5 in 10 MahaRERA registrations here have pushed their completion date back.

RERA projects140
Registrations143some projects hold several
Completion still due8657 past their date
Median extension4 months52% of registrations extended
Regulatory cases5on 4 projects
Kalyan market reportPDF: prices and rents, volumes, projects ranked by deals and the most delayed — with the latest exact salesSee what's inside · from ₹1,999

8 in 10 registrations run late here

143 MahaRERA registrations in Kalyan

3 completed27 not yet due59 extended, not yet due54 past even the latest date

Extended registrations moved their completion date by a median of 4 months.

Projects in Kalyan

140 projects registered with MahaRERA.

ProjectRERARegisteredPromised completionRevised completionTimingCases
Heena HeightsH K EnterprisesPR133101260245919 Oct 202631 Dec 2030—Not yet due0
Vighnaharta ApartmentM/s Dreams RealtyPR133000260235416 Oct 202631 Dec 2030—Not yet due0
Vakratund Residency-1Pramod EnterprisesPM133000260226513 Oct 20261 Dec 2028—Not yet due0
Seasons MannatSeasonssai Lifespaces LLPPM13310126017522 Sep 202631 Dec 203331 Dec 2033Not yet due0
Sarvoday AfrozSarvoday CombinePR133000260132828 Jul 202631 Dec 203030 Apr 2031Extended 4 mo0
Santosshi AvenueR A O Construction And DevelopersPM133000260083918 Jun 202631 Dec 203130 Apr 2032Extended 4 mo0
Gayatri SamarthGayatri BuildersP5170008112511 May 202631 Mar 202931 Jul 2029Extended 4 mo0
New Chaitanya PrabhaOm DevelopersPR13300026000479 Apr 202625 Feb 202925 Jun 2029Extended 4 mo0
Kiran EnclaveS K RaghuraajPR133000250302123 Mar 202631 Mar 202931 Jul 2029Extended 4 mo0
Om DuttakrupaTulsi Group 13PM133000250287517 Mar 202631 Dec 202830 Apr 2029Extended 4 mo0
KulswaminiKulswamini DevelopersPM13300025025442 Mar 202631 Dec 202730 Apr 2028Extended 4 mo0
Global EliteRonak EnterprisesPR133000250237616 Feb 202615 Sep 202915 Sep 2029Not yet due0
Barku HorizonShree Datta DevelopersPR133000250175912 Dec 202531 Dec 203031 Dec 2030Not yet due0
Moryagolden ImperialMoryagolden Imperial LLPPM13300025017118 Dec 202531 Dec 203031 Dec 2030Not yet due0
Sarvoday Patwardhan Baug - Building No 2Sarvoday DevelopersPR13300025016955 Dec 202531 Dec 202830 Apr 2029Extended 4 mo0
Sarvoday 1Thalia Investment Private LimitedP5170008101110 Oct 202531 Dec 202830 Apr 2029Extended 4 mo0
Shelar SupremusShelar RealtyPR133000250094124 Sep 202531 Dec 202930 Apr 2030Extended 4 mo0
Regency SolitaireJohar Hasan ZojwallaPM133000250090222 Sep 202531 Dec 203230 Apr 2033Extended 4 mo0
Stella Co-Operative Housing Society LtdSaksham GroupPR133000250065726 Aug 202531 Dec 202730 Apr 2028Extended 4 mo0
Malhar EnclaveSm EnterprisesPR133000250056514 Aug 202531 May 202830 Sep 2028Extended 4 mo0
Dream AtlantisDream Maruti InfraP5170008083516 Jul 202531 Dec 203030 Apr 2031Extended 4 mo0
Panchratna SapphirePanchratna DevelopersP5170008082414 Jul 202531 Dec 202830 Apr 2029Extended 4 mo0
Phoenix Aura phase 2Phoenix BuildconP5170008082114 Jul 202530 Jan 202730 May 2027Extended 4 mo0
Junomoneta - PlutoPalika Infratech LLPP517000807817 Jul 202531 Dec 203130 Apr 2032Extended 4 mo0
Junomoneta - ApolloPalika Infratech LLPP517000807513 Jul 202531 Dec 203130 Apr 2032Extended 4 mo0

Most active promoters

  1. Palika Infratech LLP4 projects
  2. Sarvoday Combine3 projects
  3. Johar Hasan Zojwalla2 projects
  4. Mangesh Dashrath Gaikar2 projects
  5. Om Developers2 projects
  6. Vertex Newton Projects Private Limited2 projects
  7. Vpa Developers2 projects
  8. Aliakbar Yusuf Zojwalla1 project
  9. Amrut Builders1 project
  10. Amrut Niwas1 project
Data through21 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Methodology