RERA projects in Tandulwadi
20 projects under 23 MahaRERA registrations, registered 2017–2026. 26% have a completion date extended beyond the one promised.
Locality
20RERA projects
23Registrationssome projects hold several
7Completion still due16 past their completion date
4 monthsMedian extension beyond promised date26% of registrations extended
1Regulatory caseson 1 project
24Buildings on recordfrom registration certificates
Registrations per year
New MahaRERA registrations by registration date.
| Year | Registrations |
|---|---|
| 2017 | 2 |
| 2018 | 4 |
| 2019 | 1 |
| 2020 | 1 |
| 2021 | 3 |
| 2022 | 5 |
| 2023 | 3 |
| 2024 | 2 |
| 2025 | 1 |
| 2026 | 1 |
Projects in Tandulwadi
20 projects registered with MahaRERA.
| Project | RERA | Registered | Promised completion | Revised completion | Timing | Cases |
|---|---|---|---|---|---|---|
| Jayraj Town Building DJay Nanaso Patil | P52100078779 | 13 Jan 2025 | 30 Jun 2028 | 30 Oct 2028 | Extended 4 mo | 0 |
| Spring Village IIPansare Infratech | P52100055479 | 2 Apr 2024 | 31 Dec 2027 | 30 Apr 2028 | Extended 4 mo | 0 |
| Bhagwan ComplexDigambar Bhagwan Beldar | P52100050826, P52100053634 | 9 May 2023 | 31 Dec 2026 | 31 Dec 2026 | Not yet due | 0 |
| Samyak ParadiseMr Makrand Jagdish Mahajan | P52100049847 | 6 Mar 2023 | 31 Dec 2026 | 31 Dec 2026 | Not yet due | 0 |
| Morya ClassicMorya Builders And Developers | P52100047660 | 17 Nov 2022 | 30 Sep 2024 | 30 Sep 2024 | Promised date passed | 0 |
| RamlataNitin Ramchandra Jadhav | P52100046919 | 20 Sep 2022 | 28 Mar 2026 | 28 Mar 2026 | Promised date passed | 1 |
| Varad Vinayak ResidencyAjay Balkrishna Shahane | P52100034449 | 5 Apr 2022 | 7 Mar 2027 | 7 Jul 2027 | Extended 4 mo | 0 |
| Arti ResidencyBabar Dhere Construction | P52100034261 | 30 Mar 2022 | 1 Jan 2025 | 31 Dec 2025 | Extended 11 mo | 0 |
| Matoshree ResidencyAjit Balasaheb Beldar Patil | P52100032872, P52100056411, PM1260002502617 | 2 Feb 2022 | 31 Dec 2028 | 30 Apr 2029 | Extended 4 mo | 0 |
| Krushna IconGanesh Dnyanoba Bhagat | P52100030852 | 20 Sep 2021 | 31 Dec 2025 | 31 Dec 2025 | Promised date passed | 0 |
| Vasturekha Township Building-AAayush Associates Through Proprietor Kapil Vilasrao Barge | P52100029241 | 10 May 2021 | 30 Sep 2023 | 30 Dec 2025 | Extended 27 mo | 0 |
| Bhagyashree ResidencyDattatray Bhagwan Beldar | P52100028933 | 15 Apr 2021 | 31 Dec 2023 | 31 Dec 2023 | Promised date passed | 0 |
| Matoshree Residency Building AAjit Balasaheb Beldar Patil | P52100025309 | 7 Apr 2020 | 30 Dec 2023 | 30 Dec 2023 | Promised date passed | 0 |
| Spring Village 1 Affordable HousingPansare Infratech | P52100020578 | 26 Apr 2019 | 30 Dec 2023 | 30 Dec 2023 | Promised date passed | 0 |
| Dnyaneshwari AppartmentNitin Gopal Jagetia | P52100017543 | 24 Aug 2018 | 1 Jul 2022 | 1 Jul 2022 | Promised date passed | 0 |
| Gulmohar Park B WingJay Nanaso Patil | P52100017017 | 4 Jul 2018 | 31 Jul 2022 | 31 Jul 2022 | Promised date passed | 0 |
| Jaylaxmi ComplexM/S Mahalaxmi Builders & Developers | P52100017025 | 4 Jul 2018 | 30 May 2022 | 30 May 2022 | Promised date passed | 0 |
| Varad Residency - Building BDigambar Laxman Kumbhar | P52100015132 | 31 Jan 2018 | 30 Jun 2019 | 30 Jun 2019 | Promised date passed | 0 |
| AshthavinayakUnity Group Builders And Developers | P52100010511 | 31 Aug 2017 | 31 Mar 2019 | 31 Mar 2019 | Promised date passed | 0 |
| Aditya IconAditya Buildcon | P52100005134 | 9 Aug 2017 | 31 May 2018 | 31 May 2018 | Promised date passed | 0 |
Other localities in Baramati
Most active promoters
By projects registered here, as named on MahaRERA.
- Ajit Balasaheb Beldar Patil2 projects
- Jay Nanaso Patil2 projects
- Pansare Infratech2 projects
- Aayush Associates Through Proprietor Kapil Vilasrao Barge1 project
- Aditya Buildcon1 project
- Ajay Balkrishna Shahane1 project
- Babar Dhere Construction1 project
- Dattatray Bhagwan Beldar1 project
- Digambar Bhagwan Beldar1 project
- Digambar Laxman Kumbhar1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology