RERA projects in Sawangi
2 projects under 2 MahaRERA registrations, registered 2018–2020. 50% have a completion date extended beyond the one promised.
Locality
2RERA projects
2Registrations
0Completion still due2 past their completion date, 1 marked completed
6 monthsMedian extension beyond promised date50% of registrations extended
0Regulatory casesnone on MahaRERA's lists
6Buildings on recordfrom registration certificates
Registrations per year
New MahaRERA registrations by registration date.
| Year | Registrations |
|---|---|
| 2018 | 1 |
| 2019 | 0 |
| 2020 | 1 |
Projects in Sawangi
2 projects registered with MahaRERA.
| Project | RERA | Registered | Promised completion | Revised completion | Timing | Cases |
|---|---|---|---|---|---|---|
| Geetaban Residency Phase-2Bhaishree Ventures LLP | P51500025486 | 8 Jun 2020 | 30 Sep 2023 | 31 Mar 2024 | Extended 6 mo | 0 |
| Geetaban ResidencyBhaishree Ventures | P51500016327 | 3 May 2018 | 30 Dec 2021 | — | Completed | 0 |
Other localities in Gangapur
Most active promoters
By projects registered here, as named on MahaRERA.
- Bhaishree Ventures1 project
- Bhaishree Ventures LLP1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology