RERA projects in Jalochi

124 projects under 125 MahaRERA registrations, registered 2017–2026. 44% have a completion date extended beyond the one promised.

Locality
124RERA projects
125Registrationssome projects hold several
63Completion still due62 past their completion date
4 monthsMedian extension beyond promised date44% of registrations extended
2Regulatory caseson 2 projects
260Buildings on recordfrom registration certificates

Registrations per year

New MahaRERA registrations by registration date.

MahaRERA registrations per year
YearRegistrations
201712
20186
20193
20205
202111
202217
202318
202416
202517
202620

Projects in Jalochi

124 projects registered with MahaRERA.

ProjectRERARegisteredPromised completionRevised completionTimingCases
Gokul ResidencyRajmata InfraPM12600026021727 Oct 202615 Sep 203015 Sep 2030Not yet due0
Capital Tower & Silver LeafShinde Dream Buildcon LLPPR126000260194717 Sep 202631 Aug 203131 Aug 2031Not yet due0
Adhishree ParadiseAdhshree DevelopersPR126000260154013 Aug 202613 May 202813 May 2028Not yet due0
Gujar Somani ArcadeSomani Landmarks LLPPM126000260131327 Jul 20261 Jul 20281 Nov 2028Extended 4 mo0
Leo VillasPrathmesh BuildersPR126000260098530 Jun 202631 Dec 203130 Apr 2032Extended 4 mo0
Vasundhara RajVasundhara RajPR126000260097729 Jun 202631 Dec 203130 Apr 2032Extended 4 mo0
S R Park Phase 7S R Group Promoter And BuildersPR126000260084218 Jun 202631 Mar 203031 Jul 2030Extended 4 mo0
Samarth Paradise Phase 5Vaibhav Hanumant KawadePM126000260076612 Jun 202631 Dec 202930 Apr 2030Extended 4 mo0
Darade Chavan ComplexDarade Chavan AssociatesPM12600026006664 Jun 202631 Dec 202930 Apr 2030Extended 4 mo0
Mayureshwar Classic AMayureshwar ConstructionPR126000260018418 Apr 202620 Jan 202920 May 2029Extended 4 mo0
Aditya ClassicAadishree CapitalPR126000260014317 Apr 202631 Dec 203130 Apr 2032Extended 4 mo0
Advik IconAdvik PropertiesPM126000260012617 Apr 202630 Jun 202830 Oct 2028Extended 4 mo0
SPAR AccenturesSpar AccenturesPM12600026000286 Apr 202631 Dec 203330 Apr 2034Extended 4 mo0
Tanai M Building BSurekha Vishnu KumbharPR126000250288718 Mar 202625 Mar 202825 Jul 2028Extended 4 mo0
Vrindavan ViharPrafull Dashrath Pawar And AssociatesPM126000250275312 Mar 202630 Sep 202730 Jan 2028Extended 4 mo0
Samarth HeightsM/s Samarth DevelopersPM12600025025864 Mar 20261 Jun 20291 Oct 2029Extended 4 mo0
Sujit PrideTanishq Builders And DevelopersPR126000250243623 Feb 202613 Feb 202913 Jun 2029Extended 4 mo0
Nirvana HomesOakspace RealtyP521000810905 Feb 202631 Dec 202830 Apr 2029Extended 4 mo0
Swapnapurti ParkDS ConstructionPR126000250208916 Jan 202631 Dec 202930 Apr 2030Extended 4 mo0
Chaitanya ShrushtiChaitanya BuildersPR12600025019865 Jan 202630 Sep 203130 Jan 2032Extended 4 mo0
Aishwarya TownshipRaj ConstructionPR12600025017065 Dec 202520 Feb 202720 Feb 2027Not yet due0
Isha ResidencyK K DevelopersPM12600025016723 Dec 20251 Jul 20281 Nov 2028Extended 4 mo0
Shriram EliteShriram Builders and DevelopersPR12600025016342 Dec 202531 Dec 203030 Apr 2031Extended 4 mo0
Adi AnviAdi DevelopersPM126000250150618 Nov 202531 Dec 203130 Apr 2032Extended 4 mo0
Malgunde IconMalgunde Balgude DevelopersPM126000250062321 Aug 20258 Apr 20308 Aug 2030Extended 4 mo0

Other localities in Baramati

Most active promoters

By projects registered here, as named on MahaRERA.

  1. Mehta Builders8 projects
  2. Adi Developers4 projects
  3. Surekha vishnu Kumbhar4 projects
  4. D S Construction3 projects
  5. R. H. Associates3 projects
  6. S R Group Promoter And Builders3 projects
  7. Chaitanya Builders2 projects
  8. Mayureshwar Construction2 projects
  9. Pratap Laxman Chavan2 projects
  10. Prathmesh Bajrang Kharmate2 projects
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology