21 projects under 21 MahaRERA registrations, registered 2017–2026. 21% have a completion date extended beyond the one promised.

Taluka
21RERA projects
21Registrations
4Completion still due10 past their completion date, 5 marked completed
36 monthsMedian extension beyond promised date21% of registrations extended
0Regulatory casesnone on MahaRERA's lists
14Buildings on recordfrom registration certificates

Registrations per year

New MahaRERA registrations by registration date.

MahaRERA registrations per year
YearRegistrations
20172
20182
20192
20201
20212
20221
20233
20240
20250
20261

Projects in Gangapur

21 projects registered with MahaRERA in this taluka and the places within it.

ProjectRERARegisteredPromised completionRevised completionTimingCases
Waluj Trade TowerGovind EnterprisesPC104000260114913 Jul 202631 Dec 2030—Not yet due0
Kashi Gopal ParkKamalakar Sabne, Sudhakar Sabne, Prabhakar Sabne And Madhukar SabneP515000502841 Apr 202325 Dec 2025—Promised date passed0
Renuka NagariShlok RealtyP515000502881 Apr 202331 Mar 2027—Not yet due0
Pushp Nagari Phase 1Shilp ConstructionsP5150004898024 Jan 20231 Dec 2024—Promised date passed0
Vinayak Business CenterVinayak EnterprisesP515000478811 Dec 202231 Mar 2027—Completed0
Bhanudas Nagar Phase IINinad Narendra KhocheP5150002799324 Jan 202131 Mar 2021—Completed0
Bhanudas Nagar Phase-IJoshi AssociatesP5150002794421 Jan 202131 Mar 2021—Completed0
Geetaban Residency Phase-2Bhaishree Ventures LLPP515000254868 Jun 202030 Sep 202331 Mar 2024Extended 6 mo0
Khaswa ParkShaikh Subhan Bapuji Patel, Shaikh Farooq Ibrahim And Mohammad Musa Mohammad Ismali BagwanP5150002361220 Dec 201928 Nov 2021—Promised date passed0
Samruddhi ParkMilind Shriram Patil And Manoj Rajaram NimbalkarP5150002275616 Oct 201910 Apr 2021—Completed0
Kaushalya NagariKaushalya InfraP515000179923 Oct 201830 Sep 2018—Promised date passed0
Geetaban ResidencyBhaishree VenturesP515000163273 May 201830 Dec 2021—Completed0
Mulay I SquareGangamai Industries and constructions Limited AND Nirman Constructions JVP515000051189 Aug 201730 Mar 202331 Mar 2026Extended 36 mo0
Udyog KaushalyaFaith Build Constructions Pvt LtdP515000050679 Aug 201715 Oct 202331 Dec 2030Extended 86 mo0
Bansilal NagarP51500028458————0
GoyalmusaP51500026205————0
KrishnanagarP51500026471————0
P51500033400P51500033400————0
PMAY591 EWS housing in S.no 29 Mouje Ambewadi GangapurP51500029399————0
Ramesh Dattatray JadhavP51500027153————0
Sai NagarP51500026793————0

Other talukas in Aurangabad

Most active promoters

By projects registered here, as named on MahaRERA.

  1. Bhaishree Ventures1 project
  2. Bhaishree Ventures LLP1 project
  3. Faith Build Constructions Pvt Ltd1 project
  4. Gangamai Industries and constructions Limited AND Nirman Constructions JV1 project
  5. Govind Enterprises1 project
  6. Joshi Associates1 project
  7. Kamalakar Sabne, Sudhakar Sabne, Prabhakar Sabne And Madhukar Sabne1 project
  8. Kaushalya Infra1 project
  9. Milind Shriram Patil And Manoj Rajaram Nimbalkar1 project
  10. Ninad Narendra Khoche1 project
Data through8 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology