Completion was pushed back 4 months, to Apr 2029; no MahaRERA orders on record; 0% of its units are booked.

Kalyandombivali (M Corp.), Thane 421301 · by Hamud Parvez Moulvi

DeliveryExtended 4 moPromised Dec 2028 · now due Apr 2029RegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales0% booked0 of 40 units · as the promoter reported to MahaRERA

Buying a flat here?

See every deed registered on it.

Completion was pushed back 4 months, to Apr 2029

  • This projectRegistered 26 Jun 2025, completion promised 31 Dec 2028, revised to 30 Apr 2029.

No extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales, rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

The building

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP51700080711
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5170008071126 Jun 202531 Dec 202830 Apr 2029Hamud Parvez MoulviProject page
Documents47

1 document held by Deedo, 46 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN CardPan.pdf · uploaded 31 Mar 2024Source
  • Other – Financeself declaration landowner.pdf · uploaded 19 Jun 2025Source

Legal

  • Declaration Form Bform b hamud one bldr.pdf · uploaded 5 Mar 2025Source
  • Other – Legalhamud one deviation allotment.pdf · uploaded 25 Mar 2025Source
  • Other – LegalQuery Clarification signed.pdf · uploaded 25 Mar 2025Source
  • Legal Title reportTitle updated.pdf · uploaded 25 Mar 2025Source

Migrated

  • 1 PAN CardPan.pdf · uploaded 31 Mar 2024Source
Show all 47 documentsShow fewer documents

Migrated

  • 1 Copy of Layout Approval (in case of layout)Sanction Plan Page 1 of 2_compressed.pdf · uploaded 31 Mar 2024Source
  • 2 Copy of Layout Approval (in case of layout)Sanction Plan Page 2 of 2.pdf · uploaded 31 Mar 2024Source
  • 1 Commencement Certificates / NA Order for plotted developmentCommencement Certificate.pdf · uploaded 31 Mar 2024Source
  • 1 Building Plan Approval / NA Order for plotted developmentSanction Plan Page 2 of 2.pdf · uploaded 31 Mar 2024Source
  • 1 Declaration about Commencement Certificatedeclaration about commencement.pdf · uploaded 31 Mar 2024Source
  • 1 CERSAI detailsCERSAI_Search_Report_200302681372_For_Asset_Based_Search_31_03_2024_22_59_21_909.pdf · uploaded 31 Mar 2024Source
  • 2 CERSAI detailscersai undertaking hamud.pdf · uploaded 31 Mar 2024Source
  • 1 Other – TechnicalEmail by KDMC.pdf · uploaded 31 Mar 2024Source
  • 2 Other – Technicalcredai mchi membership certificate.pdf · uploaded 31 Mar 2024Source
  • 1 Disclosure of Interest in Other Real Estate Organizationsdisclosure of interest .pdf · uploaded 31 Mar 2024Source
  • 1 a Details of encumbrances concerned to Financehamud one financial encumbrance.pdf · uploaded 5 Mar 2025Source
  • 2 a Details of encumbrances concerned to Financehamud one legal encumbrance.pdf · uploaded 5 Mar 2025Source
  • 1 Declaration in FORM Bform b hamud one bldr.pdf · uploaded 5 Mar 2025Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)hamud one architect certificate.pdf · uploaded 5 Mar 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)hamud one engineer certificate.pdf · uploaded 5 Mar 2025Source
  • 1 Deviation Report with respect to Allotment letterhamud one deviation allotment.pdf · uploaded 5 Mar 2025Source
  • 1 b Details of encumbrances concerned to Legalhamud one financial encumbrance.pdf · uploaded 5 Mar 2025Source
  • 2 b Details of encumbrances concerned to Legalhamud one legal encumbrance.pdf · uploaded 5 Mar 2025Source
  • 1 Deviation Report with respect to model copy of Agreementhamud one deviation afs.pdf · uploaded 5 Mar 2025Source
  • 1 Proforma of Agreement for saleRERA Flat Sale (Hamud One)-Revised.pdf · uploaded 18 Mar 2025Source
  • 1 Copy of the legal title reportTitle updated.pdf · uploaded 25 Mar 2025Source
  • 1 Proforma of Allotment letterRera Allotment updated with parking and bank ac clause as per circular 60.pdf · uploaded 25 Mar 2025Source
  • 1 Other – Legalhamud one deviation allotment.pdf · uploaded 25 Mar 2025Source
  • 2 Other – LegalQuery Clarification signed.pdf · uploaded 25 Mar 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)RERA form 3 sign by promoter.pdf · uploaded 7 Apr 2025Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)clarification.pdf · uploaded 7 Apr 2025Source
  • 3 Other – Technicalannexure a hamudone.pdf · uploaded 27 May 2025Source
  • 1 Declaration about all RERA Designated Bank Accounts (Format A)format a separate ac new format.pdf · uploaded 6 Jun 2025Source
  • 1 Disclosure for secured/unsecured finance availed for the projectdisclosure for secured unsecured finance.pdf · uploaded 6 Jun 2025Source
  • 1 Other – Financeself declaration landowner.pdf · uploaded 19 Jun 2025Source
  • 1 Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)format B bank as per nomenclature.pdf · uploaded 19 Jun 2025Source

Technical

  • DocumentSanction Plan Page 1 of 2_compressed.pdf · uploaded 31 Mar 2024Source
  • DocumentSanction Plan Page 2 of 2.pdf · uploaded 31 Mar 2024Source
  • DocumentSanction Plan Page 2 of 2.pdf · uploaded 31 Mar 2024Source
  • Other – TechnicalEmail by KDMC.pdf · uploaded 31 Mar 2024Source
  • Other – Technicalcredai mchi membership certificate.pdf · uploaded 31 Mar 2024Source
  • Other – Technicalannexure a hamudone.pdf · uploaded 27 May 2025Source

Technical (Architect)

  • Documenthamud one architect certificate.pdf · uploaded 5 Mar 2025Source

Technical (Engineer)

  • Documenthamud one engineer certificate.pdf · uploaded 5 Mar 2025Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvalsLand parcel 294/1/D, CTS NO. 3475/C/2

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Unit types
2BHK, 2BHK Landowner, 3BHK, 3BHK Landowner, Office Landowner, Shop, Shop Landowner40 units in all
Address
CTS NO. 3475/C/2, SURVEY NO. 294/1/A, 294/1/D, Hamud One Road, Near Kalsekar English High School, Opp. KDMC Ground, Kalyan WestPIN 421301
Village
Kalyan-Dombivali (M Corp.), Kalyan taluka
Land area for this project
1,634 sq m (17,592 sq ft)
Permissible built-up area
8,521 sq m (91,723 sq ft)
Sanctioned built-up area
3,521 sq m (37,903 sq ft)
Recreational open space
0 sq m (0 sq ft)
Designated bank account
76
Developed in phases
No

Survey, CTS, gat or plot numbers

294/1/DCTS NO. 3475/C/2SURVEY NO. 294/1/A

Land as published on MahaRERA's project page

CTS NO. 3475/C/2,SURVEY NO. 294/1/A, 294/1/D

Boundaries

North
Asra Foundations Kalsekar English High School
South
Cts No 3479
East
Shed And Old Building
West
12 Meters Road

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking40 units

0 of 40 units booked (0%), as the promoter reported to MahaRERA

2BHK · 25 units2BHK Landowner · 1 unit3BHK · 5 units3BHK Landowner · 4 unitsOffice Landowner · 1 unitShop · 3 unitsShop Landowner · 1 unit
TypeCarpet areaUnitsBooked
2BHK47.1 sq m · 507 sq ft80
2BHK47.26 sq m · 509 sq ft90
2BHK48.61 sq m · 523 sq ft80
2BHK Landowner47.1 sq m · 507 sq ft10
3BHK66.59 sq m · 717 sq ft50
3BHK Landowner66.59 sq m · 717 sq ft40
Office Landowner13.3 sq m · 143 sq ft10
Shop11.74 sq m · 126 sq ft10
Show all 11 unit rowsShow fewer unit rows
TypeCarpet areaUnitsBooked
Shop13.03 sq m · 140 sq ft10
Shop19.8 sq m · 213 sq ft10
Shop Landowner14.61 sq m · 157 sq ft10

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals4

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectShirish G Nachane—
Chartered accountantMandavia And Associates—
Chartered accountantMemon And Co—
EngineerAssociated Structural Engineers LLP Through Swapnil Shete—

Source: MahaRERA project page. Contact details are not shown.

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Report a problemMethodology