8 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.

RERA projects27
Registrations27
Completion still due1512 past their date
Median extension4 months41% of registrations extended
Regulatory cases0none on MahaRERA's lists

8 in 10 registrations run late here

27 MahaRERA registrations in Shukrawar Peth

6 not yet due9 extended, not yet due12 past even the latest date

Extended registrations moved their completion date by a median of 4 months.

Projects in Shukrawar Peth

27 projects registered with MahaRERA.

ProjectDeliveryMedian ₹/sq ftBooked
VishnupadIcon RealtyDue Jun 2029——
SamarthAarambh ConstructionsDue Apr 2029, extended 4 mo——
ShantiniketanIcon RealtyDue Apr 2029, extended 4 mo——
Yugal NirayanYugal BuildersDue Jan 2030, extended 4 mo——
Naik HeritageJamaluddin KhanDue Dec 2026, extended 4 mo——
All 27 projects →
Shukrawar Peth market reportPDF: prices and rents, volumes, projects ranked by deals and the most delayed — with the latest exact salesSee what's inside · from ₹1,999

Most active promoters

  1. Icon Realty2 projects
  2. Aarambh Constructions1 project
  3. Ambalal and Sons1 project
  4. Athesh Developers1 project
  5. Bhaktamar Realities Llp1 project
  6. Gokhale Empires Llp1 project
  7. Gokhale Ventures LLP1 project
  8. Hindustan Builders1 project
  9. Hublikar Rathi1 project
  10. Jamaluddin Khan1 project

Shukrawar Peth, in questions

How many projects in Shukrawar Peth run late?

8 in 10 MahaRERA registrations (21 of 27): their completion date was extended or has passed, data through 3 Nov 2026.

Where does this data come from?

From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Shukrawar Peth by Deedo. Medians on fewer than 3 deeds are not shown.

Data through3 Nov 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology