Khoni, Thane
Deedo IDDL-THN-KHONI10 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.
RERA projects74
Registrations96some projects hold several
Completion still due2472 past their date
Median extension4 months21% of registrations extended
Regulatory cases8on 8 projects
10 in 10 registrations run late here
96 MahaRERA registrations in Khoni
5 not yet due19 extended, not yet due72 past even the latest date
Extended registrations moved their completion date by a median of 4 months.
Projects in Khoni
74 projects registered with MahaRERA.
| Project | Delivery | Median ₹/sq ft | Booked |
|---|---|---|---|
| Khoni Pinnacle HeightsEdhan Industrial Solution LLP | Due Apr 2030, extended 4 mo | — | — |
| LVR Palava -Ready Villa's on landLodha Developers Limited | Due Jul 2028, extended 4 mo | — | — |
| Villa ImperioLodha Developers Limited | Due Dec 2030 | — | — |
| LilyLodha Developers Limited | Due Jan 2036, extended 4 mo | — | — |
| Lily E and FLodha Developers Limited | Due Jan 2035, extended 4 mo | — | — |
Nearby: other villages in Kalyan
Dombivli · 445 projectsKalyan · 176 projectsKalyandombivali (M Corp.) · 151 projectsChikanghar · 113 projectsTitwala · 94 projectsKalyan-Dombivali (M Corp.) · 60 projectsKatemanevali · 59 projectsTisgaon · 53 projectsManda · 52 projectsGandhare · 51 projectsPisavali · 26 projectsAdharwadi · 25 projects
Most active promoters
- Palava Dwellers Private Limited47 projects
- Lodha Developers Limited12 projects
- Palava Dwellers Pvt Ltd9 projects
- Macrotech Developers Limited3 projects
- Edhan Industrial Solution LLP1 project
- Maharashtra Housing And Area Development Authority1 project
- Shree Odhav Developers1 project
Khoni, in questions
How many projects in Khoni run late?
10 in 10 MahaRERA registrations (91 of 96): their completion date was extended or has passed, data through 21 Oct 2026.
Where does this data come from?
From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Khoni by Deedo. Medians on fewer than 3 deeds are not shown.
Data through21 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology