Manda, Thane
5 in 10 MahaRERA registrations here have pushed their completion date back.
RERA projects52
Registrations56some projects hold several
Completion still due1937 past their date
Median extension4 months48% of registrations extended
Regulatory cases1on 1 project
9 in 10 registrations run late here
56 MahaRERA registrations in Manda
1 completed4 not yet due15 extended, not yet due36 past even the latest date
Extended registrations moved their completion date by a median of 4 months.
Projects in Manda
52 projects registered with MahaRERA.
| Project | Delivery | Median ₹/sq ft | Booked |
|---|---|---|---|
| Om Sai Sankul COm Sai United | 4 yrs 9 mo late | — | 0% |
| Om Sai Residency NxOm Sai Residency | 3 yrs 10 mo late | — | — |
| Deep ArcadeSwayamdeep Reality | 3 yrs 10 mo late | — | 100% |
| Sai Shatabdi ResidencyPrarthana Enterprises | 5 yrs 10 mo late | — | — |
| amber apartmentshaikh nazir | 4 yrs 3 mo late | — | 96% |
| Om Shanti ResidencyOm Shanti Construction Company | 4 yrs 10 mo late | — | 46% |
| Yashwant ResidencyShree Sai Ganesh Enterprises | 7 yrs 10 mo late | — | 31% |
| Omkar HeightsSwati Enterprises | 8 yrs 10 mo late | — | 76% |
| Om Sai ResidencyOm Sai Residency | 8 yrs 10 mo late | — | 48% |
| Om Siddhivinayak ResidencyOm Siddhivinayak Enterprises | 6 yrs 10 mo late | — | 41% |
| Om Sai SankulOm Sai Constructions | 4 yrs 8 mo late | — | 34% |
| Hira ParkM/s Hira Housing Construction Co. | Due Oct 2027, extended 4 mo | — | 30% |
| IndrayaniNaresh Yashwant Patil | Due Oct 2026, extended 2 yrs 10 mo | — | 69% |
| Shreeman ResidencyOm Enterprises | Due Apr 2030, extended 4 mo | — | 17% |
| Sidheshwar Complex Building 1 A WingAdeshwar Associates | 8 yrs 10 mo late | — | 7% |
| Vedant VatikaSiddhivinayak Developers | 5 yrs 4 mo late | — | 55% |
| Siddheshwar HeightsShree Jai Malhar Enterprises | Completed | — | — |
| Mamta 1351Patil Group Builders And Developers | Due Dec 2026 | — | 53% |
| Rajeshwari ResidencyShree Siddhi Construction | 5 yrs 4 mo late | — | 27% |
| Charms City Phase IIGurukripa Landholding LLP | Due Mar 2027 | — | 43% |
| Panchamrut Bldg. No. 1Shree Abhilasha Nirmiti | 8 yrs 7 mo late | — | 27% |
| Om Sai ViharJai Mahalaxmi Enterprises | 8 yrs 5 mo late | — | 26% |
| Charms Heights Phase-II A1-A2Charms Developers | 7 yrs 7 mo late | — | 89% |
| Madhuban F1 F2Abhilasha Venture | 6 yrs 7 mo late | — | 54% |
| Charms Heights Phase-I B1-B4Charms Developers | 8 yrs 7 mo late | — | 96% |
Nearby: other localities in Kalyan
Dombivli · 405 projectsKalyandombivali (M Corp.) · 206 projectsKalyan · 140 projectsChikanghar · 108 projectsTitwala · 89 projectsKalyan-Dombivali (M Corp.) · 85 projectsKhoni · 71 projectsKatemanevali · 55 projectsTisgaon · 48 projectsGandhare · 44 projectsAdharwadi · 24 projectsPisavali · 24 projects
Most active promoters
- Charms Developers5 projects
- Abhilasha Venture2 projects
- Jayshree Builders2 projects
- Om Sai Residency2 projects
- Shree Jai Malhar Enterprises2 projects
- Adeshwar Associates1 project
- Akshar Enterprises1 project
- Arfa Construction1 project
- Avadhut Enterprise1 project
- Gurukripa Landholding LLP1 project
Data through21 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Methodology