RERA projects in Dombivli

405 projects under 413 MahaRERA registrations, registered 2017–2026. 16% have a completion date extended beyond the one promised.

Locality
405RERA projects
413Registrationssome projects hold several
170Completion still due243 past their completion date, 7 marked completed
18 monthsMedian extension beyond promised date16% of registrations extended
21Regulatory caseson 3 projects
54Buildings on recordfrom registration certificates

Registrations per year

New MahaRERA registrations by registration date.

MahaRERA registrations per year
YearRegistrations
201778
201823
201924
202038
202130
202249
202364
202448
202545
202614

Projects in Dombivli

405 projects registered with MahaRERA.

ProjectRERARegisteredPromised completionRevised completionTimingCases
The MeadowsPriism InfraaPR13300026018258 Sep 202631 Aug 2029—Not yet due0
Om Ganesh PujaBrahmand LifespacesPR13300026017967 Sep 202613 Feb 2028—Not yet due0
Payal Business ParkPayal Marble IndustriesPC13300026006948 Jun 202631 Dec 2028—Not yet due0
VedvikaM/s The ImpressionsPR13300026006765 Jun 202631 Dec 2031—Not yet due0
YashrajFore HoldingsPM133000260052122 May 202631 Dec 2028—Not yet due0
Globe AltusGlobe Prime InfraPC133000260039712 May 202631 Dec 2031—Not yet due0
YashogiriPacific Innovations LLPPR13300026003717 May 202615 Mar 2029—Not yet due0
Herambh HightsVarad InfraPR133000260009415 Apr 202631 Mar 2029—Not yet due0
Omkar SrushtiM/s Omkar ConstructionPM133000250300618 Mar 202630 Jun 2028—Not yet due0
Vedansh ResidencyLotus DevelopersPR133000250294618 Mar 202630 Jun 2028—Not yet due0
Sunrise BlissBhanushalisunrise Infrastructure LLPPR133000250270311 Mar 202631 Dec 2028—Not yet due0
Aditya Darshan ChsOm Swaminarayan InfraPR13300025026769 Mar 202631 Mar 2031—Not yet due0
Mangalmurti SerenityBhairav EnterprisesPR133000250209416 Jan 202631 Dec 2028—Not yet due0
New Arpan ChsShresht DevelopersPR133000250195831 Dec 202531 Oct 2028—Not yet due0
Ambrin 2ImpressionsPR133000250178815 Dec 202531 Dec 2027—Not yet due0
splendor westendM/S Splendor CreationPR13300025016532 Dec 202530 Apr 2030—Not yet due0
Sajan Shantaram KrupaTirupati DevelopersP5170008103231 Oct 202531 Dec 2030—Not yet due0
Sneh ShilpSneh SheltersP5170008103431 Oct 20251 May 2028—Not yet due0
Jay Annapurna Co Operative Housing Society LtdS M EnterprisesP5170008101614 Oct 202530 Dec 2027—Not yet due0
Kubber ZenitthYogiraj SkylinePR133000250120213 Oct 202525 Feb 2028—Not yet due0
Shree SparshOmkar RealtyPR133000250119013 Oct 202530 Sep 2027—Not yet due0
Shree Ram Krishna Hari ComplexRam Krishna Hari DevelopersPR13300025011179 Oct 202530 Dec 2028—Not yet due0
Dinkar EmpireD. K. Patil Builders And DevelopersPM13300025007249 Sep 202531 Dec 2031—Not yet due0
Ram JankiFore HoldingsPM13300025007033 Sep 202523 Dec 2027—Not yet due0
Dipex Kiran Co-Operative Housing Society LtdSkyfly Builders & Developers Private LimitedPR13300025006831 Sep 202531 Dec 2027—Not yet due0

Other localities in Kalyan

Most active promoters

By projects registered here, as named on MahaRERA.

  1. Bhalchandra Wadnerkar5 projects
  2. Runwal Residency Private Limited5 projects
  3. Swaminarayan Life Space LLP5 projects
  4. Fore Holdings4 projects
  5. Impressions4 projects
  6. Impressions Nxt4 projects
  7. Neelpadma Associates4 projects
  8. Splendor Shelters Pvt Ltd4 projects
  9. Horizon Projects Pvt Ltd3 projects
  10. Narendra Kalyanji Patel3 projects
Data through11 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology