Manda, Thane

5 in 10 MahaRERA registrations here have pushed their completion date back.

RERA projects52
Registrations56some projects hold several
Completion still due1937 past their date
Median extension4 months48% of registrations extended
Regulatory cases1on 1 project
Manda market reportPDF: prices and rents, volumes, projects ranked by deals and the most delayed — with the latest exact salesSee what's inside · from ₹1,999

9 in 10 registrations run late here

56 MahaRERA registrations in Manda

1 completed4 not yet due15 extended, not yet due36 past even the latest date

Extended registrations moved their completion date by a median of 4 months.

Projects in Manda

52 projects registered with MahaRERA.

ProjectDeliveryMedian ₹/sq ftBooked
Om Sai Sankul COm Sai United4 yrs 9 mo late—0%
Om Sai Residency NxOm Sai Residency3 yrs 10 mo late——
Deep ArcadeSwayamdeep Reality3 yrs 10 mo late—100%
Sai Shatabdi ResidencyPrarthana Enterprises5 yrs 10 mo late——
amber apartmentshaikh nazir4 yrs 3 mo late—96%
Om Shanti ResidencyOm Shanti Construction Company4 yrs 10 mo late—46%
Yashwant ResidencyShree Sai Ganesh Enterprises7 yrs 10 mo late—31%
Omkar HeightsSwati Enterprises8 yrs 10 mo late—76%
Om Sai ResidencyOm Sai Residency8 yrs 10 mo late—48%
Om Siddhivinayak ResidencyOm Siddhivinayak Enterprises6 yrs 10 mo late—41%
Om Sai SankulOm Sai Constructions4 yrs 8 mo late—34%
Hira ParkM/s Hira Housing Construction Co.Due Oct 2027, extended 4 mo—30%
IndrayaniNaresh Yashwant PatilDue Oct 2026, extended 2 yrs 10 mo—69%
Shreeman ResidencyOm EnterprisesDue Apr 2030, extended 4 mo—17%
Sidheshwar Complex Building 1 A WingAdeshwar Associates8 yrs 10 mo late—7%
Vedant VatikaSiddhivinayak Developers5 yrs 4 mo late—55%
Siddheshwar HeightsShree Jai Malhar EnterprisesCompleted——
Mamta 1351Patil Group Builders And DevelopersDue Dec 2026—53%
Rajeshwari ResidencyShree Siddhi Construction5 yrs 4 mo late—27%
Charms City Phase IIGurukripa Landholding LLPDue Mar 2027—43%
Panchamrut Bldg. No. 1Shree Abhilasha Nirmiti8 yrs 7 mo late—27%
Om Sai ViharJai Mahalaxmi Enterprises8 yrs 5 mo late—26%
Charms Heights Phase-II A1-A2Charms Developers7 yrs 7 mo late—89%
Madhuban F1 F2Abhilasha Venture6 yrs 7 mo late—54%
Charms Heights Phase-I B1-B4Charms Developers8 yrs 7 mo late—96%

Most active promoters

  1. Charms Developers5 projects
  2. Abhilasha Venture2 projects
  3. Jayshree Builders2 projects
  4. Om Sai Residency2 projects
  5. Shree Jai Malhar Enterprises2 projects
  6. Adeshwar Associates1 project
  7. Akshar Enterprises1 project
  8. Arfa Construction1 project
  9. Avadhut Enterprise1 project
  10. Gurukripa Landholding LLP1 project
Data through21 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Methodology