Himgiri Dealcom LLP
Deedo IDDD-MCMDOf 1 registration whose promised date has arrived, 0 kept it (0%). The rest ran a median 17 mo late.
Delivery record
2 of 2 registrations with dates moved or missed their RERA date · months late against the original promise
2 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Wellwisher RoseP52000021289 | Pashane | Certificate Signed | 30 Jun 2024 | 30 Jun 2024 | +29 mo* |
| Wellwisher IrisP52000021291 | Pashane | Certificate Signed | 30 Jun 2030 | 30 Oct 2030 | +4 mo |
Himgiri Dealcom LLP, in questions
Does Himgiri Dealcom LLP finish projects on time?
Of 1 MahaRERA registration whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 17 mo late. Across Maharashtra, 73% kept their date.
How many projects has Himgiri Dealcom LLP registered with MahaRERA?
2 projects under 2 MahaRERA registrations; 0 completed on MahaRERA.
Does Himgiri Dealcom LLP have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.