Skip to content

Katemanevali, Thane

Deedo IDDL-THN-KATEMANEVALI

9 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.

RERA projects59
Registrations60some projects hold several
Completion still due3228 past their date
Median extension4 months55% of registrations extended
Regulatory cases0none on MahaRERA's lists

9 in 10 registrations run late here

60 MahaRERA registrations in Katemanevali

1 completed8 not yet due24 extended, not yet due27 past even the latest date

Extended registrations moved their completion date by a median of 4 months.

Projects in Katemanevali

59 projects registered with MahaRERA.

ProjectDeliveryMedian ₹/sq ftBooked
Royal HillsRoyal Builders and DevelopersDue Dec 2029——
Sai Dream World Building No 04 Sai Dream VertexSai Shrishti ConstructionsDue Dec 2029——
Sai Dream World Building No 01 (Sai Dream Signature)Sai Shrishti ConstructionDue Dec 2030——
Samarth AlturaPragati ConstructionsDue Dec 2031——
Ananntshree PearlAvighna KaranDue Apr 2030, extended 4 mo——
All 59 projects →
Katemanevali market reportPDF: prices and rents, volumes, projects ranked by deals and the most delayed — with the latest exact salesSee what's inside · from ₹1,999

Most active promoters

  1. Rai Residency Private Limited4 projects
  2. Pragati Constructions3 projects
  3. Avighna Karan2 projects
  4. Ganesh Developers2 projects
  5. Pawshe Group Builders And Developers2 projects
  6. Shree Prabhat Developer2 projects
  7. Aaradhana Construction1 project
  8. Alka Prakash Mhatre1 project
  9. Anil Shilpayatan Private Limited1 project
  10. Aradhna Construction1 project

Katemanevali, in questions

How many projects in Katemanevali run late?

9 in 10 MahaRERA registrations (51 of 60): their completion date was extended or has passed, data through 21 Oct 2026.

Where does this data come from?

From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Katemanevali by Deedo. Medians on fewer than 3 deeds are not shown.

Data through21 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology