RERA projects in Khoni
71 projects under 93 MahaRERA registrations, registered 2017–2025. 2% have a completion date extended beyond the one promised.
71RERA projects
93Registrationssome projects hold several
24Completion still due69 past their completion date
39 monthsMedian extension beyond promised date2% of registrations extended
8Regulatory caseson 8 projects
21Buildings on recordfrom registration certificates
Registrations per year
New MahaRERA registrations by registration date.
| Year | Registrations |
|---|---|
| 2017 | 30 |
| 2018 | 10 |
| 2019 | 18 |
| 2020 | 8 |
| 2021 | 1 |
| 2022 | 3 |
| 2023 | 5 |
| 2024 | 2 |
| 2025 | 16 |
Projects in Khoni
71 projects registered with MahaRERA.
| Project | RERA | Registered | Promised completion | Revised completion | Timing | Cases |
|---|---|---|---|---|---|---|
| Khoni Pinnacle HeightsEdhan Industrial Solution LLP | PM1330002501569 | 24 Nov 2025 | 31 Dec 2029 | — | Not yet due | 0 |
| LVR Palava -Ready Villa's on landLodha Developers Limited | PR1330002501064 | 1 Oct 2025 | 31 Mar 2028 | — | Not yet due | 0 |
| Villa ImperioLodha Developers Limited | PP1330002500716 | 4 Sep 2025 | 31 Dec 2030 | — | Not yet due | 0 |
| LilyLodha Developers Limited | P51700079712, P51700079715, P51700079771 +2 | 21 Mar 2025 | 30 Sep 2035 | — | Not yet due | 0 |
| Lily E and FLodha Developers Limited | P51700079713 | 21 Mar 2025 | 30 Sep 2034 | — | Not yet due | 0 |
| DaffodilLodha Developers Limited | P51700079649, P51700079763, P51700079776 +4 | 18 Mar 2025 | 30 Sep 2030 | — | Not yet due | 0 |
| IL Palazzo, Hanging Gardens PalavaLodha Developers Limited | P51700077356 | 9 Aug 2024 | 31 Mar 2030 | 31 Mar 2030 | Not yet due | 0 |
| MLCP 3 Retail ShopsMacrotech Developers Limited | P51700077338 | 9 Aug 2024 | 31 Dec 2024 | — | Promised date passed | 0 |
| PearlLodha Developers Limited | P51700053067 | 12 Oct 2023 | 31 Mar 2028 | 31 Mar 2028 | Not yet due | 0 |
| OliviaLodha Developers Limited | P51700052243, P51700052470 | 2 Aug 2023 | 30 Jun 2027 | — | Not yet due | 0 |
| TulipLodha Developers Limited | P51700051956 | 13 Jul 2023 | 31 May 2027 | — | Not yet due | 0 |
| Pearl BMacrotech Developers Limited | P51700048930 | 24 Jan 2023 | 31 Jul 2026 | — | Promised date passed | 0 |
| Lodha Villa Royale PalavaLodha Developers Limited | P51700047245 | 13 Oct 2022 | 30 Sep 2025 | — | Promised date passed | 0 |
| Pearl AMacrotech Developers Limited | P51700034753 | 28 Apr 2022 | 31 Dec 2025 | — | Promised date passed | 0 |
| Violet G, H and ILodha Developers Limited | P51700033960 | 14 Mar 2022 | 30 Apr 2026 | — | Promised date passed | 0 |
| Palava Azzurra E To HPalava Dwellers Private Limited | P51700028098 | 31 Jan 2021 | 30 Jun 2026 | — | Promised date passed | 1 |
| North MLCP ShopPalava Dwellers Private Limited | P51700025674 | 1 Jul 2020 | 31 Jul 2020 | — | Promised date passed | 0 |
| Lakeside 1 ShopsPalava Dwellers Private Limited | P51700025522 | 28 Jun 2020 | 31 Jul 2020 | — | Promised date passed | 0 |
| Lakeside 2 ShopsPalava Dwellers Private Limited | P51700025535 | 28 Jun 2020 | 31 Jul 2020 | — | Promised date passed | 0 |
| Clara ShopsPalava Dwellers Private Limited | P51700025495 | 8 Jun 2020 | 31 Jul 2020 | — | Promised date passed | 0 |
| Elite 1 ShopPalava Dwellers Private Limited | P51700025471 | 3 Jun 2020 | 31 Jul 2020 | — | Promised date passed | 0 |
| Elite 2 ShopsPalava Dwellers Private Limited | P51700025470 | 3 Jun 2020 | 31 Jul 2020 | — | Promised date passed | 0 |
| Regalia ShopsPalava Dwellers Private Limited | P51700025474 | 3 Jun 2020 | 31 Jul 2020 | — | Promised date passed | 0 |
| Urbano 2 ShopsPalava Dwellers Private Limited | P51700025475 | 3 Jun 2020 | 31 Jul 2020 | — | Promised date passed | 0 |
| Violet A to CPalava Dwellers Pvt Ltd | P51700022900 | 1 Nov 2019 | 31 Jul 2024 | — | Promised date passed | 0 |
| JasminePalava Dwellers Pvt Ltd | P51700020354, P51700020373, P51700020381 | 5 Apr 2019 | 30 Mar 2023 | — | Promised date passed | 1 |
| Palava Verde A - EPalava Dwellers Pvt Ltd | P51700020267 | 30 Mar 2019 | 30 May 2025 | — | Promised date passed | 1 |
| Palava Aurelia APalava Dwellers Private Limited | P51700020161 | 29 Mar 2019 | 29 Aug 2024 | — | Promised date passed | 0 |
| Palava FrescaPalava Dwellers Pvt Ltd | P51700020139, P51700020166 | 29 Mar 2019 | 27 Nov 2026 | — | Not yet due | 0 |
| Palava Fresca A and BPalava Dwellers Pvt Ltd | P51700020160 | 29 Mar 2019 | 30 May 2026 | — | Promised date passed | 1 |
| Palava Fresca E to HPalava Dwellers Pvt Ltd | P51700020165 | 29 Mar 2019 | 30 May 2026 | — | Promised date passed | 1 |
| Palava MagnoliaLodha Developers Limited | P51700020131 | 29 Mar 2019 | 31 Dec 2029 | 31 Dec 2029 | Not yet due | 0 |
| Palava Olivia APalava Dwellers Private Limited | P51700020214 | 29 Mar 2019 | 28 Nov 2025 | — | Promised date passed | 1 |
| Palava SerenityPalava Dwellers Private Limited | P51700020155, P51700020253 | 29 Mar 2019 | 28 Nov 2025 | — | Promised date passed | 0 |
| Palava Serenity CPalava Dwellers Private Limited | P51700020159 | 29 Mar 2019 | 30 Mar 2025 | — | Promised date passed | 0 |
| Palava Serenity DPalava Dwellers Private Limited | P51700020124 | 29 Mar 2019 | 30 Apr 2024 | — | Promised date passed | 0 |
| Palava Verdana A to DPalava Dwellers Pvt Ltd | P51700020150 | 29 Mar 2019 | 28 Nov 2025 | — | Promised date passed | 1 |
| Orchid M N OPalava Dwellers Pvt Ltd | P51700019809 | 5 Mar 2019 | 30 Dec 2020 | — | Promised date passed | 0 |
| Palava Azzurra A To DPalava Dwellers Pvt Ltd | P51700019016 | 28 Dec 2018 | 30 Mar 2024 | — | Promised date passed | 0 |
| PALAVA ALLURA C and DPalava Dwellers Pvt Ltd | P51700018963 | 17 Dec 2018 | 30 Mar 2024 | — | Promised date passed | 1 |
| Palava Olivia CPalava Dwellers Private Limited | P51700017590 | 28 Aug 2018 | 28 Aug 2023 | — | Promised date passed | 0 |
| Palava Florea - A to DPalava Dwellers Private Limited | P51700017487 | 23 Aug 2018 | 31 Jul 2023 | — | Promised date passed | 0 |
| Palava - Retail Shop no 15 to 33 - Car Park Building C1Palava Dwellers Private Limited | P51700016941 | 22 Jun 2018 | 30 Sep 2018 | — | Promised date passed | 0 |
| Survey No 162 Village Khoni Tal KalyanMaharashtra Housing And Area Development Authority | P51700016831 | 18 Jun 2018 | 9 Jan 2022 | 7 Jan 2028 | Extended 72 mo | 0 |
| Orchid A to LPalava Dwellers Pvt Ltd | P51700016747 | 12 Jun 2018 | 30 Jun 2018 | — | Promised date passed | 0 |
| Palava - Trinity A to CPalava Dwellers Private Limited | P51700014396 | 29 Nov 2017 | 30 Mar 2023 | — | Promised date passed | 0 |
| Palava MarvellaPalava Dwellers Private Limited | P51700013462, P51700015660 | 7 Oct 2017 | 30 Jun 2023 | — | Promised date passed | 0 |
| Palava EstelaPalava Dwellers Private Limited | P51700013145, P51700013158 | 14 Sep 2017 | 30 Jun 2023 | — | Promised date passed | 0 |
| Palava AuroraPalava Dwellers Private Limited | P51700010960, P51700015090 | 31 Aug 2017 | 30 Oct 2023 | — | Promised date passed | 0 |
| PALAVA - ESTELA D to GPalava Dwellers Private Limited | P51700011068 | 31 Aug 2017 | 30 Mar 2023 | — | Promised date passed | 0 |
| Palava MilanoPalava Dwellers Private Limited | P51700011629, P51700015016 | 31 Aug 2017 | 30 Oct 2023 | — | Promised date passed | 0 |
| Palva Milano D, GPalava Dwellers Private Limited | P51700010109 | 24 Aug 2017 | 30 Mar 2023 | — | Promised date passed | 0 |
| Shree Hari ResidencyM/s SHREE ODHAV DEVELOPERS | P51700004461 | 9 Aug 2017 | 30 Jun 2018 | 31 Dec 2018 | Extended 6 mo | 0 |
| Palava Cluster 2-06 - A - G, I - NPalava Dwellers Private Limited | P51700000802 | 23 Jul 2017 | 30 Jun 2022 | — | Promised date passed | 0 |
| FONTANA A ,B, I and JPalava Dwellers Private Limited | P51700000506 | 18 Jul 2017 | 30 Dec 2022 | — | Promised date passed | 0 |
| Palava - Aurelia - D To GPalava Dwellers Private Limited | P51700000511 | 18 Jul 2017 | 30 Jan 2022 | — | Promised date passed | 0 |
| PALAVA CLARA A to D, D1Palava Dwellers Private Limited | P51700000448 | 18 Jul 2017 | 28 Feb 2022 | — | Promised date passed | 0 |
| Palava Fontana C - HPalava Dwellers Private Limited | P51700000596 | 18 Jul 2017 | 30 Dec 2020 | — | Promised date passed | 0 |
| Palava UrbanoPalava Dwellers Private Limited | P51700000577, P51700000696 | 18 Jul 2017 | 30 Dec 2022 | — | Promised date passed | 0 |
| Palava Clara J-MPalava Dwellers Private Limited | P51700000420 | 17 Jul 2017 | 30 Oct 2022 | — | Promised date passed | 0 |
| PALAVA EVIVA K to T, URBANO A, B, C and F, URBANO I to TPalava Dwellers Private Limited | P51700000419 | 17 Jul 2017 | 30 Jun 2019 | — | Promised date passed | 0 |
| Palava Cielo A - FPalava Dwellers Private Limited | P51700000378 | 15 Jul 2017 | 31 Dec 2018 | — | Promised date passed | 0 |
| Palava LakesidePalava Dwellers Private Limited | P51700000384, P51700000410 | 15 Jul 2017 | 31 Jul 2018 | — | Promised date passed | 0 |
| PALAVA PRIMIA E to JPalava Dwellers Private Limited | P51700000391 | 15 Jul 2017 | 28 Feb 2019 | — | Promised date passed | 0 |
| PALAVA REGALIA A to FPalava Dwellers Private Limited | P51700000390 | 15 Jul 2017 | 31 Dec 2018 | — | Promised date passed | 0 |
| PALAVA VIENTO A to DPalava Dwellers Private Limited | P51700000342 | 15 Jul 2017 | 31 Mar 2018 | — | Promised date passed | 0 |
| PALAVA VISTA A to DPalava Dwellers Private Limited | P51700000395 | 15 Jul 2017 | 30 Apr 2018 | — | Promised date passed | 0 |
| PALAVA - PASEO - D to HPalava Dwellers Private Limited | P51700000269 | 10 Jul 2017 | 30 Jun 2018 | — | Promised date passed | 0 |
| Palava ElitePalava Dwellers Private Limited | P51700000125, P51700000389 | 5 Jul 2017 | 31 Jul 2018 | — | Promised date passed | 0 |
| Palava Lagoona A To FPalava Dwellers Private Limited | P51700000124 | 5 Jul 2017 | 30 Jun 2018 | — | Promised date passed | 0 |
| Palava - Uno H - OPalava Dwellers Private Limited | P51700000142 | 5 Jul 2017 | 31 Dec 2017 | — | Promised date passed | 0 |
Other localities in Kalyan
- Dombivli404 projects
- Kalyandombivali (M Corp.)213 projects
- Kalyan137 projects
- Chikanghar107 projects
- Titwala89 projects
- Kalyan-Dombivali (M Corp.)78 projects
- Katemanevali55 projects
- Manda52 projects
- Tisgaon48 projects
- Gandhare43 projects
- Adharwadi24 projects
- Pisavali24 projects
Most active promoters
By projects registered here, as named on MahaRERA.
- Palava Dwellers Private Limited42 projects
- Lodha Developers Limited12 projects
- Palava Dwellers Pvt Ltd11 projects
- Macrotech Developers Limited3 projects
- Edhan Industrial Solution LLP1 project
- Maharashtra Housing And Area Development Authority1 project
- M/s SHREE ODHAV DEVELOPERS1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology