RERA projects in Manda

52 projects under 56 MahaRERA registrations, registered 2017–2026. 48% have a completion date extended beyond the one promised.

Locality
52RERA projects
56Registrationssome projects hold several
19Completion still due37 past their completion date, 1 marked completed
4 monthsMedian extension beyond promised date48% of registrations extended
1Regulatory caseson 1 project
87Buildings on recordfrom registration certificates

Registrations per year

New MahaRERA registrations by registration date.

MahaRERA registrations per year
YearRegistrations
201721
20187
20192
20204
20214
20228
20232
20242
20254
20262

Projects in Manda

52 projects registered with MahaRERA.

ProjectRERARegisteredPromised completionRevised completionTimingCases
Mangalmay HeightsMangalmay EnterprisesPR13300026014365 Aug 202631 Dec 202931 Dec 2029Not yet due0
Shripad ResidencySai Mauli EnterprisesP517000809941 Oct 202530 Nov 202830 Mar 2029Extended 4 mo0
Butterfly GardenOm Mangalmurti SthapatyaP517000799799 Apr 202531 Jul 202730 Nov 2027Extended 4 mo0
Sai ArcadeSai Siddhi EnterprisesP5170007969420 Mar 202531 Dec 202830 Apr 2029Extended 4 mo0
Mayureshwar ResidencyMayureshwar DevelopersP517000794757 Mar 202531 Mar 203431 Jul 2034Extended 4 mo0
Regency Sarvam Phase 13Regency Nirman LtdP517000768603 Jul 202431 Oct 202631 Dec 2025Not yet due0
GopalKrishnaPrakash Purushottam SamantP5170005577416 Apr 202431 Dec 202630 Apr 2027Extended 4 mo0
Ganpati PrasannaVijay Prabhakar PatilP517000485173 Jan 202331 Dec 202630 Apr 2027Extended 4 mo0
Aditya HeightsRatnakar Dharma PatilP5170004824419 Dec 202230 Jun 202530 Jun 2025Promised date passed0
Sai Vallabh C WingAvadhut EnterpriseP517000474612 Nov 202231 Dec 202531 Dec 2025Promised date passed0
Amrut Siddhi Building No 1 and 2Jayshree BuildersP5170004705727 Sep 202230 Sep 202530 Sep 2025Promised date passed0
Madhuban F WingAbhilasha VentureP5170004705327 Sep 202231 Dec 202630 Apr 2027Extended 4 mo0
Mega PearlMega Creative LLPP5170004627920 Jun 202231 Dec 202630 Apr 2027Extended 4 mo0
Jay ResidencyMukesh Vithal GiteP5170003484328 Apr 202231 Dec 202431 Dec 2024Promised date passed0
Kasturi PalazaArfa ConstructionP5170003495428 Apr 202230 Jun 202630 Oct 2026Extended 4 mo0
Charms City A12Charms DevelopersP5170003465420 Apr 202231 Jul 202431 Jul 2024Promised date passed1
SIDDHESHWAR HEIGHTS A WING FROM 2nd TO 14th FLOORShree Jai Malhar EnterprisesP5170003114211 Oct 202131 Dec 202417 Jan 2025Extended 1 mo0
Jagtap ApartmentVijayalakshmi DevelopersP5170003093029 Sep 202130 Jun 202330 Jun 2023Promised date passed0
Ganpati HeightsManoj Prabhakar PatilP5170002976329 Jun 202130 Sep 202630 Sep 2026Promised date passed0
Omkar ResidencyM/s OMKAR ASSOCIATESP5170002928518 May 202131 Dec 202531 Dec 2025Promised date passed0
Ashlar TattvaAkshar EnterprisesP51700027399, PR13300026006318 Dec 202031 Dec 202930 Apr 2030Extended 4 mo0
Nilgiri ResidencySai Vaishnavi EnterprisesP5170002500018 Mar 202030 Jun 202330 Sep 2023Extended 3 mo0
Ganraj HeightsShree Krishna ConstructionP5170002455218 Feb 202030 Dec 202430 Dec 2024Promised date passed0
Venus HeightsVenus InfraP5170002362924 Dec 201930 Dec 202430 Dec 2027Extended 36 mo0
Charms CityCharms DevelopersP51700019699, P5170004956122 Feb 201931 Dec 202830 Apr 2029Extended 4 mo0

Other localities in Kalyan

Most active promoters

By projects registered here, as named on MahaRERA.

  1. Charms Developers5 projects
  2. Abhilasha Venture2 projects
  3. Jayshree Builders2 projects
  4. Om Sai Residency2 projects
  5. Shree Jai Malhar Enterprises2 projects
  6. Adeshwar Associates1 project
  7. Akshar Enterprises1 project
  8. Arfa Construction1 project
  9. Avadhut Enterprise1 project
  10. Gurukripa Landholding LLP1 project
Data through15 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology