Form 2.pdf · uploaded 17 Oct 2025Source
  • Withdrawal Update Form 1Architect - Iris -30-9-25.pdf · uploaded 17 Oct 2025Source
  • Withdrawal Update Form 1Architect - Iris -30-9-25.pdf · uploaded 17 Oct 2025Source
  • Withdrawal Update Form 2iris engineer.pdf · uploaded 17 Oct 2025Source
  • Withdrawal Update Form 2iris engineer.pdf · uploaded 17 Oct 2025Source
  • Withdrawal Update Form 3Form 3-IRIS.pdf · uploaded 17 Oct 2025Source
  • Withdrawal Update Form 3Form 3-IRIS.pdf · uploaded 17 Oct 2025Source
  • Withdrawal Update Form 1IRIS - DEC 25 - FORM 1.pdf · uploaded 16 Jan 2026Source
  • Withdrawal Update Form 1IRIS - DEC 25 - FORM 1.pdf · uploaded 16 Jan 2026Source
  • Withdrawal Update Form 1IRIS - DEC 25 - FORM 1.pdf · uploaded 16 Jan 2026Source
  • Withdrawal Update Form 2Iris - Form 2.pdf · uploaded 16 Jan 2026Source
  • Withdrawal Update Form 2Iris - Form 2.pdf · uploaded 16 Jan 2026Source
  • Withdrawal Update Form 2Iris - Form 2.pdf · uploaded 16 Jan 2026Source
  • Withdrawal Update Form 3Iris Form 3_compressed.pdf · uploaded 16 Jan 2026Source
  • Withdrawal Update Form 3Iris Form 3_compressed.pdf · uploaded 16 Jan 2026Source
  • Withdrawal Update Form 3Iris Form 3_compressed.pdf · uploaded 16 Jan 2026Source
  • Withdrawal Update Form 1Form 1 - Wellwisher Iris 31-03-2026.pdf · uploaded 20 Apr 2026Source
  • Withdrawal Update Form 1Form 1 - Wellwisher Iris 31-03-2026.pdf · uploaded 20 Apr 2026Source
  • Withdrawal Update Form 2IRIS form 2 - Mar 26.pdf · uploaded 20 Apr 2026Source
  • Withdrawal Update Form 2IRIS form 2 - Mar 26.pdf · uploaded 20 Apr 2026Source
  • Withdrawal Update Form 3Form 3-WI-March 2026_Signed.pdf · uploaded 20 Apr 2026Source
  • Withdrawal Update Form 3Form 3-WI-March 2026_Signed.pdf · uploaded 20 Apr 2026Source
  • Withdrawal Update Form 1IRIS form 1.pdf · uploaded 31 Jul 2026Source
  • Withdrawal Update Form 2IRIS FORM 2 JUN 26.pdf · uploaded 31 Jul 2026Source
  • Withdrawal Update Form 3Form 3-WI-Jun 2026_Signed.pdf · uploaded 31 Jul 2026Source

Technical

  • DocumentLayout Plan Plot No 13.PDF · uploaded 14 Jun 2019Source
  • DocumentBuilding Plan Plot no 13-1.PDF · uploaded 14 Jun 2019Source
  • DocumentBuilding Plan Plot no 13-2.PDF · uploaded 14 Jun 2019Source
  • DocumentBuilding Plan Plot no 13-3.PDF · uploaded 14 Jun 2019Source

Technical (Architect)

  • DocumentIRIS form 1.pdf · uploaded 31 Jul 2026Source

Technical (Engineer)

  • DocumentIRIS FORM 2 JUN 26.pdf · uploaded 31 Jul 2026Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel Plot no 136/1/13

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Unit types
Multipurpose, Multipurpose room, multipurpose114 units in all
Address
Plot no 136/1/13, Vangani Pashane Road, Plot no 136/1/13PIN 410201
Village
Pashane, Karjat taluka
Land area for this project
2,425 sq m (26,106 sq ft)
Permissible built-up area
3,692 sq m (39,737 sq ft)
Sanctioned built-up area
3,689 sq m (39,710 sq ft)
Designated bank account
76
Developed in phases
Yes

Survey, CTS, gat or plot numbers

Plot no 136/1/13

Land as published on MahaRERA's project page

Plot no 136/1/13

Boundaries

North
plot no 12
South
road
East
Road
West
plot no 14

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking114 units

0 of 114 units booked (0%), as the promoter reported to MahaRERA

Multipurpose · 58 unitsMultipurpose room · 8 unitsmultipurpose · 48 units
BuildingTypeCarpet areaUnitsBooked
Building no 1Multipurpose24.69 sq m · 266 sq ft480
Building no 1Multipurpose room23.7 sq m · 255 sq ft80
Building No 2multipurpose24.69 sq m · 266 sq ft480
Building No 2Multipurpose23.7 sq m · 255 sq ft100

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals3

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectBharat Balchand Bathiya Bathiya—
ArchitectEry Sppaces—
EngineerSamarth Agarwal—

Source: MahaRERA project page. Contact details are not shown.

Other projects in Pashane

All 34 projects in Pashane · Compare Wellwisher Iris with another project

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Report a problemMethodology