RERA projects in Manda
52 projects under 56 MahaRERA registrations, registered 2017–2026. 48% have a completion date extended beyond the one promised.
Locality
52RERA projects
56Registrationssome projects hold several
19Completion still due37 past their completion date, 1 marked completed
4 monthsMedian extension beyond promised date48% of registrations extended
1Regulatory caseson 1 project
87Buildings on recordfrom registration certificates
Registrations per year
New MahaRERA registrations by registration date.
| Year | Registrations |
|---|---|
| 2017 | 21 |
| 2018 | 7 |
| 2019 | 2 |
| 2020 | 4 |
| 2021 | 4 |
| 2022 | 8 |
| 2023 | 2 |
| 2024 | 2 |
| 2025 | 4 |
| 2026 | 2 |
Projects in Manda
52 projects registered with MahaRERA.
| Project | RERA | Registered | Promised completion | Revised completion | Timing | Cases |
|---|---|---|---|---|---|---|
| Mangalmay HeightsMangalmay Enterprises | PR1330002601436 | 5 Aug 2026 | 31 Dec 2029 | 31 Dec 2029 | Not yet due | 0 |
| Shripad ResidencySai Mauli Enterprises | P51700080994 | 1 Oct 2025 | 30 Nov 2028 | 30 Mar 2029 | Extended 4 mo | 0 |
| Butterfly GardenOm Mangalmurti Sthapatya | P51700079979 | 9 Apr 2025 | 31 Jul 2027 | 30 Nov 2027 | Extended 4 mo | 0 |
| Sai ArcadeSai Siddhi Enterprises | P51700079694 | 20 Mar 2025 | 31 Dec 2028 | 30 Apr 2029 | Extended 4 mo | 0 |
| Mayureshwar ResidencyMayureshwar Developers | P51700079475 | 7 Mar 2025 | 31 Mar 2034 | 31 Jul 2034 | Extended 4 mo | 0 |
| Regency Sarvam Phase 13Regency Nirman Ltd | P51700076860 | 3 Jul 2024 | 31 Oct 2026 | 31 Dec 2025 | Not yet due | 0 |
| GopalKrishnaPrakash Purushottam Samant | P51700055774 | 16 Apr 2024 | 31 Dec 2026 | 30 Apr 2027 | Extended 4 mo | 0 |
| Ganpati PrasannaVijay Prabhakar Patil | P51700048517 | 3 Jan 2023 | 31 Dec 2026 | 30 Apr 2027 | Extended 4 mo | 0 |
| Aditya HeightsRatnakar Dharma Patil | P51700048244 | 19 Dec 2022 | 30 Jun 2025 | 30 Jun 2025 | Promised date passed | 0 |
| Sai Vallabh C WingAvadhut Enterprise | P51700047461 | 2 Nov 2022 | 31 Dec 2025 | 31 Dec 2025 | Promised date passed | 0 |
| Amrut Siddhi Building No 1 and 2Jayshree Builders | P51700047057 | 27 Sep 2022 | 30 Sep 2025 | 30 Sep 2025 | Promised date passed | 0 |
| Madhuban F WingAbhilasha Venture | P51700047053 | 27 Sep 2022 | 31 Dec 2026 | 30 Apr 2027 | Extended 4 mo | 0 |
| Mega PearlMega Creative LLP | P51700046279 | 20 Jun 2022 | 31 Dec 2026 | 30 Apr 2027 | Extended 4 mo | 0 |
| Jay ResidencyMukesh Vithal Gite | P51700034843 | 28 Apr 2022 | 31 Dec 2024 | 31 Dec 2024 | Promised date passed | 0 |
| Kasturi PalazaArfa Construction | P51700034954 | 28 Apr 2022 | 30 Jun 2026 | 30 Oct 2026 | Extended 4 mo | 0 |
| Charms City A12Charms Developers | P51700034654 | 20 Apr 2022 | 31 Jul 2024 | 31 Jul 2024 | Promised date passed | 1 |
| SIDDHESHWAR HEIGHTS A WING FROM 2nd TO 14th FLOORShree Jai Malhar Enterprises | P51700031142 | 11 Oct 2021 | 31 Dec 2024 | 17 Jan 2025 | Extended 1 mo | 0 |
| Jagtap ApartmentVijayalakshmi Developers | P51700030930 | 29 Sep 2021 | 30 Jun 2023 | 30 Jun 2023 | Promised date passed | 0 |
| Ganpati HeightsManoj Prabhakar Patil | P51700029763 | 29 Jun 2021 | 30 Sep 2026 | 30 Sep 2026 | Promised date passed | 0 |
| Omkar ResidencyM/s OMKAR ASSOCIATES | P51700029285 | 18 May 2021 | 31 Dec 2025 | 31 Dec 2025 | Promised date passed | 0 |
| Ashlar TattvaAkshar Enterprises | P51700027399, PR1330002600631 | 8 Dec 2020 | 31 Dec 2029 | 30 Apr 2030 | Extended 4 mo | 0 |
| Nilgiri ResidencySai Vaishnavi Enterprises | P51700025000 | 18 Mar 2020 | 30 Jun 2023 | 30 Sep 2023 | Extended 3 mo | 0 |
| Ganraj HeightsShree Krishna Construction | P51700024552 | 18 Feb 2020 | 30 Dec 2024 | 30 Dec 2024 | Promised date passed | 0 |
| Venus HeightsVenus Infra | P51700023629 | 24 Dec 2019 | 30 Dec 2024 | 30 Dec 2027 | Extended 36 mo | 0 |
| Charms CityCharms Developers | P51700019699, P51700049561 | 22 Feb 2019 | 31 Dec 2028 | 30 Apr 2029 | Extended 4 mo | 0 |
Other localities in Kalyan
Most active promoters
By projects registered here, as named on MahaRERA.
- Charms Developers5 projects
- Abhilasha Venture2 projects
- Jayshree Builders2 projects
- Om Sai Residency2 projects
- Shree Jai Malhar Enterprises2 projects
- Adeshwar Associates1 project
- Akshar Enterprises1 project
- Arfa Construction1 project
- Avadhut Enterprise1 project
- Gurukripa Landholding LLP1 project
Data through15 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology