Baramati (M Cl), Pune
Deedo IDDL-PUN-BARAMATI-29 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.
RERA projects181
Registrations183some projects hold several
Completion still due67116 past their date
Median extension4 months37% of registrations extended
Regulatory cases2on 2 projects
9 in 10 registrations run late here
183 MahaRERA registrations in Baramati (M Cl)
19 not yet due48 extended, not yet due116 past even the latest date
Extended registrations moved their completion date by a median of 4 months.
Projects in Baramati (M Cl)
181 projects registered with MahaRERA.
| Project | Delivery | Median ₹/sq ft | Booked |
|---|---|---|---|
| Yadgar Shine Building DYadgar Builders. | Due Dec 2029 | — | — |
| Ranaware IconsMorya Builders And Developers | Due Dec 2031 | — | — |
| Shreeram IconShreeram Developers | Due Mar 2029 | — | — |
| Shree HeightsR R Associates | Due Dec 2031 | — | — |
| Gadhave Nanaware ParkShri Developers | Due Dec 2028 | — | — |
Nearby: other municipal areas in Baramati
Most active promoters
- Mukti Township Development & Construction Co. Pvt. Ltd4 projects
- Sanjay Walchand Sanghavi4 projects
- Shri Developers3 projects
- Vedant Developers3 projects
- Akruti Buildcon2 projects
- Aziz Mehboob Bagwan2 projects
- Dattatray Hanumant Borade2 projects
- Deepak Bhausaheb Kate2 projects
- Jay Nanaso Patil2 projects
- Khatri Pawar Builders And Developers2 projects
Baramati (M Cl), in questions
How many projects in Baramati (M Cl) run late?
9 in 10 MahaRERA registrations (164 of 183): their completion date was extended or has passed, data through 21 Oct 2026.
Where does this data come from?
From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Baramati (M Cl) by Deedo. Medians on fewer than 3 deeds are not shown.
Data through21 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology