RERA projects in Jalochi
124 projects under 125 MahaRERA registrations, registered 2017–2026. 44% have a completion date extended beyond the one promised.
Locality
124RERA projects
125Registrationssome projects hold several
63Completion still due62 past their completion date
4 monthsMedian extension beyond promised date44% of registrations extended
2Regulatory caseson 2 projects
260Buildings on recordfrom registration certificates
Registrations per year
New MahaRERA registrations by registration date.
| Year | Registrations |
|---|---|
| 2017 | 12 |
| 2018 | 6 |
| 2019 | 3 |
| 2020 | 5 |
| 2021 | 11 |
| 2022 | 17 |
| 2023 | 18 |
| 2024 | 16 |
| 2025 | 17 |
| 2026 | 20 |
Projects in Jalochi
124 projects registered with MahaRERA.
| Project | RERA | Registered | Promised completion | Revised completion | Timing | Cases |
|---|---|---|---|---|---|---|
| Gokul ResidencyRajmata Infra | PM1260002602172 | 7 Oct 2026 | 15 Sep 2030 | 15 Sep 2030 | Not yet due | 0 |
| Capital Tower & Silver LeafShinde Dream Buildcon LLP | PR1260002601947 | 17 Sep 2026 | 31 Aug 2031 | 31 Aug 2031 | Not yet due | 0 |
| Adhishree ParadiseAdhshree Developers | PR1260002601540 | 13 Aug 2026 | 13 May 2028 | 13 May 2028 | Not yet due | 0 |
| Gujar Somani ArcadeSomani Landmarks LLP | PM1260002601313 | 27 Jul 2026 | 1 Jul 2028 | 1 Nov 2028 | Extended 4 mo | 0 |
| Leo VillasPrathmesh Builders | PR1260002600985 | 30 Jun 2026 | 31 Dec 2031 | 30 Apr 2032 | Extended 4 mo | 0 |
| Vasundhara RajVasundhara Raj | PR1260002600977 | 29 Jun 2026 | 31 Dec 2031 | 30 Apr 2032 | Extended 4 mo | 0 |
| S R Park Phase 7S R Group Promoter And Builders | PR1260002600842 | 18 Jun 2026 | 31 Mar 2030 | 31 Jul 2030 | Extended 4 mo | 0 |
| Samarth Paradise Phase 5Vaibhav Hanumant Kawade | PM1260002600766 | 12 Jun 2026 | 31 Dec 2029 | 30 Apr 2030 | Extended 4 mo | 0 |
| Darade Chavan ComplexDarade Chavan Associates | PM1260002600666 | 4 Jun 2026 | 31 Dec 2029 | 30 Apr 2030 | Extended 4 mo | 0 |
| Mayureshwar Classic AMayureshwar Construction | PR1260002600184 | 18 Apr 2026 | 20 Jan 2029 | 20 May 2029 | Extended 4 mo | 0 |
| Aditya ClassicAadishree Capital | PR1260002600143 | 17 Apr 2026 | 31 Dec 2031 | 30 Apr 2032 | Extended 4 mo | 0 |
| Advik IconAdvik Properties | PM1260002600126 | 17 Apr 2026 | 30 Jun 2028 | 30 Oct 2028 | Extended 4 mo | 0 |
| SPAR AccenturesSpar Accentures | PM1260002600028 | 6 Apr 2026 | 31 Dec 2033 | 30 Apr 2034 | Extended 4 mo | 0 |
| Tanai M Building BSurekha Vishnu Kumbhar | PR1260002502887 | 18 Mar 2026 | 25 Mar 2028 | 25 Jul 2028 | Extended 4 mo | 0 |
| Vrindavan ViharPrafull Dashrath Pawar And Associates | PM1260002502753 | 12 Mar 2026 | 30 Sep 2027 | 30 Jan 2028 | Extended 4 mo | 0 |
| Samarth HeightsM/s Samarth Developers | PM1260002502586 | 4 Mar 2026 | 1 Jun 2029 | 1 Oct 2029 | Extended 4 mo | 0 |
| Sujit PrideTanishq Builders And Developers | PR1260002502436 | 23 Feb 2026 | 13 Feb 2029 | 13 Jun 2029 | Extended 4 mo | 0 |
| Nirvana HomesOakspace Realty | P52100081090 | 5 Feb 2026 | 31 Dec 2028 | 30 Apr 2029 | Extended 4 mo | 0 |
| Swapnapurti ParkDS Construction | PR1260002502089 | 16 Jan 2026 | 31 Dec 2029 | 30 Apr 2030 | Extended 4 mo | 0 |
| Chaitanya ShrushtiChaitanya Builders | PR1260002501986 | 5 Jan 2026 | 30 Sep 2031 | 30 Jan 2032 | Extended 4 mo | 0 |
| Aishwarya TownshipRaj Construction | PR1260002501706 | 5 Dec 2025 | 20 Feb 2027 | 20 Feb 2027 | Not yet due | 0 |
| Isha ResidencyK K Developers | PM1260002501672 | 3 Dec 2025 | 1 Jul 2028 | 1 Nov 2028 | Extended 4 mo | 0 |
| Shriram EliteShriram Builders and Developers | PR1260002501634 | 2 Dec 2025 | 31 Dec 2030 | 30 Apr 2031 | Extended 4 mo | 0 |
| Adi AnviAdi Developers | PM1260002501506 | 18 Nov 2025 | 31 Dec 2031 | 30 Apr 2032 | Extended 4 mo | 0 |
| Malgunde IconMalgunde Balgude Developers | PM1260002500623 | 21 Aug 2025 | 8 Apr 2030 | 8 Aug 2030 | Extended 4 mo | 0 |
Other localities in Baramati
Most active promoters
By projects registered here, as named on MahaRERA.
- Mehta Builders8 projects
- Adi Developers4 projects
- Surekha vishnu Kumbhar4 projects
- D S Construction3 projects
- R. H. Associates3 projects
- S R Group Promoter And Builders3 projects
- Chaitanya Builders2 projects
- Mayureshwar Construction2 projects
- Pratap Laxman Chavan2 projects
- Prathmesh Bajrang Kharmate2 projects
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology