Deedo IDDL-THN-KALYANDOMBIVALI10 in 10 MahaRERA registrations here run late: their completion date was extended or has passed.
RERA projects151
Registrations161some projects hold several
Completion still due39122 past their date
Median extension4 months39% of registrations extended
Regulatory cases36on 29 projects
10 in 10 registrations run late here
161 MahaRERA registrations in Kalyandombivali (M Corp.)
8 not yet due31 extended, not yet due122 past even the latest date
Extended registrations moved their completion date by a median of 4 months.
Projects in Kalyandombivali (M Corp.)
151 projects registered with MahaRERA.
| Project | Delivery | Median ₹/sq ft | Booked |
|---|---|---|---|
| Prestige OneGirdhari Kalyandas Lulla | Due Apr 2028, extended 4 mo | — | — |
| Hamud OneHamud Parvez Moulvi | Due Apr 2029, extended 4 mo | — | — |
| Sai Nirmal ResidencySai Anant Enterprises | Due Apr 2030, extended 4 mo | — | — |
| Nav-Himalay Chs LtdShri Siddhi Builders and Developers | Due Apr 2027, extended 4 mo | — | — |
| Amber SpacesAmber Buildcon | Due Apr 2028, extended 4 mo | — | — |
Nearby: other municipal areas in Kalyan
Most active promoters
- Neptune Developers Limited29 projects
- Lfka Builders And Developers5 projects
- Ashapura Combines3 projects
- Aditya Buildcon2 projects
- Ganesha Developers2 projects
- Kalyan Development Corporation2 projects
- Pappu Developers & Group2 projects
- Shree Shankheshwar Enterprises2 projects
- Shree Siddhivinayak Builders & Developers2 projects
- Triveni Lifestyle Developers Llp2 projects
Kalyandombivali (M Corp.), in questions
How many projects in Kalyandombivali (M Corp.) run late?
10 in 10 MahaRERA registrations (153 of 161): their completion date was extended or has passed, data through 14 Nov 2026.
Where does this data come from?
From registered documents (Index II) at the Maharashtra sub-registrar offices and MahaRERA's project records, matched to Kalyandombivali (M Corp.) by Deedo. Medians on fewer than 3 deeds are not shown.
Data through14 Nov 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and orders; IGR Maharashtra Index IIExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated. Medians on fewer than 3 deeds are not shown.Report a problemMethodology