RERA projects in Kalyandombivali (M Corp.)
213 projects under 234 MahaRERA registrations, registered 2017–2025. 20% have a completion date extended beyond the one promised.
213RERA projects
234Registrationssome projects hold several
58Completion still due176 past their completion date
12 monthsMedian extension beyond promised date20% of registrations extended
40Regulatory caseson 33 projects
0Buildings on recordfrom registration certificates
Registrations per year
New MahaRERA registrations by registration date.
| Year | Registrations |
|---|---|
| 2017 | 83 |
| 2018 | 31 |
| 2019 | 17 |
| 2020 | 15 |
| 2021 | 18 |
| 2022 | 13 |
| 2023 | 20 |
| 2024 | 22 |
| 2025 | 15 |
Projects in Kalyandombivali (M Corp.)
213 projects registered with MahaRERA.
| Project | RERA | Registered | Promised completion | Revised completion | Timing | Cases |
|---|---|---|---|---|---|---|
| Prestige OneGirdhari Kalyandas Lulla | P51700080828 | 14 Jul 2025 | 31 Dec 2027 | — | Not yet due | 0 |
| Hamud OneHamud Parvez Moulvi | P51700080711 | 26 Jun 2025 | 31 Dec 2028 | — | Not yet due | 0 |
| Sai Nirmal ResidencySai Anant Enterprises | P51700080622 | 23 Jun 2025 | 31 Dec 2029 | — | Not yet due | 0 |
| Nav-Himalay Chs LtdShri Siddhi Builders and Developers | P51700080385 | 29 May 2025 | 31 Dec 2026 | — | Not yet due | 0 |
| Amber SpacesAmber Buildcon | P51700080151 | 2 May 2025 | 31 Dec 2027 | — | Not yet due | 0 |
| Balaram HeightsShree Samarth Krupa Enterprises | P51700079589 | 17 Mar 2025 | 30 Sep 2027 | — | Not yet due | 0 |
| Deepaswi HeightsYashlata Enterprises | P51700079634 | 17 Mar 2025 | 31 Dec 2027 | — | Not yet due | 0 |
| Subhash ResidencyAarav Group | P51700079631 | 17 Mar 2025 | 31 Mar 2028 | — | Not yet due | 0 |
| Nascon ParkviewSwaroop Developers | P51700079332 | 28 Feb 2025 | 31 Oct 2027 | — | Not yet due | 0 |
| Yashashree HeightsLotus Builders And Developers | P51700079342 | 28 Feb 2025 | 31 Dec 2027 | — | Not yet due | 0 |
| Sai Gokul ViharShree Sai Developers | P51700079127 | 6 Feb 2025 | 31 Dec 2028 | — | Not yet due | 0 |
| Shankheshwar PushpShree Shankheshwar Enterprises | P51700079074 | 3 Feb 2025 | 31 Mar 2027 | — | Not yet due | 0 |
| Maitreya ImperialSaish Group | P51700078872 | 17 Jan 2025 | 31 May 2025 | — | Promised date passed | 0 |
| Manakarnika CHS LtdAkshay Enterprises | P51700078653 | 1 Jan 2025 | 31 Dec 2027 | — | Not yet due | 0 |
| Hira-KrishnaShree Kesarinandan Developers | P51700078405 | 11 Dec 2024 | 31 Jul 2027 | — | Not yet due | 0 |
| Hanuman KutirThe Impressions | P51700078332 | 4 Dec 2024 | 30 Apr 2027 | — | Not yet due | 0 |
| FreesiaTirupati Builders | P51700078087 | 25 Nov 2024 | 31 Dec 2026 | — | Not yet due | 0 |
| Blue Ladder Business EnclaveBlue Ladder | P51700077657 | 17 Oct 2024 | 15 Aug 2028 | — | Not yet due | 0 |
| Amaira 2Pacific Excellence | P51700077452 | 16 Aug 2024 | 30 Apr 2027 | — | Not yet due | 0 |
| AmaraPlanacres Properties | P51700077405 | 13 Aug 2024 | 31 Dec 2026 | — | Not yet due | 0 |
| Pearl GalaxyPearlCorporates | P51700077302 | 6 Aug 2024 | 30 Dec 2026 | — | Not yet due | 0 |
| Indira GalaxyShree Developers | P51700077105 | 23 Jul 2024 | 31 Dec 2026 | — | Not yet due | 0 |
| Nirvana Gardens Phase 1 Wing A IvanaSqylines Builders LLP | P51700076843 | 28 Jun 2024 | 31 Jul 2028 | — | Not yet due | 0 |
| NarmadeshwarAshapura Combines | P51700066563 | 11 Jun 2024 | 31 Dec 2030 | — | Not yet due | 0 |
| Nirvana Gardens Phase 3 Wing C IVYSqylines Builders LLP | P51700066500 | 11 Jun 2024 | 31 Mar 2029 | — | Not yet due | 0 |
| Raja Dasrath Co- Operative Housing SocietyShree Saish Group | P51700056247 | 22 May 2024 | 31 Dec 2027 | — | Not yet due | 0 |
| Satyam Chopra EnclaveSai Satyam Properties LLP | P51700056086 | 10 May 2024 | 31 Mar 2027 | — | Not yet due | 0 |
| Shankheshwar PristineShankheshwar Kreaters | P51700055853 | 23 Apr 2024 | 31 Dec 2028 | — | Not yet due | 0 |
| Mangalmurti GardenShivam Universal | P51700055757 | 16 Apr 2024 | 31 Dec 2026 | — | Not yet due | 0 |
| Raj Empires Building No.2Raj Pritam Chaturvedi | P51700055768 | 16 Apr 2024 | 31 Mar 2027 | — | Not yet due | 0 |
| Yash MidtownYash Realty | P51700055547 | 2 Apr 2024 | 31 Dec 2028 | — | Not yet due | 0 |
| Mangalmurti ParadiseShubham Construction | P51700055074 | 29 Feb 2024 | 31 Dec 2026 | — | Not yet due | 0 |
| Atmaram HeightsVidhi Enterprises | P51700054934 | 21 Feb 2024 | 30 Jun 2027 | — | Not yet due | 0 |
| BileshwarAshapura Combines | P51700054702 | 6 Feb 2024 | 31 Dec 2028 | — | Not yet due | 0 |
| Fatima SkyLfka Builders And Developers | P51700054322 | 15 Jan 2024 | 31 Dec 2027 | — | Not yet due | 0 |
| Swara EmeraldM/S Samarth Savli Homes | P51700054245 | 10 Jan 2024 | 30 Nov 2025 | — | Promised date passed | 0 |
| Vishwanath DarshanAshapura Combines | P51700054131 | 29 Dec 2023 | 31 Dec 2029 | — | Not yet due | 0 |
| Ashapura GoldAshapura Buildtech | P51700054118 | 27 Dec 2023 | 31 Dec 2027 | — | Not yet due | 0 |
| Vinayak PreranaNakshatra Group | P51700053644 | 21 Nov 2023 | 30 Sep 2026 | — | Promised date passed | 0 |
| Sunteck Crescent ParkSunteck Property Holdings Private Limited | P51700053312, P51700053439 | 27 Oct 2023 | 31 Dec 2031 | — | Not yet due | 0 |
| Shreerang KutirShree Prabha Construction | P51700052997 | 10 Oct 2023 | 1 Jun 2026 | — | Promised date passed | 0 |
| Sumati SkylineSubhash Skyline Infra | P51700052640 | 15 Sep 2023 | 30 Sep 2026 | — | Promised date passed | 0 |
| Mangalmurti PrideSai Mauli Enterprises | P51700052588 | 11 Sep 2023 | 31 Dec 2026 | — | Not yet due | 0 |
| Nandadeep CHS LtdAditya Buildcon | P51700052450 | 8 Sep 2023 | 31 Mar 2028 | — | Not yet due | 0 |
| Gayatri Sankul NxGayatri Builders | P51700052224 | 31 Jul 2023 | 31 Dec 2027 | — | Not yet due | 0 |
| Seasons GreenJai Balaji Sai Realtors | P51700051575 | 27 Jun 2023 | 31 Dec 2027 | — | Not yet due | 0 |
| Metro LuxuriaNivara Engineers | P51700051410 | 8 Jun 2023 | 31 Dec 2027 | — | Not yet due | 0 |
| Shree Ram Radha DamodarAditya Buildcon | P51700050634 | 21 Apr 2023 | 31 Mar 2026 | — | Promised date passed | 0 |
| Lucky HeightLfka Builders And Developers | P51700050303 | 1 Apr 2023 | 31 Dec 2025 | — | Promised date passed | 0 |
| Sd GalaxySomeshwarnath Developers & Builders | P51700049857 | 6 Mar 2023 | 31 Dec 2027 | — | Not yet due | 0 |
| Yashlata PalacePradeep Shyam Kharbade | P51700049915 | 6 Mar 2023 | 31 Dec 2024 | — | Promised date passed | 0 |
| Swami ChetanaOm Sai Builders And Developers | P51700049740 | 24 Feb 2023 | 30 Apr 2025 | 31 Dec 2026 | Extended 20 mo | 0 |
| Gaurang ApartmentGanesha Developers | P51700048961 | 24 Jan 2023 | 31 Dec 2024 | 31 Dec 2025 | Extended 12 mo | 0 |
| Vastu HeritageMinakshi Developers | P51700048963 | 24 Jan 2023 | 31 Dec 2026 | — | Not yet due | 0 |
| Ritz Phase II Commercial Tower DVikas Harakchand Jain | P51700047423 | 27 Oct 2022 | 30 Sep 2026 | — | Promised date passed | 0 |
| Saras ResidencyBalaji Group Builders & Developers | P51700047251 | 13 Oct 2022 | 30 Dec 2027 | — | Not yet due | 0 |
| Shree Kacharnath CHS LtdAmogh Associates | P51700047049 | 27 Sep 2022 | 31 Dec 2024 | — | Promised date passed | 0 |
| Ameya EnclaveAtharv Realty | P51700045792 | 9 Jun 2022 | 31 Dec 2025 | — | Promised date passed | 0 |
| VighnahartaJd Aasociations | P51700045497 | 24 May 2022 | 30 Apr 2026 | — | Promised date passed | 0 |
| Amina Bi Inamdar TowerRoyal Infra | P51700045213 | 10 May 2022 | 31 Mar 2024 | — | Promised date passed | 0 |
| Tanishka ResidencyAnmol Developers | P51700035151 | 10 May 2022 | 15 Jan 2023 | — | Promised date passed | 0 |
| Nascon InspireVighnaharta Developers | P51700034385 | 5 Apr 2022 | 31 Dec 2024 | 31 Dec 2025 | Extended 12 mo | 0 |
| Seasons SaffronSeasons Sai Developers | P51700034231 | 25 Mar 2022 | 31 Dec 2026 | — | Not yet due | 0 |
| Ayesha GardenAzka Builders And Developers | P51700033810, P51700033816 | 8 Mar 2022 | 31 Dec 2024 | 30 Sep 2025 | Extended 9 mo | 0 |
| Mahalaxmi InfrastructureMahalaxmi Infrastructure | P51700033683 | 2 Mar 2022 | 31 Dec 2024 | — | Promised date passed | 0 |
| Laiba HeightsLfka Builders And Developers | P51700032899 | 2 Feb 2022 | 30 Jun 2024 | 31 Dec 2027 | Extended 42 mo | 0 |
| New Krishna BuildingRamniklal Hiralal Tanna | P51700031870 | 22 Nov 2021 | 31 Dec 2021 | — | Promised date passed | 0 |
| Regency LuxuriaRegency Nirman Ltd | P51700031251, P51700053314, P51700078991 | 15 Oct 2021 | 30 Jun 2028 | 31 Dec 2025 | Not yet due | 0 |
| Triveni ClassicTriveni Lifestyle Developers LLP | P51700030951 | 29 Sep 2021 | 30 Jun 2024 | — | Promised date passed | 0 |
| Gani HeightsNasim Niyaz Khan | P51700030519 | 30 Aug 2021 | 23 Aug 2023 | — | Promised date passed | 0 |
| Silver HeightsSulbha Enterprises | P51700030528 | 30 Aug 2021 | 31 Dec 2025 | — | Promised date passed | 0 |
| Sarvoday SymphonySwastik Realtors | P51700030468 | 25 Aug 2021 | 30 Jun 2026 | — | Promised date passed | 0 |
| Rock Mount ResidencyBuilt Charms | P51700030383 | 17 Aug 2021 | 30 Jun 2026 | — | Promised date passed | 0 |
| Sundar Residency F WingNavaditya Developers | P51700030083 | 29 Jul 2021 | 31 Dec 2024 | — | Promised date passed | 0 |
| Shree Mangal Narayan ResidencyN V Construction | P51700030047 | 26 Jul 2021 | 31 Dec 2023 | 31 Dec 2025 | Extended 24 mo | 0 |
| Mangeshi SohanMangeshi And Deveshwar Developers | P51700029848 | 8 Jul 2021 | 9 Mar 2026 | — | Promised date passed | 0 |
| Shankheshwar PlatinaShankheshwar Kreaters | P51700029221 | 10 May 2021 | 31 Mar 2025 | — | Promised date passed | 0 |
| Soham GarimaJitendra Shivaji Patil | P51700028836 | 5 Apr 2021 | 5 Oct 2024 | 31 Mar 2025 | Extended 5 mo | 0 |
| Ashtavinayak EnterprisesAnil Gemu Chavan | P51700028336 | 18 Feb 2021 | 1 Apr 2024 | — | Promised date passed | 0 |
| Shree Ram NiwasShree Ganadhish Homes | P51700028260 | 18 Feb 2021 | 30 Jun 2025 | — | Promised date passed | 0 |
| Srushti Residency Building EPappu Developers & Group | P51700028176 | 10 Feb 2021 | 30 Jun 2024 | — | Promised date passed | 0 |
| Shiv Malhar DevelopersManesh Vasant Malusare | P51700028002 | 25 Jan 2021 | 1 Apr 2024 | — | Promised date passed | 0 |
| Amber OneAmber Buildcon | P51700027251 | 26 Nov 2020 | 30 Jun 2028 | — | Not yet due | 0 |
| Vishwajeet Soman CentralShrestha Construction Company | P51700027075 | 13 Nov 2020 | 30 Jun 2025 | — | Promised date passed | 0 |
| Arya and IraMahima Infra Estates LLP | P51700026854 | 31 Oct 2020 | 30 Dec 2022 | — | Promised date passed | 0 |
| Sai Vandana Builders And DevelopersSai Vandana Builders And Developers | P51700026776 | 25 Oct 2020 | 28 Feb 2025 | — | Promised date passed | 0 |
| RitzVikas Harakchand Jain | P51700026485, P51700029726 | 25 Sep 2020 | 30 Jun 2024 | — | Promised date passed | 0 |
| Maatr WatersMaatr Enterprises | P51700026313 | 7 Sep 2020 | 30 Sep 2023 | — | Promised date passed | 0 |
| Jivan Safalya Chs LtdJ B Constructions | P51700026262 | 2 Sep 2020 | 30 May 2023 | — | Promised date passed | 0 |
| Pritam SolitaireJayesh Pramodbhai Thakkar | P51700025554 | 28 Jun 2020 | 30 Dec 2025 | — | Promised date passed | 0 |
| Surya ComplexM/S. Jai Santoshi Maa Enterprises | P51700025010 | 18 Mar 2020 | 30 Jun 2023 | — | Promised date passed | 0 |
| Mangeshi Dazzle IIKalyan Development Corporation | P51700024511 | 18 Feb 2020 | 30 Dec 2028 | — | Not yet due | 0 |
| Virat GrandeurDeiv Enterprises | P51700024245 | 29 Jan 2020 | 30 Dec 2025 | — | Promised date passed | 0 |
| Anand Homes Wing DShrinath Developers | P51700024095 | 20 Jan 2020 | 30 Dec 2023 | — | Promised date passed | 0 |
| Tharwani MajesticAnil Hardasmal Tharwani | P51700023841, P51700023872 | 7 Jan 2020 | 30 Dec 2026 | — | Not yet due | 0 |
| Shree Sai Darshan Bulding 2Shree Siddhivinayak Builders & Developers | P51700023486 | 18 Dec 2019 | 30 May 2024 | — | Promised date passed | 0 |
| Balaji DarshanBalaji Builders And Developers | P51700023018 | 14 Nov 2019 | 30 Mar 2023 | — | Promised date passed | 0 |
| Sai HeightsAaradhana Construction | P51700022628 | 9 Oct 2019 | 1 Aug 2026 | — | Promised date passed | 0 |
| Triveni Majesta B WingTriveni Lifestyle Developers LLP | P51700021897 | 8 Aug 2019 | 30 Jun 2023 | — | Promised date passed | 0 |
| Yashvi ResidencyPatel & Co. | P51700021794 | 29 Jul 2019 | 30 Dec 2022 | 30 Jun 2024 | Extended 18 mo | 0 |
Other localities in Kalyan
- Dombivli404 projects
- Kalyan137 projects
- Chikanghar107 projects
- Titwala89 projects
- Kalyan-Dombivali (M Corp.)78 projects
- Khoni71 projects
- Katemanevali55 projects
- Manda52 projects
- Tisgaon48 projects
- Gandhare43 projects
- Adharwadi24 projects
- Pisavali24 projects
Most active promoters
By projects registered here, as named on MahaRERA.
- Neptune Developers Limited18 projects
- Neptune Developers Ltd15 projects
- Lfka Builders And Developers5 projects
- Ashapura Combines3 projects
- Shankheshwar Kreaters3 projects
- Aditya Buildcon2 projects
- Amber Buildcon2 projects
- Anjana Sahebrao Chavan2 projects
- Deiv Enterprises2 projects
- Ganesha Developers2 projects
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology