RERA projects in Sawangi

2 projects under 2 MahaRERA registrations, registered 2018–2020. 50% have a completion date extended beyond the one promised.

Locality
2RERA projects
2Registrations
0Completion still due2 past their completion date, 1 marked completed
6 monthsMedian extension beyond promised date50% of registrations extended
0Regulatory casesnone on MahaRERA's lists
6Buildings on recordfrom registration certificates

Registrations per year

New MahaRERA registrations by registration date.

MahaRERA registrations per year
YearRegistrations
20181
20190
20201

Projects in Sawangi

2 projects registered with MahaRERA.

ProjectRERARegisteredPromised completionRevised completionTimingCases
Geetaban Residency Phase-2Bhaishree Ventures LLPP515000254868 Jun 202030 Sep 202331 Mar 2024Extended 6 mo0
Geetaban ResidencyBhaishree VenturesP515000163273 May 201830 Dec 2021—Completed0

Other localities in Gangapur

Most active promoters

By projects registered here, as named on MahaRERA.

  1. Bhaishree Ventures1 project
  2. Bhaishree Ventures LLP1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology